Watts Township

Anti-Data Center Policies

Watts Township’s enacted rules allow data centers only through conditional approval on industrial sites of at least 20 acres, with setbacks and water, noise, emergency-planning, and decommissioning requirements.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Watts Township
Requires data centers in Watts Township’s industrial district to obtain conditional-use approval and meet detailed rules for setbacks, noise, water, power, safety, environmental impacts, and decommissioning.Watts Township Ordinance No. [number not visible], “Ordinance for Data Center” (2026)

What this means

The measure would allow data centers only as conditional uses in the industrial district, on sites of at least 20 acres, with substantial setbacks and extensive review requirements (conditional-use and site rules). Water, noise, emergency-planning, and decommissioning rules—including financial security—would add major costs and hurdles, making development and operation substantially harder (water and decommissioning requirements).

People behind it

  • Enacted and ordained the ordinance amending the township zoning ordinance.

  • Attested the ordinance as Secretary.

  • Signed the ordinance on behalf of the Board of Supervisors.

Restrictions & requirementsHide restrictions & requirements27
  • Data centers and their accessory uses are allowed only as conditional uses in the Industrial District, requiring conditional-use approval; applicants must also obtain any required subdivision or land-development approval. Conditional uses

  • A site must contain at least 20 contiguous acres and be at least 250 feet wide at the building line. Minimum lot area

  • Buildings must be at least 200 feet from the front right-of-way and 75 feet from side and rear property lines. Where the site abuts a residential or agricultural zone, the common-line setback increases to 500 feet; accessory uses and structures must be 500 feet from all property lines. Yard regulations

  • Buildings may be no taller than 45 feet, including roof-mounted equipment, and accessory uses may not exceed the principal building’s maximum height. Height regulations

  • Impervious coverage is capped at 50% of the parcel, gross building coverage at 40%, and at least 20% of the lot—excluding stormwater facilities—must be green or open space. Coverage regulations

  • Exterior design is subject to requirements for architectural treatments on specified visible facades and Planning Commission approval of a natural color palette; fluorescent and metallic exterior wall colors are prohibited. Building design requirements

  • Data-center accessory equipment must be visually and audibly screened. Ground-mounted equipment screening must reach at least 12 feet; roof-mounted equipment screening is limited to 10 feet. Within 300 feet of a public roadway, another zoning district, or a sensitive receptor, specified operating equipment must be fully enclosed unless the manufacturer’s specifications make enclosure mechanically infeasible, in which case it must be screened by an allowed method. Equipment screening

  • Landscape buffer yards are required along property boundaries, with a 50-foot minimum along public streets, next to residential or agricultural districts or uses, and within 500 feet of a sensitive receptor. The ordinance specifies native tree and shrub planting quantities and requires buffers to be maintained; regulated environmental encumbrances cannot count toward the buffer. Buffer-yard requirements

  • Exterior lighting requires a lighting plan, full-cutoff or fully shielded fixtures, and illumination no greater than 0.1 foot-candles at property lines. Freestanding fixtures may not exceed 20 feet; strobing and colored lighting are prohibited, and LED color temperature may not exceed 3000kw as stated in the ordinance. Lighting limits

  • Applicants must submit pre-development and post-construction noise studies; post-construction studies are due six months after each phase reaches full occupancy, with additional studies every year at the owner’s or occupant’s expense. Normal-operation sound must not exceed 45 dBC or 45 dBA at property lines, and vibration must not exceed 0.15 inches per second at adjoining property lines. The Township may revoke zoning permits if an owner or occupant fails to remediate a sound violation. Noise-study and sound limits

  • Backup generators may be used only during outages, natural disasters, similar emergencies, and regular reliability testing and exercising. Generators exceeding the sound limits may not be tested from 8:00 p.m. to 7:00 a.m. EST; auxiliary power-system testing should occur from 8:00 a.m. to 6:00 p.m. EST. Emergency-related sound exemptions are specified, including a limited period after an emergency ends. Backup-generator definition and testing limits

