Warwick Township
Anti-Data Center Policies
Warwick Township’s enacted ordinance sets cooling, water-use, setback, and water-supply requirements for data centers, increasing construction and compliance costs, but still allowing approval.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Warwick TownshipThe current rules are in Ordinance No. 1-2026, which the Board of Supervisors adopted on April 1, 2026.Warwick Township, Chester County — data-center ordinance (No. 1-2026)
What this means
The measure imposes cooling and water-use rules, setbacks from homes or other protected places and water-supply requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements14
Permitted use for closed-loop centers; special exception only for open-loop, § 1928.P
Base height rules of § 1903 apply, § 1928.A.4
65 dBA at all times at adjoining lot lines, § 1928.H
Vibration study showing none past the property line, § 1928.I.4.
Water supply feasibility study; well inventory for open-loop centers, § 1928.I.1 and P.3
Projected water needs required for open-loop centers, § 1928.P.3
Section 1928.I.3 requires the applicant to show that disposal of domestic and cooling or industrial wastewater has been provided for and approved by the Sewage Enforcement Officer or PA DEP, but it does not state that the approval must be in hand before the zoning permit.
Tier IV generators; no annual testing, § 1928.I.5
Battery systems considered in fire plan under building code, § 1928.I.6
Berm and planted buffer; no width, § 1928.F.7
Equipment screened, § 1928.F.6
Emergency plan approved by the fire company, § 1928.I.6
Section 1928.G requires a traffic impact study with the land development application covering daily operational traffic and emergency response access, but it does not cover construction traffic or set a study area reaching the nearest arterial or interchange.
Agreement with financial security, 12-month restoration, § 1928.K
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Permitted in the I Industrial District (open-loop by special exception)