West St. Clair Township
Anti-Data Center Policies
West St. Clair Township allows data centers but imposes potentially limiting setbacks and other siting, design, environmental, and operating requirements.
current law · West St. Clair TownshipRequires data centers in West St. Clair Township to meet local rules for site location, noise, water use, power, safety, environmental protection, screening, and decommissioning.West St. Clair Township Ordinance No. 66 — Data Center Ordinance
What this means
The ordinance would allow data centers, but major siting limits—including 500-foot setbacks and a 65-foot height limit—could rule out many sites. Noise, environmental, cooling, power, and screening requirements would also add meaningful costs and work, creating significant barriers rather than a ban.
People behind it
- West St. Clair Township Board of Supervisors
The ordinance identifies the Board of Supervisors as the body that adopted and enacted the measure.
Restrictions & requirementsHide restrictions & requirements19
The ordinance applies to data center plans submitted on or after July 1, 2026. It becomes effective immediately and applies to plans submitted on or after the effective date.
Buildings are limited to 65 feet tall. A waiver must be requested in the land development application, supported by professional engineering, architectural, and safety analyses, and may require an independent review at the applicant’s expense; approval requires proof that the height will not harm emergency response, environmental resources, or neighboring properties and that no reasonable alternative exists. The maximum building height is 65 feet.
Principal buildings, accessory structures, and data center electric substations must be at least 500 feet from adjoining property lines and public road rights-of-way, 1,500 feet from existing occupied buildings off the project parcel or sensitive receptors, and 500 feet from waterbodies, streams, and wetlands. The ordinance specifies these setback distances.
Parking must include at least one space per employee on the largest shift, plus three visitor spaces; at least one loading bay is also required and must be arranged to avoid obstructing street traffic and preserve emergency access. The ordinance sets minimum parking and loading requirements.
Noise is limited to a 57 dBA CNEL at sensitive-receptor property boundaries, developed-property boundaries, and the nearest residential property line. The limits do not apply to specified emergency alerts and utility work, snow removal, or road repair; the Board may require noise barriers or devices. The ordinance establishes a 57 dBA standard.
Air, dust, smoke, glare, exhaust, heat, and humidity from an activity must be managed so they are not perceptible at or beyond the property line. Impacts must not be perceptible beyond the property line.
Electrical equipment must be housed in metered, grounded, pre-engineered metal enclosures rated to resist an internal electrical fire for at least 30 minutes, with doors that close automatically during a fire even if power fails. Battery or other energy-storage systems must demonstrate compliance with NFPA 855 or similar standards and include fire suppression designed for battery storage. The ordinance requires fire-rated enclosures and energy-storage safeguards.
Applicants must obtain written service-provider verification of adequate supply capacity and equipment, cooling-system adequacy, and no harmful electrical interference or voltage fluctuations, and provide the planning commission written verification that electrical work passed a third-party final inspection. The ordinance requires written utility verification and inspection.
Projects must provide a photometric plan for Board review. Lighting must be fully shielded, generally use exterior lighting no warmer than 3,000 K, keep residential and agricultural boundary illumination very low (the ordinance gives an average of no more than 0.2 foot-candles as an example), and reduce nonessential overnight lighting using controls such as timers or sensors. The ordinance requires review of a photometric plan.
The perimeter must have security fencing at least eight feet high, made with high-quality design and materials. The perimeter fencing must be a minimum of eight feet in height.
Substations must be screened by year-round opaque landscaping or an eight-foot screen wall; onsite substations must be placed to the side or rear of the principal building, outside a required front yard. Onsite power lines of 34.5 kV or less must be buried. Substations also have a 500-foot setback from offsite residential structures. The ordinance requires substation screening and undergrounding of specified lines.
Every data center must maintain onsite or behind-the-meter generation capable of supporting critical operations. Generators must be Tier 4 or higher and operate at the lowest dBA levels; generation systems must meet environmental, safety, and interconnection standards. All data centers must maintain generation for critical operations.
Sites must provide boundary buffers and screening, with enhanced buffer widths determined by the combined building footprint: 100 feet for footprints under 100,000 square feet, 150 feet for 100,000–250,000 square feet, and 300 feet above 250,000 square feet along public street frontage and near specified sensitive uses; other property lines generally require 50 feet. The ordinance also prescribes plantings and screening, and allows written modifications or waivers through the land development application. Buffer widths vary by building footprint.
Applicants must submit an environmental and community impact analysis covering operations, site resources, regulated materials disposal, potential effects on services and municipal finances, likely environmental impacts, and mitigation; they must also show impacts are within levels allowed by applicable laws and ordinances. The ordinance requires an environmental and community impact analysis.
Data centers must use closed-loop cooling; open-loop, once-through, or discharge-based cooling systems are prohibited. Open-loop and discharge-based cooling systems are prohibited.
