Uwchlan Township
Neutral Data Center Policies
Uwchlan Township allows data centers in designated districts through special or conditional-use review, providing a defined approval route but adding a step that may bring delay and uncertainty.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Uwchlan TownshipThe current rules are in Ordinance 2026-08, the Industrial Uses Ordinance, which the Board of Supervisors adopted on August 10, 2026.Uwchlan Township, Chester County — data-center ordinance (No. 2026-08)
What this means
The measure provides a route for data centers through a special permit or conditional-use review in designated districts. That offers legal certainty, but the extra approval step can add time and uncertainty.
Restrictions & requirementsHide restrictions & requirements24
150 ft riparian buffer, § 621.603.C
Section 621.602.F sets 45 dBA from 7:00 a.m. to 7:00 p.m. and 40 dBA at night at the property line under representative worst-case operating conditions, but it names no metric, meter class, or measurement standard.
60 dBC day, 50 dBC night, § 621.602.F
Pre-construction and post-occupancy studies, § 621.602.A, B
Public water only as primary source; no well study, § 621.604.K(1)
Closed-loop without evaporative cooling, § 621.604.K(2)
Drought response plan; no cap or water reporting, § 621.604.K(5)
Tier 4 generators with annual testing reports, § 621.604.G, H
Thermal impact plan with waste heat reuse review, § 621.605.
Electronic waste plan; refrigerants in decommissioning, § 621.609 and § 621.610.
Utility letters and interconnection documents; no electrical inspection, § 621.604.B, D(6).
Energy usage plan; solar encouraged only, § 621.604.D
Principal on-site power prohibited; export facilities need separate approval, § 621.604.E, J(2).
Substations side or rear and screened; lines not buried, § 621.604.J(4)
Section 621.404 requires a 250-ft landscaped buffer from residential districts and dwellings designed as a full year-round visual screen, and requires the plantings to be maintained and replaced as necessary.
Outdoor equipment fully screened, § 621.607.I
Plan reviewed by fire chief, radio coverage, signage; no annual update, § 621.606
Annual fire safety inspections, § 621.606.A(5)
Section 621.601.A requires a Traffic Impact Study, and Section 621.501.A, which applies to all Industrial Uses, sets its scope as projected trips, levels of service, crash history, and queuing at intersections the Township Traffic Engineer identifies, but construction traffic is not covered.
Plan, closure notice, security; 18 months, § 621.610
Section 301 defines a data center to include artificial intelligence training, blockchain processing, cryptocurrency mining, and high-performance computing, and excludes accessory server rooms incidental to a non-industrial use, but the exclusion sets no stated size or power limit.
Annual energy reports, § 621.604.L
Mitigation plans required; no specific penalties, § 621.602.G
Public meeting before planning commission and project website, § 621.611
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the PI, PIC, and PCID districts
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data