  • Applicants must submit a traffic impact study. Primary access must be from an arterial or collector road; access driveways must be at least 50 feet from lot lines adjoining residential uses; and data-center equipment may not be placed between the principal data-center building and an arterial or collector street. Access requirements

  • Security fencing must be at least eight feet high, including appendages. Non-riverine water sources within the project boundary, including stormwater facilities, must be enclosed by fencing at least six feet high. Fencing requirements

  • Applicants must demonstrate a second emergency access route, submit an emergency response plan, and provide ongoing training for local fire personnel. Projects with battery or other energy storage must demonstrate compliance with NFPA Standard 855 or similar standards and include battery-specific environmentally safe fire suppression; approval also requires sufficiently protective fire-suppression, containment, ventilation, and evacuation procedures. Emergency-management requirements

  • Parking must provide one space per on-site employee for the largest two shifts, at least one tree per six spaces, and parking-lot islands or endcaps with trees. Parking lots must be at least 50 feet from lot lines adjoining residential parcels or tracts. Parking requirements

  • At least one loading space is required, loading and service areas must be screened from public streets and residential uses and located to the side or rear, and loading areas must be at least 50 feet from lot lines adjoining residential land. Access roads must be at least 26 feet wide; cul-de-sacs must be at least 120 feet in diameter; and a paved 26-foot-wide fire lane around the building must meet the ordinance’s access and clearance requirements. Loading and fire-lane requirements

  • Cooling systems must be closed-loop, and all fill water must be brought in from outside the township. Applicants must provide water-use plans and certified raw-water-needs analyses; where nonpublic water is proposed, a feasibility study must address supply and effects on nearby wells and be confirmed by the Township Engineer before final plan approval. The Township may require the developer to fund a Township-selected water study. Water-use requirements

  • A data center may not be approved without sufficient water or if it is likely to adversely affect nearby existing wells. Developers, landowners, or lessees must provide a $2.5 million bond or acceptable financial security to protect against well-supply depletion or contamination; the amount is reviewed annually for possible increase. Water-approval and bond requirements

  • Before approval of a certificate of completion or occupancy, applicants must provide written power-provider verification of adequate capacity and infrastructure, and written verification that electrical work passed inspection. Utility and power equipment must be on the Industrial District lot. Applicants must document how they intend to offset electricity consumption; an offset target of at least 25% is encouraged, not stated as mandatory. Power-supply requirements

  • The ordinance requires low-impact site-design practices, including minimizing land disturbance and impervious surfaces and maximizing tree preservation. It also requires woodland disturbance to be minimized: removal of trees at least six inches in diameter at breast height must be clearly necessary, and no more than 50% of an existing tree mass, tree line, hedgerow, or qualifying freestanding trees may be removed. Woodland-disturbance limit

  • Backup-generator emissions must comply with state and federal air-quality standards. Applicants must provide a Pennsylvania Natural Heritage Program study receipt dated within two years of the first subdivision or land-development application, plus any required agency clearance letters, and comply with measures in those letters. Air-quality and species requirements

  • A qualified professional must prepare an Environmental and Community Impact Analysis addressing specified site, environmental, infrastructure, emergency-services, school, municipal-finance, and comprehensive-plan impacts and mitigation. The ordinance also requires a stormwater management plan and an analysis of alternatives, unavoidable adverse impacts, and critical impact areas. Impact-analysis requirements

  • A PADEP blasting activity permit is required for most blasting operations. Blasting permit

  • Applicants must submit a decommissioning plan covering e-waste and hazardous materials. Before permit issuance, they must provide financial security acceptable to the municipality of at least 110% of an engineer’s decommissioning-cost estimate; estimates must be updated every ten years and after material modifications, with security adjusted accordingly. E-waste may not be buried, abandoned, or disposed of on-site. Decommissioning security and e-waste rules

  • Operators must notify the Township within 30 days after operations cease or a partial shutdown begins. A facility is presumed abandoned after 12 continuous months without demonstrable efforts to resume use; if decommissioning is not completed within 18 months after cessation or abandonment, the municipality may complete it at the property owner’s expense. Shutdown and abandonment deadlines

