Upper Uwchlan Township
Neutral Data Center Policies
Upper Uwchlan Township allows data centers in designated districts through special permit or conditional-use review, providing a defined approval path but adding time and uncertainty.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Upper Uwchlan TownshipCreates a data-center-specific ordinance in Upper Uwchlan Township, but the provided text does not show what it requires or restricts.Ordinance No. 2026-03 — Data Center Ordinance (including Upper Uwchlan Township Zoning Ordinance § 200-72.4 and § 200-44(13))
current law · Upper Uwchlan TownshipThe current rules are in Ordinance 2026-03, which the Board of Supervisors adopted on August 17, 2026.Upper Uwchlan Township, Chester County — data-center ordinance (No. 2026-03)
What this means
The measure provides a route for data centers through a special permit or conditional-use review in designated districts. That offers legal certainty, but the extra approval step can add time and uncertainty.
Restrictions & requirementsHide restrictions & requirements25
LI Limited Industrial district only, § 200-44.B(13)
Conditional use by Board of Supervisors; approval lapses in 6 months, § 200-116.H.
Section 200-72.4.B sets data centers and data center accessory uses back 1,000 feet from any lot developed with a sensitive receptor, and Section 200-72.4.D defines those accessory uses to include ground level and rooftop mechanical equipment.
35 ft, rooftop equipment not limited, § 200-72.4.C
55 dBA day, 45 dBA night at residential, § 200-72.4.G(9) Table 2
Section 200-72.4.G(9), Table 6, makes an increase of more than 3 dBA above the documented baseline ambient level a violation, measured with an ANSI Type 1 or Type 2 meter (Table 5), but the baseline is not defined as L90 and no floor is set below which the cap does not apply.
70 dBC day, 60 dBC night, Table 3
Pre-construction and post-construction studies, § 200-72.4.G(1), (3)
65 VdB and PPV limits with study, § 200-72.4.G(3)(f)
Public water required, no groundwater for cooling; no well study, § 200-72.4.H
Air-cooled or closed-loop required; evaporative not named, § 200-72.4.H(5)
Usage estimates and drought plan; no cap or reporting, § 200-72.4.H
Tier 4 generators with annual testing reports, § 200-72.4.F(7)
Electronic waste plan; refrigerants in decommissioning, § 200-72.4.M, N.
Utility interconnection documentation; no electrical inspection, § 200-72.4.F(6)
Energy usage plan; renewables encouraged only, § 200-72.4.F
Substations side or rear and screened; lines 34.5 kV or less buried, § 200-72.4.J
Mechanical equipment screened on all sides, § 200-72.4.D
Elevations and renderings required, § 200-72.4.E
Plan reviewed by fire department, radio coverage, 24-hour signage; no annual update, § 200-72.4.K
Annual fire safety inspections, § 200-72.4.K(1)(e)
Construction plan for vehicle times and locations; no bond, § 200-72.4.L
Plan and closure notice; security optional, 18 months, § 200-72.4.N
One post-construction noise study, § 200-72.4.G(3)
Generator testing website only
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the LI Limited Industrial district
Sources