Loading map…

West Caln Township

Anti-Data Center Policies

West Caln Township’s enacted ordinance requires data centers to meet minimum site sizes and keep away from homes and other protected places, increasing costs; approval remains possible.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · West Caln Township
The current rules are in the township's new zoning chapter (Chapter 350), which the Board of Supervisors adopted as Ordinance No. 2026-01 on June 17, 2026.West Caln Township, Chester County — data-center ordinance (No. 2026-01)

What this means

The measure imposes setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements22
  • Environmental impact study required, § 350-1141.B(14)

  • Section 350-1141.B(15) applies Section 350-1214.E to data centers, and Section 350-1214.E(1) limits 5-minute LAeq sound at any location on a residential receiving property to 50 dBA by day and 45 dBA at night, measured by an acoustical engineer with a Type 1 meter under ANSI/ASA S1.13-2020 and S12.18-1994.

  • 60 dBC day and 55 dBC night, § 350-1214.E

  • Sound modeling and as-built study 6 months after occupancy, § 350-1141.B(15)

  • ISO residential vibration curve with studies, § 350-1214.G.

  • Public water and provider capacity letter, § 350-1141.B(16)

  • Closed-loop cooling encouraged only, § 350-1141.B(16)(a)

  • Utility capacity letter with application; no inspection, § 350-1141.B(17)(b).

  • Power use documentation required, § 350-1141.B(17)(a)

  • Known electric rate impacts must be disclosed, § 350-1141.B(17)

  • 100-ft intensive buffer on all lines, § 350-1141.B(7).

  • Equipment fully enclosed or screened, § 350-1141.B(12)

  • Architectural renderings required, § 350-1141.B(11)

  • Emergency plan reviewed by fire department, radio coverage, 24-hour contacts; no annual update, § 350-1141.B(18)

  • Hazardous materials identified in emergency plan, § 350-1141.B(18)(d)

  • Annual fire safety inspections, § 350-1141.B(18)(d)

  • Additional emergency access may be required, § 350-1141.B(18)(a)

  • Plan; security optional, § 350-1141.B(20)

  • One as-built sound and vibration study, § 350-1141.B(15)(c)

  • Section 350-1141.B(15)(f) allows the zoning permit to be rescinded if a noise or vibration violation is not remedied within 30 days, and Section 350-1141.B(15)(h) lets the Township recover its enforcement costs by lien, but no hearing precedes rescission and enforcement under Sections 616.1 and 617.2 of the Municipalities Planning Code is not cited in the data center provisions.

  • Section 350-1141.B(15)(d) lets the Township select an entity to conduct or verify any required sound or vibration study at the applicant's sole cost, but this is a verification study rather than applicant-paid consultant review of the applicant's studies in land development review.

  • Landowner and operator agreement required, § 350-1141.A

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the MP Multi-Purpose district

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data