West Whiteland Township

Anti-Data Center Policies

West Whiteland Township allows data centers through approval, but setbacks, noise controls, decommissioning requirements and renewable-energy rules significantly limit projects.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · West Whiteland Township
Regulates data centers by limiting where larger facilities can locate and requiring approval, impact controls, operating standards, and a plan for eventual closure.West Whiteland Township proposed data-center zoning ordinance (Chapter 325 amendment)

What this means

The proposal would allow data centers in the I-2 district, but large or primary-use facilities would face conditional-use review and a 750-foot buffer from homes (limited to the I-2 district). It also requires 100% renewable electricity and adds noise, emergency-planning, and decommissioning obligations, creating significant hurdles even though data centers are not banned (offset one hundred percent).

People behind it

  • Prepared revisions to the proposed data-center zoning amendment.

  • Identified as the Township body that would enact and ordain the measure.

Restrictions & requirementsHide restrictions & requirements16
  • Large data centers and any data center used as a property's principal use are limited to the I-2 General Industrial District. Data centers under 20,000 square feet are allowed as accessory uses in all zoning districts; the 20,000-square-foot threshold counts multiple data-center areas in the same building together. Limited to the I-2 district

  • A conditional-use approval is required for a data center that is a principal use, regardless of size, or an accessory use occupying at least 20,000 square feet. The application is subject to additional impact studies and information requirements. Conditional use requirements

  • Data-center structures, including structures for accessory uses, must be at least 750 feet from a residential use that exists when the conditional-use application is submitted. The distance is measured from the structure's exterior wall to the residential lot line. 750 feet

  • Facilities or equipment intended to provide a data center's primary energy source are prohibited as accessory uses. Primary energy source

  • Applicants must document the facility's water needs, withdrawals, consumption, wastewater discharge, water sources, and effects on the environment and existing users. If a public utility is a water source, the applicant must provide its confirmation that it can meet the project's needs. Water usage

  • Applicants must document average and peak energy demand, energy sources, effects on utility infrastructure and customers, and backup-power arrangements. Where a Pennsylvania Public Utility Commission-regulated or licensed utility is proposed, the application must include the utility's capacity confirmation and note estimated capital-improvement costs if needed. Operators must develop or purchase new renewable energy sufficient to offset 100% of projected data-center electricity use. One hundred percent

  • The site must meet the zoning district's area and bulk requirements, and the application must demonstrate that required landscaping is feasible, including a screening buffer around the site. Screening buffer

  • Applicants must submit an emergency response plan covering specified emergencies, response procedures, public notice where other properties could be affected, waste disposal, and restoration of off-site damage. The Township's Emergency Management Coordinator must find the plan satisfactory; if a professional consultant is needed for review, the applicant pays the cost. Emergency response plan

  • Applicants must submit a qualified professional's noise-and-vibration report covering preconstruction conditions, projected operational effects—including cooling equipment and emergency power—and mitigation needed for compliance. Vibration perceptible to human senses beyond the property line must be mitigated until it is no longer perceptible. A post-construction report is due within three months of the first August 31 after the center becomes fully operational; violations require immediate corrective steps. Post-construction report

  • The noise ordinance sets a 50 dBC sound limit for all receiving land-use categories at all times. 50 dBC

  • Battery and other energy-storage accommodations must comply with NFPA Standard 855 and have fire-suppression systems designed for the devices used. NFPA Standard 855

  • Electronic waste must be handled by an entity acceptable to the Township that specializes in recycling and safe disposal, and the operator must keep a log available to the Township on request. Electronic waste

  • The facility must undergo at least annual fire-safety inspections. The operator must pay for any site-specific first-responder training or equipment identified as necessary. At least once annually

  • The Township may require a Community Benefits Agreement as a condition of conditional-use approval, addressing identified community impacts and needs such as monitoring, emergency-service capabilities, flood-risk reduction, and open-space or historic-resource improvements. Right to require a CBA

  • Applicants must provide a decommissioning plan. Decommissioning must begin within one year after operations cease and finish within the following 18 months, unless the Board of Supervisors agrees to a longer period. Final land-development approval requires financial security sufficient to cover the full estimated cost; the Township may draw on it if the plan is not completed satisfactorily and may require a plan and cost review no more than once every 24 months. Financial security

  • Parking for data centers of 20,000 square feet or less must be at least two spaces or one space per 4,000 square feet of floor area, whichever is greater. Parking for larger facilities is determined during the conditional-use hearing. Parking standards

Benefits & exceptionsHide benefits & exceptions3
  • Data centers are allowed in the I-2 General Industrial District, subject to conditional-use review and the ordinance’s additional requirements. Permitted in the I-2 district.

