Wharton Township
Anti-Data Center Policies
Wharton township does not specifically regulate data centers; in the B-2 district, an unlisted use generally needs special-exception approval and must meet lot-size, setback, and permit requirements. The ordinance does not ban data centers or set data-center-specific operating rules.
current law · Wharton TownshipDoes not specifically regulate data centers; they would be subject to the township’s general zoning and permitting rules.N/A — No data center-specific laws or bans identified for Wharton, Pennsylvania
What this means
The ordinance does not specifically address data centers, so an unlisted use would generally need special-exception approval in the B-2 district, rather than being freely allowed (unlisted uses). B-2 also has minimum lot-size, setback, and permit requirements, creating real approval steps and costs, but the ordinance does not ban data centers or impose data-center-specific operating rules.}
People behind it
- Board of Supervisors
Enacted the ordinance and is responsible for specified approvals and amendments.
- Zoning Officer
Administers and enforces the ordinance, reviews permit applications, and issues or refers permits.
- Zoning Hearing Board
Hears and decides matters assigned under the ordinance, including special exceptions, variances, and appeals.
Show 1 more peopleShow fewer people
- Planning Commission
Reviews specified applications and proposals and makes recommendations to the Board of Supervisors or Zoning Hearing Board.
Restrictions & requirementsHide restrictions & requirements6
A data center is not expressly listed as a permitted use. If treated as an unlisted use, the ordinance directs that it be handled as a special exception in the B-2 district, rather than as a by-right use. Unlisted uses are deemed special exceptions in B-2.
A special exception requires Zoning Hearing Board approval after a public hearing. The Board may impose conditions, including setbacks, screening, limits on nuisances and operating hours; it must consider neighborhood effects and traffic, and abutting owners must be notified. The Board may impose reasonable conditions and safeguards.
For a data center located in B-2, district standards include a minimum 2-acre lot, 200-foot minimum lot width, 60-foot front setback, 30-foot side and rear setbacks, and a 35-foot building-height limit, subject to stated exceptions. Minimum lot area for any use in this district is two acres.
A zoning permit is required before new construction, structural alteration, development, or a change in use. Applications require a sketch plan; any necessary sewage permit must be obtained before applying, and the zoning permit is issued only after compliance with applicable codes and ordinances is determined. Persons desiring to undertake any new construction.
Permit and application deadlines can constrain project timing: an application is generally deemed abandoned after six months unless diligently pursued or a permit is issued; a zoning permit expires after 12 months; and a special-exception authorization may be rescinded if the necessary permits are not obtained or work does not begin within 12 months. An application for a permit ... shall be deemed to have been abandoned six months.
The Township may charge zoning-permit and administration fees, with amounts set by resolution of the Supervisors. Fees for permits and administration.
Benefits & exceptionsHide benefits & exceptions1
A use not specifically authorized in any district is treated as a special-exception use in the B-2 Industrial Business District, providing a possible approval route for an unlisted use such as a data center if it qualifies. Approval is not automatic: the Zoning Hearing Board must grant the special exception. Unlisted uses are deemed special exceptions in B-2
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data