Westfall Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Westfall Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Westfall TownshipProposes allowing data centers only in C-2 and C-3 districts, subject to limits and requirements for height, setbacks, fire protection, and decommissioning; the draft has not been adopted.Westfall Township proposed data-center moratorium and draft zoning ordinance
What this means
The draft would allow data centers only in C-2 and C-3 districts and bar them in several others, sharply limiting where they could be built (allowed districts). It also proposes costs for required studies, fire-protection equipment, infrastructure, and eventual removal, creating significant hurdles, though it is not an outright ban (applicant costs).
People behind it
- Christian E. Weed
Township solicitor who prepared and presented the proposed data-center ordinance draft.
Restrictions & requirementsHide restrictions & requirements7
The revised draft would allow data centers in C-2 and C-3 districts and prohibit them in CD, R-1, R-2, C-1, ED, and GC districts. permitted in the C-2 General Commercial and C-3
The draft would require a proposed data-center project to comply with the Township Comprehensive Plan. compliant with the Townships Comprehensive Plan
The draft would cap building height at 35 feet. capped at thirty-five feet
The revised draft proposed a 300-foot setback measured from the road right-of-way. proposed setback would be three hundred feet
When required, third-party studies would have to be conducted by an approved, qualified third party, with the applicant paying the cost. at the burden of the applicant
The draft was to be amended to make the applicant pay for specialized equipment or chemicals needed to provide fire protection. applicant shall bear the cost
The draft includes language assigning the applicant the cost of infrastructure updates. cost of infrastructure updates is to be borne by the applicant
Benefits & exceptionsHide benefits & exceptions1
The draft would allow data centers as a use in the C-2 and C-3 zoning districts, subject to consistency with the Township’s Comprehensive Plan; it would prohibit them in the CD, R-1, R-2, C-1, ED, and GC districts. Permitted use in the C-2 and C-3 districts
Sources
pending · Westfall TownshipThe Planning Commission recommended the draft to the Supervisors on August 25, 2026, the Pike County Planning Commission listed it for review on September 28, 2026, and the Supervisors' November 2, 2026 agenda lists it with the moratorium recommendation, with no hearing scheduled.Westfall Township, Pike County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements29
Section 4B of draft Ordinance 182 limits data centers and accessory uses to 35 ft including rooftop equipment, but the amendment does not contain the height limits for other principal buildings in the district.
Environmental Impact Assessment and PNDI review required, draft Ord. 182 § 4 Environmental and Community Impact
Section 4P requires a new conditional use approval for any expansion, intensification, change in operating capacity or cooling technology, added water or energy demand, or added accessory infrastructure.
60 dBA day and 55 dBA night at the property line; 45 dBA night applies only at sensitive receptors, draft Ord. 182 § 4D(1)
Low-frequency noise to be limited by design; no dBC limit or study, draft Ord. 182 § 4D(1)
Section 4D(1)(a) to (c) requires a preliminary study at conditional use, an interim study at building permit, and an as-built study six months after occupancy, using ANSI S1.4-2014 meters.
Generator testing allowed as industry standards require, draft Ord. 182 § 4D(2)
Water feasibility study for nonpublic sources with independent hydrologist review; no pump tests, draft Ord. 182 § 4J(2)
Closed-loop cooling only to the extent feasible, draft Ord. 182 § 4J(6)
Projected water needs disclosed; no cap, reporting, or drought plan, draft Ord. 182 § 4J(1)-(2)
Section 4J(7) requires a showing that disposal of domestic and cooling wastewater has been provided and approved by the SEO, the Municipal Authority, DRBC, or DEP, without stating when the approval must be in hand.
Stormwater management plan required within the assessment, draft Ord. 182 § 4 Environmental and Community Impact
Tier 4 generators required; no annual testing or reports, draft Ord. 182 § 4H(5)
Heat may not be perceptible past the property line and heat islands must be assessed, draft Ord. 182 § 4E(1)
Decommissioning plan covers e-waste, batteries, refrigerants, and hazardous materials, draft Ord. 182 § 4R(6)-(7).
Utility certification of capacity before approval and third-party electrical inspection before occupancy, draft Ord. 182 § 4H(3)-(4)
On-site generation is a separate use with its own zoning approval, draft Ord. 182 § 4H(2).
Approval may be conditioned on no cost impact to others; applicant not required to pay upgrades, draft Ord. 182 § 4H(3)(e)
Perimeter vegetative buffer within 50 ft of fencing; no 100-ft width, draft Ord. 182 § 4L
Site screened and buffered around the entire perimeter; no equipment height or acoustic standard, draft Ord. 182 § 4L
Hazardous materials disposal addressed; no storage setbacks or containment, draft Ord. 182 § 4R(7)(b)
Third-party electrical inspection before occupancy; no annual fire inspections, draft Ord. 182 § 4H(4)
The Environmental and Community Impact part of Section 4 requires a traffic impact analysis in every case covering construction and operation, including oversized construction vehicles, for roads and interchanges within one-half mile of the site.
Construction traffic analyzed in the traffic study; no work hours, haul routes, or road bond, draft Ord. 182 § 4 Environmental and Community Impact
Section 4R(2) to (4) requires immediate notice of cessation, removal within six months, and 110 percent security, but the agreement is not recorded and there is no two-year reuse rule for buildings.
Section 4R(5) requires cost estimates after the first year of operation and every fifth year, and states that the financial security shall be updated every five years.
One as-built sound study after occupancy, draft Ord. 182 § 4D(1)(c)
Sections 4H(3)(e), 4I(5), and 4J(5) allow approvals or zoning permits to be revoked for grid, radiation, or water impacts, but no notice and hearing is required before revocation and Sections 616.1 and 617.2 of the MPC are not cited.
Township may retain independent experts; applicant pays only after a noise violation or for radiological surveys, draft Ord. 182 § 4D(3), I, and J(2)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the C-2 and C-3 districts