A Pennsylvania Natural Heritage Program study dated within two years of the first relevant conditional-use/special-exception or subdivision and land-development application, plus any required agency clearance letters, must be provided; applicants must follow measures to avoid, minimize, or mitigate effects on protected species and habitat. The required PNDI study must be dated within two years.
Where a site contains, borders, or lies within 150 feet of specified waters or wetlands, the project must protect, convert, or establish a riparian forest buffer. The buffer is generally at least 100 feet on each side, with added width for specified slopes and wetlands; earth disturbance, development, and storage or stockpiling are prohibited within it, and the buffer must be protected in perpetuity. The ordinance requires riparian buffers for sites within 150 feet of listed waters.
For data centers anticipated to use nuclear energy, applicants must submit a preliminary radiological survey with the application, covering perimeter points within 400 feet of residential or commercial activity. An as-built survey is required six months after a certificate of occupancy; surveys may be commissioned by the Township at the applicant’s or developer’s expense. A radiation violation suspends the permit until compliance is verified, and failure to remediate can lead to permit revocation. Nuclear-powered projects require preliminary and follow-up radiological surveys.
Applicants must provide a decommissioning plan to return participating properties to preconstruction condition, including removal of facilities and infrastructure without an ongoing purpose. The plan must include financial security—such as a bond, parent-company guarantee, or irrevocable letter of credit, but not cash—at least equal to estimated decommissioning costs after salvage or recycling value, based on an applicant-funded third-party engineering estimate subject to Township review. The decommissioning plan must include financial security.
Benefits & exceptionsHide benefits & exceptions5
A data center may seek a waiver from the 65-foot building-height limit through its land-development application. It must provide professional engineering, architectural, and safety analyses and show that the added height will not harm emergency response, environmental resources, or neighboring properties, and that no reasonable alternative exists; the Township may require an independent review at the applicant’s expense. Height-waiver requirements
The Township may modify or waive the specified enhanced-buffer-yard requirements. Any waiver must be in writing and submitted with the land-development application under the Township’s SALDO. Buffer-yard waiver provision
With Board of Supervisors approval, existing vegetation may be used instead of new berms and plantings for screening. Existing vegetation provision
On-site or behind-the-meter power generation using natural gas, renewable fuels, or other clean sources is permitted for reliability, efficiency, or sustainability, subject to environmental, safety, and utility-interconnection standards. Systems must use Tier 4 or better generators, and data centers must maintain on-site or behind-the-meter generation capable of supporting critical operations. On-site generation provision
The stated noise limits do not apply to emergency alerts or emergency work to provide electricity, water, or other public utilities when public health or safety is involved, or to snow removal and road repair. Noise-limit exceptions
Sources
current law · West St. Clair TownshipRequires data centers in West St. Clair Township to meet local rules for siting, noise, safety, power, water use, environmental protection, and cleanup when operations end.Ordinance #66 Data Center Ordinance, West St. Clair Township
What this means
The ordinance would make projects substantially harder: it requires 1,500-foot setbacks from occupied buildings and large landscaped buffers, which could sharply limit suitable sites. It also adds substantial design, environmental, safety, and operating requirements, with no meaningful financial incentives to offset the burden.
People behind it
- West St. Clair Township Board of Supervisors
The ordinance states it was duly adopted and enacted by the Board of Supervisors.
