Wallace Township

Anti-Data Center Policies

Wallace Township’s enacted ordinance requires setbacks from protected places, minimum site sizes, and cooling and water-use controls, while retaining an approval route that narrows where and how data centers can operate.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Wallace Township
The Board of Supervisors enacted Ordinance No. 186 on July 9, 2026, according to the signed copy provided by the township manager, and the text is not posted online.Wallace Township, Chester County — data-center ordinance (No. 186)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements23
  • Conditional use reviewed by the Board of Supervisors; no one-year expiration of approval, § 1328

  • 35 ft maximum for buildings and other structures; no separate rooftop equipment limit, § 1328A(3)

  • Community and environmental impact statement covering water quality, groundwater, and wildlife habitat, § 1328K(3)

  • 55 dBA day and 45 dBA night Leq at residential uses; day limit above 50 dBA, § 1328E(9) Table 2

  • Section 1328E(5) and Table 6 treat an increase of 3 dBA or more above the pre-construction baseline ambient level as a violation, with Type 1 or Type 2 meters in Table 5, but the baseline is not an L90 measure and the cap applies only where the baseline already exceeds the fixed limits.

  • 70 dBC day and 60 dBC night at the nearest property line, § 1328E(9) Table 3

  • Noise studies with the conditional use application and within 180 days after operations begin; none at building permit, § 1328E(1) and (3)

  • Vibration limits of 0.2 to 0.5 in/s PPV and 65 VdB with pre- and post-construction studies, § 1328E(1) and (3)(f)

  • Air-cooled or closed-loop cooling required unless an alternative uses less water and energy, § 1328F(4).

  • Daily and annual water use estimates and a drought response plan; no cap or ongoing reporting, § 1328F(1) and (5)

  • Diesel generators must meet EPA Tier 4 with annual testing reports to the Township, § 1328H(2)(a)-(b)

  • Decommissioning plan covers disposal or recycling of materials; no specific e-waste plan, § 1328J(2)

  • Utility feasibility evidence and interconnection documentation with the application; no electrical inspection, § 1328B and H(1)(f).

  • Energy usage plan with documented renewable efforts; no on-site renewable requirement, § 1328H(1)

  • Backup generation addressed, enclosed, and limited; generation for normal power not addressed, § 1328H(2)

  • Equipment screened on all sides and generators in sound-attenuating buildings; no 12-ft standard, § 1328D(1) and H(2)(d)

  • Elevations and renderings of principal facades required with the application, § 1328D(2)

  • Emergency response plan accepted by the fire department; no annual updates, radio coverage, or posted contacts, § 1328I(1)

  • Annual fire safety inspections by a qualified professional, § 1328I(1)(e)

  • Impact statement describes vehicle trips; no traffic study required, § 1328K(1)

  • Construction plan sets times and locations for construction vehicle access; no road bond, § 1328J(1)

  • Decommissioning plan, removal within 18 months, and security only at Township option, § 1328J(2)

  • One post-construction noise and vibration study within 180 days, § 1328E(3)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data