Whitehall Township

Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Whitehall Township.

pending · Whitehall Township
Would establish zoning and operating standards for data centers in Whitehall Township, including limits on building size, height, and site coverage.Proposed data-center zoning amendment (ordinance; not yet enacted)

What this means

The proposed rules would add meaningful limits: for example, 40% maximum building coverage and a 50-foot height limit, plus environmental design requirements. They could constrain or add cost to projects, but the sources don’t describe a ban or enough operational limits to suggest a more severe barrier; the ordinance was still only at its first hearing.

Restrictions & requirementsHide restrictions & requirements7
  • Data centers must be designed or arranged to avoid detrimental effects on high-value streams, wetlands, floodplains, steep slopes, and other environmentally sensitive areas. Avoid detrimental impacts to environmentally sensitive areas

  • Data centers must be arranged to minimize disturbance to natural, unimproved land and encourage preservation of mature trees and wooded areas. Minimize disturbances to natural and unimproved land

  • The ordinance establishes a minimum lot size for data center uses; the provided source does not state the threshold. Minimum lot size

  • The ordinance establishes minimum setbacks for data centers; the provided source does not state the distances. Minimum setback requirements

  • Building coverage for data center uses is capped at 40%. Maximum building coverage of 40%

  • Data center buildings are limited to a maximum height of 50 feet. Maximum building height of 50 feet

  • Impervious coverage for data center uses is capped at 70%. Maximum impervious coverage at 70%

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data