  • Conditional-use applicants bear the burden of showing compliance, must submit a development plan and specified supporting information, and must undergo a public hearing before the Board of Supervisors. The Planning Commission reviews the application and forwards recommendations within 30 days of receipt. Conditional-use procedure

  • Applicants must pay the filing fee and costs of required public hearings, including advertising and Township solicitor, engineer, planner, stenographer, and transcript costs. The Township may not issue a building or other required permit until those costs are paid in full. Application costs and payment requirement

Benefits & exceptionsHide benefits & exceptions4
  • Data centers and their accessory uses may be proposed as conditional uses in the Industrial District, subject to the ordinance’s criteria and approval process (“are conditional uses”).

  • The ordinance recognizes supporting systems—including substations, pump stations, cooling systems, backup power, and communications—as data-center accessory uses when located on the same tract or adjacent parcels developed as a unified project. Those uses are included in the Industrial District conditional-use provision (“utilities, utility lines, electrical substations”).

  • A Data Center Park may be developed for three or more data centers, with sub-lots eligible to become independent tax parcels; the park must be an integrated development exclusively for data centers and comply with applicable zoning and subdivision rules (“sub-lots to be subdivided as independent tax parcels”).

  • Backup generators and other defined non-coal backup equipment may provide power during outages, natural disasters, or similar emergencies, and may be used for regular reliability testing and exercising (“only to be used during periods of outages”).

Sources

current law · Watts Township
The current rules are in Ordinance 26-01, which the Board of Supervisors enacted on June 25, 2026, and the developer MRP Industrial has since challenged it through curative amendments and a land use appeal in the Perry County court.Watts Township, Perry County — data-center ordinance (No. 26-01)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements29
  • Conditional use with Board of Supervisors hearing, § 363.18 and § 618.D; no approval expiration

  • Buffer yard near sensitive receptors but no setback distance, § 495.G

  • Environmental and Community Impact Analysis required, § 495.U

  • Single 45 dBA limit at property lines, § 495.J.2

  • Pre-development study but no background cap, § 495.J.1

  • 45 dBC limit at property lines, § 495.J.2

  • Studies with the application and 6 months after occupancy; none at building permit, § 495.J.1

  • Water feasibility study and fill water from outside the township; no pump tests, § 495.O

  • Closed loop required; evaporative cooling not restricted, § 495.O.1

  • Water consumption plan only, § 495.O.3

  • Removed water handled per EPA guidelines, § 495.O.1

  • Stormwater management plan required, § 495.U.5.b

  • Generators must meet state and federal emission standards, § 495.S

  • Heat island impacts must be described, § 495.U.5

  • Written utility capacity verification and electrical inspection are due only before the certificate of completion or occupancy, later than the building permit, § 495.P.1.

  • Plan to offset electric use required; renewables encouraged only, § 495.P.2 and § 495.Q

  • Substations screened as part of the use; line burial not addressed, § 495.G.1

  • 50-ft planted buffer next to residential or agricultural land, § 495.G.2

  • Equipment screened on all sides, 12 ft for ground equipment, with audible screening, § 495.G.1.

  • Emergency Response Plan by a qualified professional, § 495.L.2

  • Developer must provide fire personnel training on a continuing basis, § 495.L.5.

  • Types of materials stored must be described, § 495.U.1

  • Electrical inspection before occupancy; no annual inspections, § 495.P.1

  • Section 495.K.1 requires a traffic impact study to document potential impacts and necessary mitigation, but it does not cover construction traffic or set a study area reaching the nearest arterial or interchange.

  • 110% security and 30-day notice, but 18-month removal period, § 495.W

  • Annual noise studies at owner expense, § 495.J.1.d

  • Section 495.J.1.e allows the Township to revoke zoning permits when a sound violation is not remedied, but no notice or hearing precedes revocation.

  • Board may require a developer-funded township water study; no general review at applicant cost, § 495.O.6

  • Owner and operator affidavit for decommissioning; end user not required, § 495.W.2.a

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data