White Deer Township

Anti-Data Center Policies

White Deer Township allows data centers by right in its Commercial Manufacturing District, but requires studies of noise, water, power and emergency response, noise testing, and 200-foot setbacks from certain uses.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · White Deer Township
Allows data centers in White Deer Township’s Commercial Manufacturing District, subject to requirements for setbacks, landscaping, noise, water and power supply, emergency planning, building design, and parking.White Deer Township data center zoning ordinance amendment

What this means

The measure allows data centers by right in the Commercial Manufacturing District, which makes them possible there without a special-use approval (permitted by right). But projects face meaningful costs and limits, including 200-foot setbacks from certain uses and required studies of noise, water, power, and emergency response (setback and study requirements).

People behind it

  • Township Solicitor who presented the revised ordinance draft and was directed to submit it for County and Planning Commission review.

  • Moved to adopt Ordinance No. 82 and seconded the motion to advance the draft for review.

  • Seconded the motion to adopt Ordinance No. 82 and moved to advance the draft for review.

Restrictions & requirementsHide restrictions & requirements13
  • Data centers are allowed by right only in the Commercial Manufacturing Zoning District, and only when approved under the section’s procedures and standards. permitted by right in the Commercial Manufacturing Zoning District

  • A data center’s maximum building height is 60 feet, including roof-mounted equipment; accessory uses may not exceed the principal building’s height. maximum building height for a Data Center

  • Data centers and their accessory uses must be set back 200 feet from Village or Rural Residential District boundaries and from the lot line of any property developed with a sensitive receptor. set back two hundred (200’) feet

  • A landscape buffer at least 25 feet wide is required next to Village or Rural Residential Districts, sensitive receptors, or public roadways, with specified native trees and shrubs. The Supervisors may count existing vegetation or topography toward the buffer if the stated review supports it. landscape buffer is required

  • Cooling, ventilation, and power-supply equipment within 300 feet of a public roadway, Village or Rural Residential District, or sensitive-receptor lot line must be fully enclosed. If that is mechanically infeasible, it must be screened by one of the listed methods. Roadway-facing fencing may not be chain-link or use barbed wire or similar visibly intrusive deterrents, unless screened as allowed. must be fully enclosed

  • Applicants must provide professional sound studies demonstrating limits of 67 dB(A) during weekday daytime hours and 57 dB(A) at night and on weekends, measured at the property line. Studies are required during land development review, building-permit review, and six months after the certificate of occupancy; later studies may also be required. The limits do not apply during power outages, but studies must report anticipated levels with emergency generators running. A qualified professional must also show that vibration will not be perceptible beyond the property line. maximum daytime

  • For public water, the applicant must submit certification that the authority will supply the needed water. For nonpublic water, a feasibility study must assess supply and effects on nearby wells and waters; approval is barred unless the study finds adequate yield and no adverse effect on nearby water quantity or quality. water feasibility study

  • Projects must provide proof of Susquehanna River Basin Commission review and approval if withdrawals average at least 100,000 gallons per day over 30 days, or consumptive use averages at least 20,000 gallons per day over 30 days. Water withdrawals

  • Applicants must demonstrate that wastewater disposal—including domestic wastewater and water used for cooling or industrial purposes—has been provided and approved by the Township Sewage Enforcement Officer and/or Pennsylvania DEP. adequate means of wastewater disposal

  • For a grid connection, applicants must provide the electric provider’s certification that capacity is available and service will be provided, and identify known project impacts on electric rates or availability for other uses. On-site generation for normal operations is treated as a separate use and requires approval under the zoning rules for that use. necessary capacity is available

  • Applicants must submit an Emergency Response Plan for review and acceptance by local fire and emergency-management services during land development. It must address emergency procedures, access, responder training, and annual professional fire-safety inspections. Battery or other energy-storage systems must comply with NFPA 855 or similar standards and include storage-specific fire suppression; approval requires sufficiently protective emergency procedures. Emergency Response Plan

