Borough of Vandling
Anti-Data Center Policies
Vandling borough’s enacted ordinance requires data centers to keep setbacks from homes and other protected places and meet noise limits, including sound testing. An approval route remains, but these limits significantly restrict suitable sites and operations.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Vandling BoroughThe current rules are in Ordinance No. 1 of 2026, which Borough Council adopted on June 15, 2026.Vandling Borough, Lackawanna County — data-center ordinance (No. 1 Of 2026)
What this means
The measure imposes setbacks from homes or other protected places and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements23
500-ft front, side, and rear yard setbacks, Setbacks table
500-ft yard setbacks protect all neighboring uses; below 1,000 ft, Setbacks table
Base nonresidential height limits apply; a variance is needed to exceed them, Height
Water study maps streams; no riparian buffer or impact assessment
55 dBA day and 45 dBA night at residential lot lines; 65 dBA at commercial and industrial lines, Sound and Vibration
The Sound and Vibration section, items A to C, requires a preliminary sound study with the special exception application, an interim study with building permit plans, and an as-built study six months after the certificate of occupancy, but no measurement method is stated and the as-built study is not required at full operating load.
Generator noise evaluated; no testing limits, Sound and Vibration D
Vibration study showing none perceptible past property lines, Sound and Vibration E.
Water feasibility study and hydrologist analysis of raw water needs; no bar on wells for cooling, Water and Sewer Service
Projected water needs disclosed, Water and Sewer Service
Sewer service letter and disclosure of how water will be released; no cooling discharge approval, Water and Sewer Service
Emissions compliance required, Environmental Requirements
Decommissioning plan must address electronic waste, Environmental Requirements
Utility certification of capacity; no electrical inspection, Power Supply A.
Emergency plan must include NFPA 855 compliance; no battery-specific suppression, Emergency Management
Emergency response plan reviewed in the special exception process; no fire company review, annual update, radio, or 24-hour contacts, Emergency Management
Emergency plan must address responder training; no funding, Emergency Management
Hazardous materials addressed only in the decommissioning plan
Annual inspections required in the emergency plan, Emergency Management
Primary access from an arterial or collector street and emergency access routes with Knox-Box devices, Access and Security A and B
Decommissioning plan without financial security, Environmental Requirements
One as-built sound study six months after occupancy, Sound and Vibration C
Water and Sewer Service item 3 allows the Borough to require the developer to fund a water study done on the Borough's behalf by an entity the Borough selects, but no provision has the applicant pay for the Borough's consultants to review its other studies in land development review.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Special exception in the M-1 and M-2 industrial districts