Borough of West Hazleton
Slightly Anti-Data Center Policies
West Hazleton allows data centers only in industrial zones, with setbacks, water and electricity planning, cooling rules, and noise limits that can constrain sites and designs. It does not ban them; whether all requirements make projects broadly impractical is unclear.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Borough of West HazletonProposes allowing data centers in West Hazleton’s heavy-industrial zones, with possible approval as a special exception in light-industrial zones; the amendment had not yet been adopted.West Hazleton data center zoning restriction (unlisted use)
What this means
The proposed amendment would make data centers an allowed use in M2 heavy-industrial zones, giving developers a clearer path to build and operate them. But it would not open all areas to data centers, and the request to allow them in M1 zones as a special exception was still under consideration (M2-zone proposal and M1 request).
Benefits & exceptionsHide benefits & exceptions1
The proposed amendment would allow data centers in M2 zones, which are designated for heavy industrial use (allow data centers in an M2 zone).
Sources
current law · Borough of West HazletonRestricts data centers to industrial zones and requires plans for water and electricity use to avoid significantly affecting residents.West Hazleton Borough data center zoning ordinance (adopted October 13, 2026)
What this means
The measure would limit data centers to industrial zones and require plans for water and electricity use, adding real siting and planning hurdles. But it does not ban data centers, and the sources give no detail suggesting the requirements would make projects broadly impractical.
People behind it
- West Hazleton Borough Council
Began drafting the data center ordinance and adopted it.
Restrictions & requirementsHide restrictions & requirements2
Data center construction is limited to industrial zones.
Data centers must provide water- and electricity-usage plans intended to ensure their operation will not significantly affect West Hazleton residents.
Benefits & exceptionsHide benefits & exceptions1
Data centers may be constructed in industrial zones, provided they submit water- and electricity-use plans intended to prevent significant impacts on residents.
Sources
current law · West Hazleton BoroughThe rules are in Ordinance No. 6 of 2026, which Borough Council adopted 7 to 0 on October 13, 2026 after a public hearing the same evening, adding § 420-86 to the zoning ordinance.West Hazleton Borough, Luzerne County — data-center ordinance (No. 6 of 2026)
What this means
The measure imposes setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. The limits sharply reduce usable sites or workable project designs, making development substantially harder despite an available approval route.
Restrictions & requirementsHide restrictions & requirements37
Conditional use in M-2 only; schedule marks N in R-1, R-2, B-1 and M-1 and limits listed uses to the noted districts, § 420-16
Conditional use before the Planning Commission and Borough Council; no lapse provision, § 420-16 and § 420-86.N
Agricultural lands are sensitive receptors subject to setbacks, but data centers are not barred on preserved farmland, § 420-12 and § 420-86.A(1)
Sensitive receptors include schools, day care, hospitals and parks, protected by the 1,500 and 2,500 ft setbacks, § 420-12 and § 420-86.A(1)
100 ft maximum with roof equipment limited to 4 ft above; relation to the M-2 limit not stated and rooftop screening only within 300 ft of roads or residential areas, § 420-86.A(2) and B(3)
300 ft setback from water bodies, streams and wetlands, plus an Environmental Impact Statement; no wider buffer on steep slopes, § 420-86.A(1)(c)[2] and J(2)
Campus on contiguous parcels regulated as one integrated use; no separation between campuses or combined limits, § 420-12
§ 420-48.B table limits plus ambient plus 10 dBA, measured under ANSI S1.4 and § 420-48.C; no separate day and night values in the text, § 420-86.C(1)-(2)
Infrasound limited to 90 dBZ and tonal analysis under ISO/TS 20065; no dBC or octave-band limits, § 420-86.C(1) and C(2)(c)
Preliminary study at land development, interim study at building permit, and as-built study six months after occupancy, by ANSI S1.4 and § 420-48.C methods, § 420-86.C(2)
Vibration study showing no vibration above the perception threshold of § 420-49 at the property line; perception-based standard, § 420-86.C(3)
Public water required for cooling where available, with will-serve letter; nonpublic supply needs a feasibility study without pump tests, § 420-86.D(1)-(2)
Closed-loop cooling required unless an alternative uses less water and energy; no water-use rate or noise showing for evaporative systems, § 420-86.D(4)
Drought contingency plan when the Borough or County declares a drought water shortage; no metered use reporting, § 420-86.D(5)
Wastewater Disposal Analysis with Code Officer and DEP approval, authority certification, and no approvals until state and regional permits are obtained, § 420-86.D(6)-(7)
Diesel generators must be Tier IV with annual testing and reports to the county and municipality on emissions, § 420-86.E(7)(a) and (c)
Thermal Impact Mitigation Plan evaluating off-site thermal impacts and waste heat reuse, certified by a Professional Engineer, § 420-86.K
Electronic Waste Plan for servers, batteries and hazardous materials; no disposal contract kept in effect, § 420-86.L
Utility will-serve and capacity letter, proof of filed application and paid fees, and signed transmission security agreement before the application is complete, § 420-86.E(1) and N
Energy Usage Plan required without stated contents, and on-site solar to offset at least 25 percent of annual use, § 420-86.E(3)-(5)
On-site generation for normal operation is a separate conditional use under its own regulations and subject to the data center setbacks, § 420-86.A(1) and E(4)(a), E(6)
Substations to the side or rear, screened by an 8 ft wall or fence and opaque landscaping, 500 ft from homes; no line burial, § 420-86.E(2)
Battery storage must comply with NFPA 855 and include dedicated fire suppression, § 420-86.F(3)(b)
Rate and availability impacts must be noted and a signed transmission security agreement provided; upgrade costs and cost assignment not required, § 420-86.E(1)
50 ft landscape buffer with berm, evergreen plantings and replacement within 18 months, § 420-86.B(1)-(2)
Full-cutoff, downward fixtures with no light source visible from adjacent residences; no limit on light crossing the property line, § 420-86.G(6)
Equipment within 300 ft of roads, residential districts or sensitive receptors must be enclosed or screened; not all equipment on all sides, § 420-86.B(3)
Elevations and renderings of facades visible off-site required; no visual impact study, § 420-86.G(7)
ERP must ensure responder training specific to the installed system; no annual training at the applicant's cost or equipment requirement, § 420-86.F(1)(d) and F(5)
Fuel tanks subject to equipment setbacks and bulk fuel storage under § 420-81; no spill response plan filed, § 420-86.A(1) and E(8)
Annual fire safety inspections with deficiencies corrected within a set time, but reports submitted only on request, § 420-86.F(1)(e)-(h)
Decommissioning plan with security of at least 100 percent, starting within 12 months of cessation and finished within 18 months; below 110 percent and no recorded agreement, § 420-86.I
New cost estimate every five years with security increased; no update after the first year, § 420-86.I(3)
As-built sound study after opening and annual generator testing reports; no ongoing noise, water or power reports, § 420-86.C(2)(a)[3] and E(7)(c)
As-built sound violations are ordinance violations and injunctive relief for decommissioning; no revocation grounds, § 420-86.C(2)(a)[3] and I(4)
Borough Engineer and Council review of energy, thermal and waste plans; consultant review cost not assigned to the applicant, § 420-86.E(3), K(7) and L(2)
Applicant public meeting before the first Council or Planning Commission meeting and a project website kept from two weeks before through final land development approval, § 420-86.M
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the M-2 district
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data