  • Building façades facing a road, Village or Rural Residential District, or existing residential use must include at least two specified design elements for every 150 horizontal feet. at least two of the following design elements

  • Parking must be provided at the lesser of one space per 8,000 square feet of floor area intended for regular employee access or one space per employee on the maximum shift. whichever is lesser

Benefits & exceptionsHide benefits & exceptions7
  • Data centers are permitted by right in the Commercial Manufacturing Zoning District, subject to the section’s procedures and standards. permitted by right

  • The ordinance allows data center buildings up to 60 feet tall, including roof-mounted equipment; accessory uses may be as tall as the principal building. maximum building height

  • Existing topography or vegetation may count for all or part of the required landscape buffer if the Board of Supervisors so determines, upon recommendations from the Township Engineer and Planning Commission. existing topography and/or vegetation

  • If equipment cannot mechanically be fully enclosed based on manufacturer specifications, it may instead be screened using specified alternatives, including the landscape buffer, existing vegetation, buildings, a berm, or a solid screen. not mechanically feasible

  • Roadway fencing need not meet the stated restriction on chain-link or visibly intrusive deterrents when it is fully screened by an allowed screening method. fully screened from view

  • Parking is set at one space per 8,000 square feet of employee-accessible floor area or one space per employee on the maximum shift, whichever is less. whichever is lesser

  • The specified maximum sound limits do not apply during power outages, although sound studies must report anticipated levels when all emergency power-generation equipment is running. shall not apply during times of power outage

Sources

current law · White Deer Township
Data centers must be set back 200 feet from homes, schools, parks, and other sensitive uses, are limited to 67 dBA by day and 57 dBA at night at the property line, and require sound studies before and after construction, a vibration study, utility confirmation of power capacity, and an emergency response plan reviewed by the fire department.White Deer Township, Union County — data-center ordinance (No. 82)

What this means

The measure imposes technical studies and utility checks, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements19
  • Permitted by right, § 449(1)

  • 60 ft maximum, including roof-mounted cooling and ventilation equipment, § 449(3)(a)

  • 67 dBA weekday daytime and 57 dBA at night and on weekends at the property line, § 449(6)(a)

  • Section 449(6)(a)(1) to (3) requires preliminary, interim, and as-built sound studies using ANSI S1.4 sound level meters, with the as-built study six months after the certificate of occupancy, but the limits apply to normal operations and no study is required at full operating load.

  • Water feasibility study required where the use relies on nonpublic water, with Susquehanna River Basin Commission approval above set withdrawals, § 449(7)(b) and (c)

  • The feasibility study must describe how water will be used, including for cooling, but only for nonpublic water, § 449(7)(b)(3)

  • Projected water demand disclosed in the feasibility study, § 449(7)(b)(1)

  • Section 449(7)(d) requires the applicant to demonstrate that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Sewage Enforcement Officer or DEP, but does not state that the approval must be in hand before the zoning permit.

  • Utility certification of available capacity required; no third-party electrical inspection, § 449(8)(a).

  • On-site generation is a separate use with its own zoning approval, § 449(8)(b).

  • Power supply equipment within 300 ft of roads, residential districts, or sensitive receptors must be enclosed or screened, § 449(5)(a)

  • Known impacts on electric rates must be noted; no duty to pay for grid upgrades, § 449(8)(a)

  • 25 ft planted buffer next to residential districts, sensitive receptors, and public roads, § 449(4)

  • Equipment within 300 ft of roads, residential districts, or sensitive receptors enclosed or screened, § 449(5)(a)

  • Emergency Response Plan reviewed by the fire department and emergency services; no annual updates, radio coverage, or posted contacts, § 449(9)(a)

  • Plan must ensure first responders receive training, cost not assigned, § 449(9)(a)(4)

  • Annual fire safety inspections; no third-party electrical inspection before occupancy, § 449(9)(a)(5)

  • As-built sound study after opening, with later studies at the Township's option, § 449(6)(a)(3)

  • A failed as-built sound study is a violation of the ordinance, § 449(6)(a)(3)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Permitted by right in the Commercial Manufacturing District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data