Washington Township
Anti-Data Center Policies
Washington Township’s enacted rules allow data centers by special exception in three commercial and industrial districts, subject to setbacks, site-size limits, and detailed operating reviews and conditions.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Washington TownshipOne text describes Ordinance O015-2026 as amending Chapter 285 and adding data centers to the uses prohibited in all zoning districts (amends Chapter 285; prohibited in all zoning districts).Washington Township Ordinance O015-2026
What this means
The township adopted an AI data center ordinance, and the notice describes a pathway to approval by special exception in three commercial and industrial districts. But it also lists many data-center-specific reviews and operating conditions, including noise, water, power, environmental impacts, and decommissioning, adding meaningful costs and delay (special-exception approval and requirements); the minutes record the ordinance’s adoption (adopt the AI Data Center Ordinance).
People behind it
- Township Council of Washington Township, Gloucester County, New Jersey
Introduced and adopted Ordinance 0015-2026 amending the Township zoning code to define data centers and prohibit them in all districts.
- Christine Ciallella
Township Clerk who attested the ordinance and was directed to publish notice of its passage and file copies with the required agencies.
- Anthony DellaPia
Mayor who approved Ordinance 0015-2026.
Show 3 more peopleShow fewer people
- Board of Supervisors of Washington Township, Berks County, Pennsylvania
Proposed and adopted the zoning-ordinance amendment regulating data centers and data-center accessory uses.
- Romnie Long
Moved adoption of the Pennsylvania AI Data Center Ordinance No. 2026-1.
- Thomas Powanda
Seconded the motion to adopt the Pennsylvania AI Data Center Ordinance No. 2026-1.
Restrictions & requirementsHide restrictions & requirements12
Washington Township, Gloucester County, New Jersey prohibits data centers in all zoning districts.
The New Jersey ordinance applies the prohibition broadly to data centers and functionally equivalent uses, structures, or facilities, including facilities supporting cloud services, streaming, cryptocurrency mining, artificial intelligence, machine learning, and other computing or data-storage purposes.
The New Jersey ordinance does not take effect immediately; it becomes effective 30 days after final passage by the Township Council or 20 days after mayoral approval, whichever occurs first.
Before adoption, the New Jersey ordinance must be referred to the Township Planning Board for review, and the Planning Board has 35 days after referral to report on whether the proposal is substantially consistent with the Master Plan.
Washington Township, Berks County, Pennsylvania allows data centers and data center accessory uses only by special exception in the C-Commercial, LI-Light Industrial, and GI-General Industrial districts, creating an additional zoning approval requirement.
The Pennsylvania amendment imposes dimensional standards, landscape buffers, and screening and fencing requirements on data centers and data center accessory uses.
The Pennsylvania amendment imposes noise, vibration, and other performance standards, together with post-construction verification and ongoing compliance requirements.
The Pennsylvania amendment requires review of potential negative impacts and an environmental and community impact analysis.
The Pennsylvania amendment establishes requirements concerning water and sewer service, power supply, safety, emergency planning, spill prevention, and pollution prevention and control plans.
The Pennsylvania amendment establishes requirements for electronic-waste disposal and emergency contact information.
The Pennsylvania amendment establishes requirements for parking, off-street loading, lighting, and project phasing.
The Pennsylvania amendment requires a decommissioning plan for data centers and data center accessory uses.
Benefits & exceptionsHide benefits & exceptions1
Allows data centers and data center accessory uses in the C-Commercial, LI-Light Industrial, and GI-General Industrial districts through the special-exception approval process, subject to the ordinance’s additional requirements.
Sources
current law · Washington TownshipThe current rules are in Ordinance 2026-1, which the Board of Supervisors adopted on May 28, 2026 after a public hearing, and the Supervisors held a hearing scheduled for October 22, 2026 on an amendment to the water and sewer, power supply, and decommissioning requirements, whose outcome had not been posted as of October 29, 2026.Washington Township, Berks County — data-center ordinance (No. 2026-1)
What this means
The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements28
District height limit including roof equipment, § 131-82.B(1).
200-ft setback from streams and wetlands and an environmental impact analysis; not a planted riparian buffer, § 131-82.B(4)(d) and Q
Phasing allowed under the subdivision ordinance; no phasing plan or new approval, § 131-82.P
Section 131-82.E(2)(a) bars facility sound above the pre-existing ambient Leq set by a 48-hour baseline study at the property line, but the baseline is an Leq rather than an L90 and no floor is set below which the cap does not apply.
Low-frequency noise addressed separately; no dBC limit, § 131-82.E(2)(c)
Sound study before approval and a post-construction study within 180 days; none at building permit, § 131-82.E(1) and (3)
Water feasibility study; no bar on wells for cooling, § 131-82.G(5)
Closed-loop cooling required; evaporative cooling not restricted, § 131-82.G(3)
Projected water demand disclosed, § 131-82.G(5)(a)
Cooling blowdown discharge managed in a pollution prevention plan and industrial user permit before connection, § 131-82.G(6) and J(3)(g).
Section 131-82.J(3)(f) requires contaminated stormwater from fueling, transformer, and other pollution sources to be routed through oil and water separators or equivalent treatment, and Section 131-82.J(2)(d) requires secondary containment sized to 110 percent of the largest tank for all tanks and transfer areas, with spill kits at fuel locations.
Electronic waste plan for servers, batteries, and hazardous materials; refrigerants not named, § 131-82.K
Utility certification of capacity; no electrical inspection, § 131-82.H(1).
Power supply equipment enclosed or screened, § 131-82.D(1)
Section 131-82.H(1) requires a utility capacity certification and an assessment of impacts on rates and availability and, where capacity is insufficient, the system improvements the applicant must provide at its own expense.
Landscape buffer under the subdivision ordinance; no width stated, § 131-82.C
Screen materials must match the building only; no design standards, § 131-82.D(1)(e)
Ground and roof equipment fully enclosed or screened to reduce noise; no 12-ft height, § 131-82.D(1)
Emergency response plan accepted by the fire department, with emergency contacts; no annual updates or radio coverage, § 131-82.J(1) and L
Plan must ensure first responder training, § 131-82.J(1)(d)
Spill prevention plan with 110 percent secondary containment; no storage setbacks, § 131-82.J(2)
Annual fire safety inspections by a qualified professional, § 131-82.J(1)(e)
Vehicle trips described in the impact analysis only; no traffic study, § 131-82.Q(1)(a)
Decommissioning within 6 months with 100 percent security net of salvage; not 110 percent, § 131-82.R
One post-construction sound verification study, § 131-82.E(3)
Corrective measures within 30 days and injunctive relief for decommissioning, § 131-82.E(3)(b) and R(4)
Section 131-82.G(5)(k) lets the Township retain professionals at the applicant's cost to review water impact studies and plans, with compliance shown before preliminary plan approval (Section 131-82.P), but applicant-paid review does not extend to the sound, traffic, and other required studies.
Owner and operator contact given to emergency services only; no disclosure before approval, § 131-82.L
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the C, LI, and GI districts (amendment pending)
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data