West Nantmeal Township
Anti-Data Center Policies
West Nantmeal Township’s enacted ordinance requires setbacks, cooling and water-use rules, and noise limits and sound testing for data centers. Projects still have an approval route, but these limits narrow where and how they can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · West Nantmeal TownshipThe Board of Supervisors adopted Ordinance No. 4-2026 by a 3-0 vote on August 10, 2026, after a hearing that began July 13, 2026, and the ordinance is not yet codified.West Nantmeal Township, Chester County — data-center ordinance (No. 4-2026)
What this means
The measure imposes setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements27
Conditional use in the I-1 Limited Industrial District only, § 215-17.C(9)
Conditional use; no approval expiration, § 215-17.C(9)
50 ft maximum height; rooftop equipment height not limited, Matrix Chart 5
Community and environmental impact statement covering water quality, groundwater, and wildlife habitat, § 215-123.1.K(3)
55 dBA day and 45 dBA night at residential receiving uses, higher at commercial and industrial uses, § 215-123.1.D(9) Table 2
Section 215-123.1.D(9), Table 6, treats an increase of 3 dBA or more above the baseline ambient level documented before construction as a violation, measured with a Type 1 or Type 2 ANSI meter, but the baseline is not defined as L90 and no floor is set below which the cap does not apply.
70 dBC day and 60 dBC night at the nearest property line, § 215-123.1.D(9) Table 3
Pre-construction study with the application and as-built study within 180 days; no building permit study, § 215-123.1.D(1) and (3)
Vibration limits of 0.2 to 0.5 in/s PPV and 65 VdB in the post-construction study; imperceptibility at the property line not stated, § 215-123.1.D(3)(f)
Public water for domestic use; public water, wells, groundwater, and surface water barred for cooling, with groundwater monitoring wells, § 215-123.1.E(1), E(4), and J(2).
Section 215-123.1.E(5) requires air-cooled or closed-loop water circulation systems and bars groundwater and surface withdrawals as the primary cooling source, but evaporative systems are not expressly barred or limited to a stated water-use rate shown to meet the noise limits.
Daily and annual water use estimates and drought response plan; no cap or reporting, § 215-123.1.E(2) and (6)
Diesel generators must meet EPA Tier 4 with annual testing reports, § 215-123.1.G(2)(a)-(b)
Decommissioning plan covers disposal or recycling of materials, § 215-123.1.J(3)
Utility interconnection documentation with the application; no electrical inspection, § 215-123.1.G(1)(f)
Energy usage plan required; renewables documented but not required, § 215-123.1.G(1)
On-site generation is a private utility needing special exception approval, data center setbacks, and independent review, § 215-123.1.H.
Substations at the side or rear and screened; power lines serving the property must be buried, § 215-123.1.H(2)-(4)
Facade material change and main entrance feature required, § 215-123.1.C(2) and (4).
Mechanical equipment screened on all sides; no height or acoustic standard, § 215-123.1.C(1)
Elevations and renderings of principal facades required, § 215-123.1.C(2)
Emergency response plan accepted by the fire department and reviewed semi-annually; no radio coverage or 24-hour contact signage, § 215-123.1.I(1)-(2)
Engineered containment of contaminated firefighting water and hazardous substances; no storage setbacks, § 215-123.1.I(4)
Annual fire safety inspections, § 215-123.1.I(1)(e)
Construction plan with access times and locations for construction vehicles; no haul route bond, § 215-123.1.J(1)
Plan and financial security for full cost, completion within 18 months; no closure notice, § 215-123.1.J(3)
One post-construction noise and vibration study within 180 days, § 215-123.1.D(3)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the I-1 Limited Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data