  • Data centers under 20,000 square feet may operate as accessory uses by right in all zoning districts; the special data-center rules apply to principal-use centers regardless of size and accessory centers of 20,000 square feet or more. Permitted as an accessory use by right.

  • The ordinance expressly allows several supporting accessory uses, including electrical substations, backup energy equipment, roof-mounted solar systems, wireless communications facilities, and water-treatment facilities. Primary energy sources are prohibited as accessory uses; water-treatment and other support facilities are subject to stated review and safety conditions. Specifically permitted ancillary uses.

Sources

current law · West Whiteland Township
The Board of Supervisors adopted Ordinance No. 492 on October 14, 2026, effective immediately, and the next step is for the township to codify it on eCode360.West Whiteland Township, Chester County — data-center ordinance (No. 492)

What this means

The measure imposes setbacks from homes or other protected places, noise limits and sound testing and money set aside for eventual removal. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements21
  • Conditional use; no approval expiration, § 325-28.4.D

  • Section 325-28.4.D(3)(b) of Ordinance 492 keeps any data center structure, including structures for accessory uses, 1,000 feet from property in the R-1 and O/R districts, but the distance is measured from exterior walls rather than from all outdoor equipment, and homes in other residential districts are not protected.

  • District area and bulk requirements, including height, stated to apply; no rooftop equipment limit, § 325-28.4.D(3)(a)

  • Water impacts on groundwater and surface waters disclosed only; no riparian buffer or impact assessment, § 325-28.4.D(1)(c)

  • Chapter 213 limits apply; no separate data center day and night dBA limits, § 325-28.4.D(5)(d)

  • 50 dBC for all receiving land uses at all times, § 213-3.A(1) as amended by Section 1

  • Pre-construction study with application and post-construction report; none at building permit, § 325-28.4.D(5)

  • Vibration study with mitigation so none is perceptible past the property line, § 325-28.4.D(5)(e).

  • Water source identified with utility capacity documentation; no well restriction, § 325-28.4.D(1)(b)

  • E-waste and hazardous waste sent to recycling entities with a log; no full plan, § 325-28.4.E(3)

  • Utility capacity documentation with the application; no electrical inspection, § 325-28.4.D(2)(b).

  • Energy needs description and 100% renewable offset; no on-site generation required, § 325-28.4.D(2)

  • Electrical substations allowed as part of the use; not screened or placed, § 325-28.4.C(5)

  • Estimated cost of required utility improvements disclosed, § 325-28.4.D(2)(b)

  • Screening buffer around the site perimeter under § 281-35.D, width not stated, § 325-28.4.D(3)(a)

  • Emergency response plan reviewed by the Emergency Management Coordinator; no annual update, radio coverage, or contact signage, § 325-28.4.D(4)

  • Hazardous materials used or stored on site must be listed, § 325-28.4.D(7)

  • Annual fire safety inspection; no third-party electrical inspection, § 325-28.4.E(4)

  • Financial security for the full decommissioning cost, 18-month completion; not 110% or 6 months, § 325-28.4.G

  • One post-construction noise and vibration report, § 325-28.4.D(5)(f)

  • Applicant pays for a consultant reviewing the emergency plan only, § 325-28.4.D(4)(e)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I-2 General Industrial District

Sources

expired · West Whiteland Township
Pauses data center applications under the current zoning ordinance while the Township develops data center-specific rules.West Whiteland Township Resolution 2026-18 — zoning curative amendment process

What this means

If adopted as described, the measure would temporarily stop data-center applications from moving forward under the current zoning rules, making development and expansion substantially harder during the pause. The source says the Township has 180 days to address the zoning gap, so this is a temporary freeze rather than a permanent ban (“effectively puts a freeze”; “180 days to correct the invalidity”).

Timing

Ends
180 days after adoption

The freeze applies to data-center applications under the current zoning ordinance while the Township addresses the invalidity. The source states that the Township has 180 days to correct it; it does not state an extension condition.

People behind it

  • Enacted the municipal curative resolution declaring the zoning ordinance invalidity related to data centers. The Board of Supervisors enacted a Resolution.

  • Reviewing the draft ordinance amendment intended to address the invalidity. continue reviewing the draft ordinance amendment.

Restrictions & requirementsHide restrictions & requirements1
  • The resolution temporarily freezes data-center-related applications and prevents them from proceeding under the current Zoning Ordinance. The minutes do not specify the freeze’s duration. freezes any application received related to data centers

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data