Borough of West Homestead

Anti-Data Center Policies

West Homestead allows data centers in industrial areas only with special approval, setbacks, noise testing, height limits, utility documentation, and emergency plans, adding review and compliance costs without banning them.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Borough of West Homestead
Defines data centers to include facilities that process, transfer, or store digital information, including cryptocurrency mining, and identifies related accessory uses such as backup generators, substations, cooling systems, and security facilities.West Homestead Zoning Ordinance, § 27-402, “Data Center” definition
Benefits & exceptionsHide benefits & exceptions2
  • Accessory uses are generally permitted unless another provision of the chapter says otherwise. This can apply to accessory uses, but does not itself establish that a data center or any particular accessory use is allowed in a specific zoning district.

  • The code defines data center accessory uses to include specified supporting facilities on the same tract or adjacent parcels developed as a unified data center project, including backup generators used during interruptions, substations, utility lines, cooling and wastewater facilities, pump stations, water towers, and security structures. Energy generation systems intended to supply the data center during normal operations are expressly excluded from this definition.

Sources

current law · Borough of West Homestead
Requires data centers in the industrial district to obtain special-exception approval and meet specific rules for setbacks, landscaping, noise, water and power supply, emergency planning, and parking.West Homestead Zoning Ordinance, § 27-1125, “Data Centers” (Ordinance No. 745)

What this means

Data centers would be allowed in the industrial district, but only with special-exception approval and substantial requirements, including setbacks, sound studies, water or power documentation, and emergency planning (special-exception approval and standards). These rules could add significant cost and delay to building and operating a facility, though they do not prohibit data centers.

Restrictions & requirementsHide restrictions & requirements13
  • Data centers are allowed only by special exception in the IND Industrial Zoning District, subject to the section’s procedures, standards, and criteria.

  • A data center building may be no more than 60 feet high, including roof-mounted equipment; accessory uses may not exceed the principal building’s height. Data centers and accessory uses must be set back 200 feet from R-1, R-1T, MU, and SC zoning district boundaries and from the lot line of a property developed with a sensitive receptor.

  • A landscape buffer at least 25 feet wide is required between the facility and adjoining R-1, R-1T, MU, or SC zoning, a sensitive receptor, or a public roadway. The buffer has specified native tree and shrub planting quantities and minimum sizes. The Council may count adequate existing topography or vegetation toward the buffer on recommendation from the Borough Engineer and Planning Commission.

  • Cooling, ventilation, and power-supply equipment within 150 feet of a public roadway or a sensitive receptor’s lot line must be fully enclosed unless the manufacturer’s specifications make enclosure mechanically infeasible. In that case, it must be fully screened by specified means, such as the landscape buffer, existing vegetation, a building, a berm, or a solid screen.

  • Property fencing is allowed, but fencing along public or private roadways may not be chain-link, including chain-link with slatted inserts, or include barbed wire or similarly visibly intrusive deterrents. This restriction does not apply if the fencing is fully screened by an authorized screening method.

  • Applicants must submit a professional acoustical study demonstrating maximum sound levels at the property line of 67 dB(A) during weekdays from 7:00 a.m. to 8:00 p.m. and 57 dB(A) during weekday nights and weekends. A preliminary study is required for the special-exception process; an interim study is required during building-permit review, with recommended sound controls incorporated into construction plans; and an as-built study is required six months after the certificate of occupancy and before final escrow release for a land-development phase. The Borough may require later studies. The limits do not apply during power outages, but studies must report anticipated sound with all emergency generators running.

  • Applicants must provide a qualified professional’s vibration study demonstrating that vibration from the data center, its accessory uses, and associated equipment will not be perceptible to human senses beyond the property line.

  • For a public water supply, the applicant must provide public-authority documentation certifying that the authority will supply the required water. For nonpublic water, the applicant must submit a feasibility study addressing adequacy and effects on nearby water resources, with specified information on demand, sources, use, yield, withdrawals, wells, and surface waters. Approval is barred unless the study establishes adequate supply and no endangerment or adverse effect on nearby groundwater or surface waters. Adequate wastewater disposal, including cooling or industrial wastewater, must also be demonstrated and approved by the Sewage Enforcement Officer and/or Pennsylvania DEP.

