West Pike Run Township

Anti-Data Center Policies

West Pike Run Township’s enacted ordinance requires data centers to meet setbacks from homes and other protected places and minimum site sizes, sharply limiting suitable sites and project designs despite an approval route.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · West Pike Run Township
The current rules are in Ordinance No. 2-2026, the West Pike Run Township Data Center Ordinance of 2026, which the Board of Supervisors adopted on August 17, 2026.West Pike Run Township, Washington County — data-center ordinance (No. 2-2026)

What this means

The measure imposes setbacks from homes or other protected places and minimum site-size requirements. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.

Restrictions & requirementsHide restrictions & requirements29
  • Conditional use; no approval expiration, § 171.1(B)(1)

  • Sensitive receptors defined but no setback stated

  • Environmental impact assessment required, § 171.1(B)(36)

  • 55 dBA day and 45 dBA night via Noise and Dust Ordinance, § 171.1(B)(25)

  • Section 171.1(B)(25) of the data center ordinance applies the Noise and Dust Ordinance, whose Section 6.C bars noise more than 10 dBA above ambient at any residential property line, but Section 6.D makes the most restrictive of the ambient and absolute standards govern, so there is no floor, and no L90 statistic is stated for ambient.

  • Octave-band limits of 65 dB at 31.5 Hz and 60 dB at 63 Hz; no day and night dBC limits, Noise and Dust Ordinance § 6.E

  • Application study plus pre- and post-construction studies; no building permit study, § 171.1(A)(1)(c) and (B)(24)

  • ISO residential vibration curve with vibration study; not a none-perceptible standard, § 171.1(B).

  • Water provider capacity letter; no well or hydrogeologic rules, § 171.1(B)

  • Closed-loop systems for water conservation; no evaporative restriction, § 171.1(B)(34)

  • Water usage disclosed with application; no cap or drought plan, § 171.1(A)(1)(b)

  • Section 171.1(B)(11) requires the operator to show that disposal of domestic and cooling wastewater has been provided and approved by DEP, without stating when the approval must be in hand.

  • EPA Tier 4 final generators; no annual emissions testing, § 171.1(B)(33)

  • E-waste recycling at decommissioning; no plan for batteries and refrigerants, § 171.1(B)(48)

  • Electrical provider capacity letter and utility agreement; no third-party inspection, § 171.1(B)(6).

  • Annual energy efficiency report; no required on-site renewables, § 171.1(B)(33)

  • Section 171.1(B)(7) and (9) make generation serving the data center a separate use approved under the Fossil Fuel Electric Generating Facilities Ordinance (Ord. No. 3-2026), which requires its own conditional use approval (Section IV.A), 500 ft and 1,500 ft setbacks (Section V.D.1), the township Noise and Dust Ordinance (Section X), and state and federal emission standards (Section XII.F.1).

  • On-site lines buried; substations not required to be screened or placed to the rear, § 171.1(B)(30)

  • 100-ft planted buffer next to residential, commercial, and agricultural districts, § 171.1(B)(28).

  • Equipment fully screened with noise shielding; no 12-ft height, § 171.1(B).

  • Plan accepted by fire department, posted emergency contacts; no radio coverage, § 171.1(B)(43)

  • Section 171.1(B)(13) requires annual responder training and special equipment provided to the responding fire companies at the operator's expense, but it does not require training before occupancy or the equipment to be kept on site.

  • Hazardous materials plan; no storage setbacks or containment, § 171.1(B)(50)

  • Annual fire safety inspections; no third-party electrical inspection, § 171.1(B)(43)

  • Must meet township traffic impact study requirements, § 171.1(B)(35)

  • Truck routes, construction transportation plan, road bond; no work hours, § 171.1(B)(17)

  • 125% security and notice to public safety, but removal may take up to 240 days after abandonment is determined, § 171.1(B)(47), (B)(48)

  • Post-construction study and annual reports on generator hours and complaints; no ongoing noise, water, or power reports

  • Studies reviewed by township engineer at operator expense; no independent expert review, § 171.1(A)(1)(c) and (e)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the B-1 Business/Industrial District

Sources

pending · Township of West Pike Run
Proposes to define data centers and set requirements for them in different zoning districts.West Pike Run Township Zoning Ordinance — data center provisions

People behind it

  • Identified as the municipality whose Ordinance No. 2 of 2026 would amend the zoning ordinance.

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data