West Mahanoy Township
This restriction takes precedence for the map color while in effect.
Anti-Data Center Policies
West Mahanoy Township’s enacted measure pauses covered data-center applications or development for 180 days, delaying projects but not permanently banning them.
Rating from Schuylkill County as there are no scored current or future laws outside temporary restrictions for West Mahanoy Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · West Mahanoy TownshipPauses consideration of data center proposals for 180 days while the township updates its zoning rules.West Mahanoy Township curative-amendment resolution on data centers (180-day pause)
What this means
The measure would put data-center applications on hold for 180 days, causing a substantial delay to new projects and expansions. It does not describe a ban on existing operations, but the township plans to consider rules on issues such as noise, buffers, and power sources, which could add further requirements. Applications would be placed on hold.
Timing
- Ends
- 180 days after adoption
The 180-day pause applies to considering data-center and solar-farm proposals. No extension condition is stated.
People behind it
- West Mahanoy Township
The township invoked the curative-amendment process and its supervisors unanimously approved the resolution placing data-center and solar-farm proposals on hold for 180 days (supervisors voted unanimously to approve a resolution).
- Siana Law
Hired as special counsel to prepare zoning and land-development ordinance updates related to the measure (special counsel to prepare ordinance updates).
Restrictions & requirementsHide restrictions & requirements1
For 180 days, the township will not consider landowner curative amendments or proposals for data center or solar farm uses, and applications for those uses are put on hold. The township shall not be required to entertain or consider them during that period.
Sources
current law · West Mahanoy TownshipThe Supervisors unanimously adopted a resolution invoking the curative amendment process for data centers and solar farms, which declares the zoning ordinance invalid as to those uses and pauses related applications for 180 days.West Mahanoy Township, Schuylkill County — data-center moratorium / curative resolution curative resolution (2026-09-15)
What this means
The measure pauses covered data-center applications or development for 180 days. That stops affected projects from moving ahead during the pause, even though it is not a permanent ban.
Timing
- Ends
- 180 days; exact operative ending date not independently verified.
The Supervisors unanimously adopted a resolution invoking the curative amendment process for data centers and solar farms, which declares the zoning ordinance invalid as to those uses and pauses related applications for 180 days.
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data