  • For a grid connection, the applicant must provide the electric service provider’s certification that capacity is available and service will be provided, and note known project impacts on electric rates or availability for other uses. On-site energy-generation systems supplying the data center during normal operations are treated as a separate use and require approval under the zoning rules applicable to that use.

  • Applicants must submit an Emergency Response Plan prepared by a qualified professional and reviewed and accepted by the local fire department and emergency management services as part of the special land-development process. It must cover emergency procedures and site access, ensure first-responder training, and provide for annual professional fire-safety inspections.

  • A data center proposing battery storage or another energy-storage device must demonstrate compliance with NFPA Standard 855 or similar standards and provide fire-suppression systems designed specifically for battery storage. Approval also requires demonstrating that fire suppression, containment, ventilation, and evacuation procedures sufficiently protect public health, safety, and welfare.

  • Building facades facing a road or an existing residential use must include at least two specified design elements—changes in materials, pattern, texture, or color; changes in building height; or step-backs or recesses at least five feet deep—every 150 horizontal feet.

  • Data centers must provide at least one parking space per 8,000 square feet of floor area designed and intended for regular employee access, or one space per employee at the largest shift, whichever requirement is lesser.

Benefits & exceptionsHide benefits & exceptions7
  • Data centers are allowed in the IND Industrial District through the special-exception approval process. Permitted as a use by special exception

  • Required parking is limited to one space per 8,000 square feet of regularly employee-accessible floor area or one space per employee on the largest shift, whichever is fewer. Whichever is lesser

  • The required landscape buffer may count toward the required setback, avoiding a separate buffer area beyond that setback. May be part of the minimum setback distance

  • Where existing vegetation and/or topography is adequate to meet the buffer’s screening purpose, the Council may count it as all or part of the required buffer, on recommendation from the Borough Engineer and Planning Commission. May determine that existing topography and/or vegetation constitutes all or part

  • Cooling, ventilation, and power-supply equipment within 150 feet of a roadway or sensitive receptor need not be fully enclosed if enclosure is mechanically infeasible under the manufacturer’s specifications; it must instead be fully screened by one or more listed methods. Except where not mechanically feasible

  • Roadside fencing need not meet the restrictions on chain-link fencing and visually intrusive deterrents if it is fully screened using one or more of the specified screening methods. Applicant shall not be required to comply

  • The data-center noise limits do not apply during power outages, although sound studies must still report anticipated levels with all emergency generators running. Maximum decibel levels specified herein shall not apply during times of power outage

Sources

current law · West Homestead Borough
These rules are in Section 27-1125 of the restated zoning ordinance, Ordinance No. 745, which Borough Council adopted on January 13, 2026.West Homestead Borough, Allegheny County — data-center ordinance (No. 745)

What this means

The measure imposes noise limits and sound testing, setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements14
  • 67 dBA day, 57 dBA night at property line, § 27-1125(6)(A)

  • Section 27-1125(6)(A) to (D) require preliminary, interim (building permit), and as-built sound studies six months after occupancy using ANSI S1.4 meters and generally accepted methodology, but the limits apply during normal operations and the as-built study is not required at full operating load.

  • Water feasibility study if nonpublic water, § 27-1125(7)(B)

  • Projected water demand disclosed in feasibility study, § 27-1125(7)(B)(1)

  • Wastewater disposal, including cooling water, approved by SEO or DEP, § 27-1125(7)(B)(11)

  • Power generation is a separate use with its own approval, § 27-1125(8)(B).

  • Known electric rate impacts must be noted, § 27-1125(8)(A)

  • 25 ft landscape buffer, § 27-1125(4)(A)

  • Equipment within 150 ft of road or sensitive receptor enclosed or screened, § 27-1125(5)

  • Emergency Response Plan reviewed by fire department, § 27-1125(9)(A)

  • Plan must ensure first responder training, § 27-1125(9)(A)(4)

  • Annual fire safety inspections, § 27-1125(9)(A)(5)

  • As-built sound study after opening, § 27-1125(6)(D)

  • Exceeding limits is a violation of the chapter, § 27-1125(6)(D)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the IND district