Upper Tulpehocken Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Upper Tulpehocken Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Upper Tulpehocken TownshipThe draft has no ordinance number and is the working version revised after the Planning Commission's first review, which the township provided on October 19, 2026; it awaits Berks County Planning Commission comments and is to be reviewed at the November 2026 Planning Commission and Supervisors meetings, with no hearing scheduled.Upper Tulpehocken Township, Berks County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements31
500-ft setback from waterways and a hydrological study; no riparian buffer widening at slopes or wetlands, proposed § 460-102A(6) and Other Performance Standards (11)
Single 55 dBA limit at any lot line at any time, proposed § 460-102 Noise Control
Noise studies must evaluate hum; no dBC limit, proposed § 460-102 Noise Study
Preliminary study with the application, interim during land development, and as-built after occupancy; no building permit study, proposed § 460-102 Noise Study (1)-(3)
Generator testing and maintenance capped at 8 hours per month; no daytime limit, proposed § 460-102 Onsite Generation 2(c)
Municipal water required and hydrological study; no pump tests, proposed § 460-102 Other Performance Standards (9) and (11)
Proposed Section 460-102 Other Performance Standards (9)(c) requires the data center to recirculate, reuse, and recycle water in a closed-loop system explained in a separate report, but does not bar evaporative cooling or limit it to a stated water-use rate shown to meet the noise limits.
Analysis of water needs including cooling required; no cap, reporting, or drought plan, proposed § 460-102 Other Performance Standards (9)(a)
Effluent discharge study with the application, including temperatures; no approved discharge plan, proposed § 460-102 Other Performance Standards (10)
Diesel generators must meet EPA Tier 4; no annual testing or reports, proposed § 460-102 Onsite Generation 2(a)
Heat must be imperceptible beyond lot lines and a heat study may be required, proposed § 460-102 Other Performance Standards (3)
Utility interconnection agreement showing capacity; no third-party electrical inspection, proposed § 460-102 Other Performance Standards (12).
Rooftop solar on at least 65% of the roof required; no energy usage plan, proposed § 460-102 Onsite Generation 1
Backup generators, fuel cells, and battery storage addressed; no separate use approval, proposed § 460-102 Onsite Generation 2
Battery storage must follow applicable codes; no NFPA 855, proposed § 460-102 Onsite Generation 2
Proposed Section 460-102 Other Performance Standards (12) requires an interconnection agreement from the electric service provider stating available capacity and the grid upgrades required before service, with all upgrade costs borne by the applicant and rate impacts explained, but does not require the estimated cost of the upgrades or the tariff terms that assign it.
75-ft landscaped buffer with 15-ft berm along all lot lines, proposed § 460-102 Landscape Buffer and Berm
Glare must be imperceptible beyond the lot lines; no lighting shielding standard, proposed § 460-102 Other Performance Standards (3)
Rooftop and ground equipment screened from public view to equipment height; no acoustic screening, proposed § 460-102 Equipment Screening
Scenic viewshed mitigation plan only if requested by the Supervisors, proposed § 460-102 Other Performance Standards (14)
Continuity of Operations and Emergency Preparedness Plan updated every two years; no fire company review or radio coverage, proposed § 460-102 Continuity of Operations
Plan describes coordination with first responders; no training required, proposed § 460-102 Continuity of Operations
Generator fuel containment at 110% and fenced outdoor storage; no storage setbacks, proposed § 460-102 Onsite Generation 2(b) and Other Performance Standards (6)
Inspection protocol only in an operations agreement on request, proposed § 460-102 Other Performance Standards (14)
Construction traffic study only if requested by the Supervisors, proposed § 460-102 Other Performance Standards (14)
Secondary emergency access approved with the fire chief; no arterial or collector requirement, proposed § 460-102 Emergency Access
Construction mitigation plan only if requested by the Supervisors, proposed § 460-102 Other Performance Standards (14)
Security equal to net decommissioning cost, 30-day notice, removal within 6 months; security below 110%, proposed § 460-102 Decommissioning 1-5
Proposed Section 460-102 Decommissioning 4 and 5 require the net decommissioning cost estimate before final land development approval, after the first year of operation, and every fifth year, and require the operator to post and maintain security in an amount equal to the net decommissioning cost.
One as-built noise study after occupancy, then on request, proposed § 460-102 Noise Study (3)
Owner must remediate noise violations; no specific penalties, proposed § 460-102 Noise Study (3)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the I-1 General Industrial District