Warwick Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Warwick Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Warwick TownshipThe draft ordinance is unnumbered and undated, the Township Manager gave it to the Planning Commission on July 22, 2026, and the township reported on October 26, 2026 that no public meetings were scheduled to review it.Warwick Township, Lancaster County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements26
Conditional use approval; no one-year expiration of approval, Section 2
Only stream locations in the water feasibility study; no environmental assessment or riparian buffer, § 340-65.1 H(1)
60 dBA day and 55 dBA night at the property line, above the 50 and 45 dBA standard, § 340-42.B
65 dBC day and 60 dBC night, above the 60 and 55 dBC standard, with low-frequency analysis in the noise studies, § 340-42.B and C(1)-(2)
Pre-construction study with the initial plan submittal and post-construction study after occupancy; no building permit study, § 340-42.C(1)-(2)
Generator testing limited to 7:00 a.m. to 7:00 p.m. at 80 dBA; no weekday limit or hours cap, § 340-42.B(2)(a)
Water feasibility study of supply and impacts on nearby wells; wells for cooling not barred and no pump tests, § 340-65.1 H(1)(a)
The water feasibility study clause states that closed loop geothermal systems are required, but evaporative cooling is not expressly restricted, § 340-65.1 H(1)(a)[1]
Projected water needs by purpose disclosed, with SRBC approval for large withdrawals; no cap, reporting, or drought plan, § 340-65.1 H(1)(a)-(b)
Disposal of wastewater used for cooling must be provided and approved by the Sewage Enforcement Officer or DEP with the conditional use application, § 340-65.1 H(6)
Emissions must meet state and federal standards; no Tier 4 requirement, § 340-65.1 H(3)
Decommissioning plan covers removal and recycling of server infrastructure, hazardous materials, and batteries; refrigerants not named, § 340-65.1 H(5)(a)
Electric provider documentation certifying available capacity; no third-party electrical inspection, § 340-65.1 H(7).
Substations counted as accessory uses and screened on all sides; no side or rear placement or buried lines, Section 1 and § 340-65.1 D(1)
Section 340-65.1 H(7) requires a capacity certification from the electric provider, a note of known rate impacts, and makes the applicant responsible for any required electrical service upgrades, but the required upgrades are not identified or disclosed.
Fixtures fully shielded or cutoff and directed downward and inward, with a 25 ft mounting limit; no bar on light crossing the property line, § 340-65.1 E(1)
Visual screening on all sides to 12 ft for ground equipment and 10 ft for roof equipment, plus audible screening, § 340-65.1 D(1).
Emergency Response Plan reviewed and accepted by local emergency management, with annual fire safety inspections; no annual updates, radio coverage, or posted 24-hour contacts, § 340-65.1 H(8)
Plan must include training procedures for first responders; funding not required, § 340-65.1 H(8)(f)
Battery storage secondary containment sized at 110% of worst-case firefighting effluent; no hazardous materials storage setbacks, § 340-65.1 H(4)
Annual fire safety inspections by a qualified professional; no third-party electrical inspection, § 340-65.1 H(8)(g)
Section 340-65.1 G requires a traffic impact analysis under Zoning Section 340-44 and SALDO Section 285-14, but the data center provisions do not require coverage of construction traffic or a study area reaching the nearest arterial or interchange.
Recorded decommissioning agreement with a bond of 5% of assessed value; no 110% security, closure notice, or removal deadline, § 340-65.1 H(5)(c)
One post-construction noise study and vibration study, with 24-hour sound monitoring equipment but no reporting, § 340-42.B(1)(b) and C(2), (5)
Section 340-42.C(3) and (5) rescind the Certificate of Occupancy when required noise or vibration mitigation is not completed, but no notice or hearing precedes the rescission.
Owner and operator must attest to cleanup responsibility in the application, and the decommissioning party must be named; end user not required, § 340-65.1 H(10) and H(5)(b)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the I-1 Industrial Zone
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data