Weisenberg Township does not ban data centers, but unclear industrial-district eligibility and zoning, site, and noise rules may complicate and delay approval.

current law · Weisenberg Township
Regulates land use and development generally, without setting data-center-specific rules for data centers.Weisenberg Township Zoning Ordinance

What this means

The ordinance does not ban data centers, but it does not clearly say whether they are allowed in industrial districts, making approval less predictable. Data center projects would also have to meet zoning, site, and noise rules, creating meaningful extra work and possible delays.

People behind it

  • Administers the Zoning Ordinance by hearing appeals and issuing written decisions or findings of fact.

  • Co-developed the ordinance with the Board of Supervisors and is designated to monitor future changes and make recommendations. developed by the Weisenberg Township Planning Commission

  • Co-developed and enacted the ordinance, and adopted its amendments. DULY ENACTED AND ORDAINED

Show 1 more peopleShow fewer people
  • Responsible for administering and enforcing the ordinance. administer and enforce the provisions

Restrictions & requirementsHide restrictions & requirements9
  • The ordinance does not expressly list data centers as a use. Each district is limited to its listed uses, and a special-exception use requires Zoning Hearing Board approval; a data center must qualify under a use category allowed in its district. [district use limits](https://www.weisenbergtownship.org/ordinances/zoning_ord.pdf#:~:text= no%20building%2C%20structure%2C%20lot%20or%20land%20shall%20be%20used%20for%20other%20than)

  • Construction, structural alteration, enlargement, relocation, or a change of use requires the applicable building or zoning permit, and plans and intended use must conform to the ordinance. Work generally must start within six months after permit issuance and the building must be completed within one year. For permits based on Zoning Hearing Board decisions, the permit must be issued within two years, with a one-year completion extension allowed. permit requirements and deadlines

  • District standards limit lot area and width, building and lot coverage, height, and yard dimensions; the limits vary by district and use. Several commercial and industrial use categories have a 35-foot height limit, while specified warehouse or industrial uses may reach 50 feet with an ESFR sprinkler system. district dimensional standards

  • The Environmental Protection overlay prohibits development on natural slopes of 25 percent or greater. Floodplain rules prohibit uses requiring enclosed structures, fill, or storage of materials or equipment. environmental-area restrictions

  • Road setbacks measured from the road centerline are 100 feet on regional highways, 90 feet on arterials, 80 feet on collectors, and 75 feet on local roads, unless a greater front-yard requirement applies. road setback distances

  • Buffer yards are required in specified circumstances, including 50 feet along residential-district boundaries and 10 feet between residential and nonresidential uses within a district. Required buffers must be landscaped and screened and generally cannot contain buildings, parking, or processing activity. buffer-yard requirements

  • Off-street parking must be provided according to the schedule for the applicable use; for unlisted uses, the most similar listed use governs. Commercial or industrial uses with at least 5,000 square feet of aggregate net floor area must also provide truck-loading spaces under a size-based schedule. parking and loading requirements

  • Uses must stay within specified noise limits at property lines and may not create seriously offensive vibration or light beyond the lot or conditions dangerous to public welfare. Additional exterior building illumination is generally prohibited apart from sign illumination. noise limits

  • Building and zoning permit and appeal fees are set by Township resolution. Continuing violations may incur a civil penalty of up to $500 per day, plus court costs and reasonable attorney fees. fees and penalties

Benefits & exceptionsHide benefits & exceptions4
  • If classified as a warehouse or office, a data center may be permitted in the General Commercial District; the General Industrial District also permits warehouses, offices, communications equipment buildings, and public utility facilities. The ordinance does not specify how a data center is classified, and applicable district requirements still apply. Permitted uses in the General Industrial District, permitted uses in the General Commercial District.

  • For warehouse and industrial uses in the General Commercial and General Industrial Districts, the maximum building height is 50 feet with an Early Suppression Fast Response sprinkler system; the listed minimum lot area is 40,000 square feet and minimum lot width is 120 feet. These standards apply to a data center only if it qualifies as one of those uses. Height standard.

  • Public utility facilities, including generating and switching stations, lines, pipes, and pumping stations, are permitted uses in the Light Industrial and General Industrial Districts. This applies to qualifying utility facilities, not automatically to a data center. Public utility facilities.

  • Lawfully established existing uses may continue, and existing businesses and industry may keep operating even if their zoning district does not allow the use; ownership may be transferred. Expansion of a nonconforming use is limited: its floor area or impervious area cannot increase by more than 50% over the amount when it became nonconforming, measured in aggregate. Existing businesses and industry can continue to operate, 50% expansion limit.