Restrictions & requirementsHide restrictions & requirements20
Caps data-center building height at 65 feet. A waiver requires engineering, architectural, and safety analyses by qualified professionals, may require a third-party review at the applicant’s expense, and is allowed only if the applicant proves there is no reasonable alternative and no specified impacts. 65 feet
Requires principal buildings, accessory structures, and data-center substations to be 500 feet from adjoining property lines and public road rights-of-way, 1,500 feet from existing off-site structures or sensitive receptors, and 500 feet from waterbodies, streams, or wetlands. Parking must be 50 feet from roads and property lines. setback distances
Requires one parking space per employee on the largest shift, plus three visitor spaces, and at least one loading bay on a principal building, arranged to avoid obstructing street traffic and preserve emergency access. parking requirements
Limits Community Noise Equivalent Level to 57 dBA at sensitive-receptor property boundaries, developed-property boundaries, and the nearest residential property line. Emergency alerts and specified emergency utility work, snow removal, and road repair are excepted; the Board may require a noise barrier or device. 57 dBA
Requires air, dust, smoke, glare, exhaust, heat, and humidity from operations to be managed so they are not perceptible at or beyond the property line. not perceptible at or beyond the property line
Requires operational equipment to be housed in metered, grounded, pre-engineered metal enclosures rated to resist an internal electrical fire for at least 30 minutes, with doors that close automatically during a fire even if electrical power fails. Battery or other energy-storage proposals must demonstrate compliance with NFPA 855 or similar standards and include battery-specific fire suppression. fire rating
Requires written verification from the utility provider that supply capacity and equipment can serve the project without undermining projected service-area load growth, and that cooling and operations will not negatively affect the region or cause electrical interference or voltage fluctuations. The applicant must also provide written verification of a third-party final inspection of electrical work. written verification
Requires a photometric plan for each project for Board review; site and building lighting must be fully shielded, exterior lighting generally must not exceed 3,000 K, and nonessential lighting must be controlled to reduce overnight lighting. The ordinance gives an example boundary level of no more than 0.2 foot-candles at residential and agricultural boundaries. photometric plan
Requires security fencing around the perimeter at least eight feet high and made of high-quality design and materials. minimum of eight feet
Requires substations to have year-round opaque landscaping or an eight-foot screen wall; onsite substations must be at the side or rear of the principal building, screened from public view, and outside required front yards. Onsite power lines of 34.5 kV or below must be buried. Substations must also be 500 feet from off-site residential structures. power lines
Requires Tier 4 or higher generators, operated at the lowest dBA levels, and requires every data center to provide and maintain onsite or behind-the-meter generation capable of supporting critical operations. Tier 4 or greater generators
Requires loading bays, truck entries, and truck drive aisles to be located away from nearby sensitive receptors unless physically impossible, and requires screening as provided elsewhere in the ordinance. located away from nearby Sensitive Receptors
Requires buffer yards and screening along property boundaries, except at site entrances and exits. Depending on combined building footprint, minimum buffers along public street frontage and property lines abutting or within 500 feet of specified sensitive uses are 100 feet for projects under 100,000 square feet, 150 feet for 100,000–250,000 square feet, and 300 feet for over 250,000 square feet; other property lines generally require 50 feet. Dense specified tree and shrub planting is required, though the Township may modify or waive requirements. minimum 100-foot buffer yard
Requires ground-mounted equipment adjacent to and serving the principal building to be completely screened, and prohibits ground-mounted equipment in required setbacks. Rooftop equipment must be screened on all four sides and set back from the parapet or exterior wall according to the ordinance’s height-based rules. completely screened
Requires an environmental and community impact analysis addressing operations, traffic, site resources, material disposal, effects on emergency services and public facilities, and likely environmental impacts and mitigation; the applicant must show impacts fall within acceptable levels under applicable laws and ordinances. environmental and community impact analysis
Requires closed-loop cooling and prohibits open-loop, once-through, or discharge-based cooling systems. open-loop, once through, or discharge-based cooling systems are prohibited
Requires a Pennsylvania Natural Heritage Program study dated within two years of the first specified application and any required agency clearance letters; applicants must follow clearance measures to avoid, minimize, or mitigate effects on protected species and habitat. dated within two years
If a site contains, borders, or is within 150 feet of specified waters or wetlands, requires protection, conversion, or creation of a riparian forest buffer. The buffer is at least 100 feet wide, with additions for steeper slopes and certain wetlands or ponds; earth disturbance, development, and storage or stockpiling are prohibited within it, and the buffer must be protected in perpetuity. minimum of 100 feet
For a data center anticipated to use nuclear power, requires a preliminary radiological land survey with the application and an as-built survey six months after the certificate of occupancy. The Township may commission additional surveys at the applicant’s or developer’s expense; a permit is rescinded for a radiation-limit violation until compliance is verified, and may be revoked if the violation is not remediated. six months after issuance
Requires a decommissioning plan to return participating properties to preconstruction condition and remove facilities and infrastructure with no ongoing purpose. The plan must include financial security—such as a bond, parent-company guarantee, or irrevocable letter of credit, but not cash—at least equal to estimated decommissioning costs after salvage or recycling value, based on an applicant-funded third-party engineering estimate and subject to Township review. financial security
Benefits & exceptionsHide benefits & exceptions5
A developer may seek a waiver from the 65-foot height limit by including the request in the land-development application and providing professional analyses. Approval requires showing that the height will not affect emergency response, environmental resources, or neighboring properties, and that no reasonable alternative exists. A request for a waiver
The Township may modify or waive enhanced buffer-yard requirements; a written waiver must accompany the land-development application. The Township may grant a modification or waiver
With Board approval, existing vegetation may be used instead of new berms and plantings for screening. Use of existing vegetation
On-site or behind-the-meter generation using natural gas, renewable fuels, or other clean sources is allowed, subject to environmental, safety, and utility-interconnection standards. Data centers must also maintain on-site or behind-the-meter generation capable of supporting critical operations; generators must be Tier 4 or greater. On-site or behind the meter generation
An on-site electric substation does not need a buffer or screening between the substation and the data-center principal building. Onsite substations do not require a buffer or screening
Sources