West Brandywine Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for West Brandywine Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · West Brandywine TownshipThe township posted the task force draft for public review on September 11, 2026, and on September 17, 2026 the Board of Supervisors voted to send it to the Township Engineer to identify properties that fit its standards and recommend any changes.West Brandywine Township, Chester County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements31
Conditional use; approval expires if no filing within 6 months, Section 3.H
Section 4.B leaves the data center height blank in this draft, caps mechanical equipment at 35 feet and total height including parapet at 40 feet, and defers to the Section 200-45 exceptions; no district limit for other principal buildings appears in the text.
Riparian buffers 100 to 200 ft, plus 200-ft water resource buffer, Sections 5.D and 9
Section 3.E treats as a material modification needing a new hearing any increase in approved noise, any increase in peak electrical demand above 5% of the approved load, any increase in water use, and any new outdoor mechanical equipment or added building height or footprint, while Section 3.G exempts in-kind replacement of equal or lesser output.
Section 7.A(6) sets 45 dBA at all property lines at all times, but the ordinance states no metric, meter class, or measurement procedure for that limit.
Sections 2 and 7.C treat an increase over 3 dBA as an adverse effect and bar any increase over a baseline that exceeds the code limit, but the baseline study is not an L90 measure, no method is stated, and no floor applies.
Single 60 dBC limit, Section 7.A(6)
Baseline study with application and post-construction study, Section 7.A
Section 8.C limits generator use to emergencies, routine testing of no more than 1 hour per generator per month between 10:00 a.m. and 4:00 p.m. Monday through Friday, or as otherwise required by law.
Below human perception with studies, Section 7.A(5).
Public water required; hydrogeologist in impact analysis; no well bar, Sections 8.B and 14
Closed-loop air-cooled required; evaporative towers prohibited, Section 8.A
Section 3.L requires real-time monitoring of water use with data accessible to the Township Engineer through a web portal, and Section 8.B caps use, but no drought plan appears.
Wastewater characterization study and blowdown treatment rules, Section 8.B.4 and 7.E.6.
Section 7.E.6(b) designates the site a stormwater hotspot with structural BMPs treating 100% of runoff, and Section 11.G.3 contains fire suppression water, but no spill containment is required for fuel, generator, and transformer areas.
Tier 4 Final generators with annual reports and monitors, Section 8.C
2 degree heat island limit with modeling; no reuse review, Section 7.E.2(c)
Utility certification and interconnection agreement; no inspection, Section 8.C.
Substations screened by wall and placed behind building; lines buried, Sections 5.F, 5.G, 18.F
Section 8.C.2 requires a grid study identifying peak load and required transmission upgrades, and Sections 8.C.3 and 18.E require the applicant to fund them, but no estimated cost, tariff terms, or executed service agreement before the zoning permit is required.
8-ft planted berm; no width set, Section 6.A
Equipment enclosed and screened; no 12-ft acoustic screen rule, Sections 6.A and 7.E.1
Emergency plan approved by fire officials and 24-hour signs; no annual update or radio rule, Sections 11 and 13
Hazardous materials inventory and fire water containment, Sections 11.G and 14.B.3.
Testing every 6 months and annual fire marshal inspections, Sections 11.C and 20.B
Section 14.B.1(c) requires a traffic study in every impact analysis covering trip frequencies, construction equipment deliveries, and fuel deliveries, but states no study area reaching an arterial or interchange.
150% security; no closure notice or 6-month removal, Section 17
Section 17.A.1(c) requires the cost estimate to be updated annually, but Section 17.B only requires the security amount to be reviewed every 5 years and does not require it to be adjusted to match the updated estimate.
Annual compliance certification and real-time monitoring, Section 3.L
Section 21.D allows the Board to revoke or suspend the conditional use approval after a public hearing for habitual noncompliance, defined as three or more adjudicated violations in 24 months; Section 19.C requires written notice and a cure period; and Section 21.B sets civil penalties under MPC Section 617.2.
Section 20.A requires an Administrative Escrow at the time of application to pay township consultants who review the application and its studies and testify at hearings, which is the zoning stage.
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the L-I district
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data