Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for West Lebanon Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · West Lebanon Township
Would require data centers seeking to use more water than the township can supply to obtain a special exception and show they have adequate water and cost arrangements.N/A — No adopted data-center-specific law or ban identified in West Lebanon Township

What this means

The proposed rule would make data centers that exceed local water capacity seek a special exception and show they have adequate water and cost arrangements (special-exception approval and water requirements). That could add approval time and expense, but it applies to high water use rather than banning data centers generally.

Restrictions & requirementsHide restrictions & requirements1
  • Under the draft ordinance, a data center seeking to use more water than local capacity must obtain special-exception approval and demonstrate adequate water and cost arrangements (“exceed local water capacity”).

Benefits & exceptionsHide benefits & exceptions1
  • Provides a special-exception approval route for data centers seeking to exceed local water capacity, conditional on demonstrating adequate water and cost arrangements.

Sources

pending · West Lebanon Township
A township attorney reported on October 5, 2026 that the draft had been significantly revised and sent back to county planning for review, and the township manager provided the undated and unnumbered draft on October 23, 2026, with no adoption hearing yet announced.West Lebanon Township, Lebanon County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose money set aside for eventual removal, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements24
  • Noise retest after expansion only; no new approval or phasing plan, § 27-802.1(6)

  • 55 dBA day and 45 dBA night at residential and sensitive receptor lot lines, § 27-802.1(6)

  • Noise impact study before approval and compliance test within 90 days of operation, § 27-802.1(6)

  • Water demand analysis and provider capacity letter; groundwater barred without SRBC approval, § 27-802.1(9)

  • Cooling method not required to be disclosed, § 27-802.1(2) and (9)

  • Projected water demand disclosed; no cap, reporting, or drought plan, § 27-802.1(9)

  • Adequate wastewater disposal capacity must be shown, § 27-802.1(9)

  • Fuel storage and generators must meet federal, state, county, and Township rules, § 27-802.1(14)

  • Decommissioning plan must include recycling or disposal procedures, § 27-802.1(15)

  • Electric utility documentation of ability to serve with the application; no electrical inspection, § 27-802.1(10).

  • Substations within 300 ft of streets or homes enclosed or fully screened, § 27-802.1(5)

  • Battery storage covered by the emergency plan and fire code; no NFPA 855, § 27-802.1(13) and Section 4

  • Section 27-802.1(8) and (10) require the applicant to identify the on-site and off-site electrical infrastructure improvements required to serve the data center and who will build and pay for them, and Section 27-802.1(11) assigns attributable utility cost increases to the operator, but no cost estimate, tariff terms, or executed service agreement is required.

  • 25-ft landscaped buffer next to Residential Districts and sensitive receptors, § 27-802.1(5)

  • Equipment within 300 ft of streets or homes enclosed or fully screened; no height or acoustic standard, § 27-802.1(5)

  • Emergency plan approved by Department of Emergency Services with contacts; no annual update or radio coverage, § 27-802.1(13)

  • Hazardous materials and fuel storage addressed in emergency plan, § 27-802.1(13)-(14)

  • Traffic study only at the Board's discretion, § 27-802.1(12)

  • Emergency access shown on plans; no road class or secondary access, § 27-802.1(12)

  • Construction traffic routes identified; no work hours or road bond, § 27-802.1(12)

  • 110% security; no closure notice or 6-month removal deadline, § 27-802.1(15)

  • Security reviewed at least every 5 years; no first-year update, § 27-802.1(15)

  • One noise compliance report within 90 days of operation, § 27-802.1(6)

  • Section 27-802.1(18) requires the applicant to reimburse reasonable fees of Township engineers, acoustical, environmental, traffic, and other consultants for review of its application, plans, studies, permits, and approvals through construction, backed by an escrow.

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: special exception in the Manufacturing District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data