Upper Saucon Township
Anti-Data Center Policies
Upper Saucon Township requires data centers to receive conditional-use approval and meet impact, setback, buffering, and operating requirements, adding review and compliance costs without banning them.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Upper Saucon TownshipProposes to allow data centers only by conditional use in specified zones, subject to detailed requirements for siting, water, energy, noise, environmental impacts, safety, and reporting, while repealing the prior data-center ordinance.Ordinance No. 141-EE, proposed amendment to the Upper Saucon Township Zoning Ordinance
What this means
The proposal would allow data centers in industrial and Enterprise Overlay zones, but only through conditional-use approval and with extensive requirements for water, energy, noise, emergency response, and other impacts (conditional use and comprehensive regulations). These added studies, plans, and operating standards could make projects significantly harder and costlier, though they do not amount to a ban.
People behind it
- Upper Saucon Township Board of Supervisors
Will conduct the public hearing and consider adoption of the proposed zoning ordinance amendment.
Restrictions & requirementsHide restrictions & requirements10
Data centers would be allowed only as conditional uses in the Industrial and Enterprise Overlay zones, requiring conditional-use approval.
Dimensional limits include a minimum lot size of 10 acres, a maximum Data Center Limit of Disturbance of 75 acres, a minimum lot width of 250 feet, and a maximum impervious or lot coverage of 50%. The proposal also sets building-height and setback requirements.
The proposal establishes parking and loading requirements, as well as lighting and signage standards.
Principal structures would be subject to aesthetic and architectural design requirements, landscape-buffer requirements, and screening and fencing requirements.
Water and sewer provisions would require a Water Resources Impact Report and Water Management Plan, and would establish closed-loop cooling, operational-system, stormwater-function, and cooling-return-flow standards.
Energy provisions would require an Energy Impact Plan and renewable-energy measures, set standards for backup power generation, power lines, and substations, and require disclosure about fiber and telecommunications infrastructure.
Noise and vibration provisions would require a Noise Study and Mitigation Plan, set maximum sound levels and vibration limits, and require monitoring. The proposal also revises maximum permitted exterior noise levels in the Agricultural Preservation and Industrial districts.
The proposal establishes air-quality standards and prohibits electromagnetic interference.
Operators would need an Emergency Response Plan, an electronic-waste plan, and a Thermal Impact Mitigation Plan, and would be subject to thermal-impact mitigation requirements.
The proposal establishes decommissioning standards and requires annual reporting.
Benefits & exceptionsHide benefits & exceptions1
Data centers may be permitted as conditional uses in the Industrial and Enterprise Overlay zones, subject to the requirements in the new Section 495. “Data Centers as a conditional use within the Industrial (I) Zone”
Sources
current law · Upper Saucon TownshipThe Board of Supervisors' October 26, 2026 agenda listed a public hearing and a possible adoption vote on Ordinance No. 141-II, which would repeal and replace those rules with a 75-acre disturbance cap, required closed-loop cooling and public water and sewer, a 65 dBA property line limit, a decommissioning plan and agreement, and annual reporting, but the outcome has not been confirmed.Upper Saucon Township, Lehigh County — data-center ordinance (No. 141-EE)
What this means
The ordinance allows data centers through conditional-use approval but requires setbacks, buffers and technical operating safeguards. Those add meaningful review and compliance costs; a later proposed replacement is a separate action and is not assumed to be in force.
Restrictions & requirementsHide restrictions & requirements24
80-ft height including rooftop equipment, § 495.C.4
Water resources report only; no environmental assessment
Single 70 dBA daytime limit at the property line, § 495.F.1
Ordinance 141-EE requires a predictive study with the conditional use application and an as-built study six to nine months after occupancy, using ANSI S1.4-2014 meters and ISO or FHWA modeling methods.
Water Resources Impact Report required, § 495.H.1
Water supply and withdrawals disclosed in impact report, § 495.H
Ordinance 141-EE requires the applicant to demonstrate that domestic, cooling, and industrial wastewater disposal has been approved by the Sewage Enforcement Officer, the geotechnical consultant, and DEP.
EPA Tier 4 generators with annual testing and reports, § 495.G
Electronic Waste Plan covers servers and batteries; refrigerants not named, § 495.K
Utility capacity certification; no third-party inspection, § 495.I.3.
Energy Management Plan required; renewables only a good faith effort, § 495.I.1-2
Substations screened and counted as accessory uses, § 495.A and § 495.E.1
Known impacts on electric rates must be identified, § 495.I.3
100-ft landscape buffer next to residential districts and sensitive receptors, § 495.D.2.
Facade must change every 150 ft and resemble an office complex, § 495.L.
Equipment within 300 ft enclosed or screened with noise-absorbing screens, § 495.E
Architectural elevations required, § 495.L.2
Emergency Response Plan reviewed by the local fire department, § 495.J.1
Plan must ensure first responder training, § 495.J.1.d
Annual fire safety inspections, § 495.J.1.e
Electronic waste plan only; no decommissioning plan or security
One as-built sound study after opening, § 495.F.1.c
Noise violation found by as-built study is an ordinance violation, § 495.F.1.c
End user must be identified during conditional use review, § 495.B
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Industrial zone and Enterprise Overlay Zone
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data