Loading map…

Borough of West Leechburg

Anti-Data Center Policies

West Leechburg’s enacted ordinance limits noise and requires sound testing for data centers, increasing construction, review, or compliance costs while still allowing approval.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · West Leechburg Borough
The rules were added to Chapter 290 Zoning by Ordinance No. 343, which Borough Council adopted on May 13, 2026.West Leechburg Borough, Westmoreland County — data-center ordinance (No. 343)

What this means

The measure imposes noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements17
  • 67 dBA day and 57 dBA night at the property line, § 290-91.F

  • Section 290-91.F.1 requires preliminary, interim, and as-built sound studies using ANSI S1.4 sound level meters, with the as-built study six months after the certificate of occupancy, but does not require any study at full operating load.

  • Water feasibility study for nonpublic sources, § 290-91.G.2

  • Projected water demands disclosed, § 290-91.G.2

  • Section 290-91.G.4 requires the applicant to show that disposal of domestic, cooling, and industrial wastewater has been provided and approved by the Kiski Valley Water Pollution Control Authority or DEP, but does not state that the approval must be in hand before the zoning permit.

  • MS4 compliance required, § 290-91.G.5

  • Utility capacity documentation; no third-party electrical inspection, § 290-91.H.1.

  • On-site generation is a separate use with its own approval, § 290-91.H.2.

  • Known rate and availability impacts must be noted, § 290-91.H.1

  • 25 ft landscape buffer, § 290-91.D

  • Two design elements every 150 horizontal feet, § 290-91.K.

  • Equipment within 300 ft enclosed or screened; no 12 ft standard, § 290-91.E

  • ERP reviewed by fire department with annual inspections; no radio or contact rule, § 290-91.I

  • Responders must receive training; no funding, § 290-91.I

  • Annual fire safety inspections, § 290-91.I

  • As-built sound study six months after occupancy, § 290-91.F

  • Exceeding noise limits is a violation; general enforcement, § 290-91.F

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data