Borough of West Chester

Anti-Data Center Policies

West Chester borough’s enacted ordinance limits noise, requires sound testing and setbacks from protected places, and sets minimum site sizes; data centers may still be approved, but face added costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · West Chester Borough
Regulates where data centers may be located and how they may operate in West Chester Borough.Ordinance No. 05-2026 adding § 112-917, Data center and data center campus
current law · West Chester Borough
The current rules are in Ordinance No. 05-2026, which Borough Council adopted on July 15, 2026.West Chester Borough, Chester County — data-center ordinance (No. 05-2026)

What this means

The measure imposes noise limits and sound testing, setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements21
  • Conditional use; no approval expiration found, § 112-917.D

  • 60-ft height limit, § 112-311.B

  • 55 dBA day and 45 dBA night for residential receivers, § 112-917.F Table 2

  • Section 112-917.F, Table 6, treats an increase of 3 dBA or more above the baseline ambient level documented before construction as a violation, measured with a Type 1 or Type 2 ANSI meter (Table 5), but the baseline is not defined as L90 and no floor is set below which the cap does not apply.

  • 70 dBC day and 60 dBC night, § 112-917.F Table 3

  • Pre-construction and 180-day post-construction studies, § 112-917.F

  • 65 VdB perception limit with studies, § 112-917.F(3)(f)

  • Public water required; groundwater not primary cooling source; no pump tests, § 112-917.G

  • Air-cooled or closed-loop required; cooling towers allowed with legionella plan, § 112-917.G

  • Daily and annual estimates and drought plan; no cap or reporting, § 112-917.G

  • Tier 4 generators with annual testing reports, § 112-917.E(7)

  • E-waste plan for servers, batteries, and hazardous materials, approved by the borough, § 112-917.L.

  • Utility application and transmission security agreement; no inspection, § 112-917.E(6)

  • Energy usage plan; renewables encouraged only, § 112-917.E

  • 10-ft buffer strip next to residential districts, § 112-311.C

  • Equipment screened on all sides, § 112-917.C

  • Emergency plan accepted by fire officials, 24-hour signs, radio coverage; no annual update, § 112-917.J

  • Annual fire safety inspections, § 112-917.J(1)(e)

  • Construction traffic plan with access times; no bond, § 112-917.K

  • Plan, closure notice, 18-month removal; security optional, § 112-917.M

  • One post-construction noise study, § 112-917.F(3)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the ID Industrial district