Upper Providence Township

Anti-Data Center Policies

Upper Providence allows data centers only with conditional-use approval on qualifying M-2 sites, subject to large setbacks and extensive power, water, noise, and emergency-response requirements.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Upper Providence Township
Restricts data centers to conditional-use approval in the M-2 industrial district and sets requirements for site size, setbacks, energy and water use, noise, emergency response, and public notice.Upper Providence Township data-center zoning ordinance (Ordinance No. 2026; adopted June 22, 2026)

What this means

The ordinance allows data centers, but only through conditional-use approval in the M-2 district, on sites with more than 25 developable acres, and with large setbacks from homes and other sensitive places. It also requires extensive plans and standards for power, water, noise, and emergency response, creating significant costs and hurdles even though development is not banned.

People behind it

  • Enacted Ordinance No. 619 on June 15, 2026.

Restrictions & requirementsHide restrictions & requirements17
  • Data centers are allowed only by conditional use in the M-2 Manufacturing Industrial District; freestanding data centers are excluded from the administrative buildings or centers permitted in the IO-1 district. Conditional uses

  • A site must have direct access from an arterial or collector road, secondary emergency access from a lower-classification road, and more than 25 developable acres. The developable acreage

  • A data center requires an overall site master plan, and material changes to the plan or site layout require a new conditional-use approval. Any material changes

  • Principal buildings, accessory uses, and truck-idling areas must be at least 250 feet from property lines and 1,000 feet from residential districts and sensitive receptors. The latter distance may be reduced to 500–999 feet only if the applicant demonstrates specified enhanced environmental, noise, screening, and thermal-impact protections. Minimum Setbacks

  • Data centers and freestanding accessory uses are limited to 60 feet in height; principal-building height includes rooftop equipment and accessory uses. Maximum building coverage is 40%, and maximum impervious coverage is 50%. Maximum Height

  • Applicants must provide an energy-use plan with the conditional-use application, covering demand, supply sources, backup power, storage if applicable, renewable-energy efforts, and grid-interconnection information. Projects must meet the current LEED BD+C: Data Centers rating system or an equivalent approved by the Township Engineer; the Township may require supplemental or amended plans before zoning approval. Energy Usage Plan

  • A grid-connected project with planned demand over 50 MW must procure at least 10% of its power from qualifying renewable sources through a power purchase agreement or similar arrangement; renewable energy credits alone do not qualify. minimum of 10%

  • Energy-generation systems that regularly supply a data center are treated as separate principal uses, not part of the data-center use, and require applicable state, federal, municipal, and zoning approvals. They must be sited and designed to limit impacts; the data center must be between the generation systems and sensitive receptors. separate principal use

  • On-site substations face siting and screening rules, including an 800-foot setback from certain nonindustrial zoning boundaries or properties containing a sensitive receptor. On-site power lines of 34.5 kV or below must be buried; higher-voltage lines are encouraged to be buried. minimum of 800 feet

  • Diesel backup generators must meet EPA Tier 4 standards and undergo annual testing, with reports provided to the municipality. Fossil-fuel emergency generation is limited to outages or maintenance/readiness testing capped at 100 hours per year; routine testing is restricted to 9 a.m.–3 p.m. Monday through Friday. Peak shaving and supplying power to the grid are prohibited. capped at 100 hours per year

  • Where public water is available, private wells and direct surface-water withdrawals cannot be the primary cooling-water source. Data centers must use closed-loop cooling unless the applicant demonstrates that an alternative uses less water and energy; public-water capacity documentation or a nonpublic-water feasibility study is required, along with applicable permits and a drought-response plan. closed-loop water circulation system

  • Applicants must analyze wastewater needs and disposal. Public systems require documentation of capacity; private disposal requires a feasibility study, and untreated wastewater cannot be discharged to stormwater systems or surface waters. Wastewater disposal analysis

  • A qualified professional must prepare a thermal-impact mitigation plan with the zoning application, addressing heat sources, off-site effects, mitigation, feasible waste-heat reuse, and possible monitoring. The Township may require supplemental or amended plans before zoning approval. Thermal Impact Mitigation Plan

  • Applicants must submit pre-construction and post-construction noise studies, including low-frequency analysis and measurements at property lines. Limits are 40 dB(A)/50 dB(C) from 7 p.m. to 7 a.m. and 45 dB(A)/60 dB(C) from 7 a.m. to 7 p.m.; where baseline noise is higher, the project may not exceed baseline levels. Sound levels at the property line

  • A zoning application must include an emergency-response plan reviewed and accepted by local fire and emergency-management services. It must address emergency procedures, first-responder training at the applicant’s expense, and annual fire-safety inspections; battery storage must meet NFPA 855 or similar standards and include specialized fire suppression. at the expense of the applicant

  • Applicants must submit an electronic-waste plan for safe removal and recycling or disposal of servers, hazardous materials, batteries, and related equipment when equipment is updated or decommissioned; the Township may require supplemental or amended reports before zoning approval. Electronic Waste Plan

  • Before the first planning-commission meeting discussing the proposal, the applicant must hold an advertised public meeting. The applicant must also maintain a public project website starting at least two weeks before that meeting and continuing until final land-development approval. at least two weeks prior

Benefits & exceptionsHide benefits & exceptions6
  • Data centers are allowed to seek conditional-use approval in the M-2 Manufacturing Industrial District, provided the site has more than 25 developable acres, specified road access, and an overall site master plan. Conditional-use eligibility and site requirements.

  • The usual 1,000-foot separation from residences and other sensitive receptors may be reduced to 500–999 feet if the applicant demonstrates stronger environmental performance, including noise no higher than ambient levels, visual screening or aesthetic improvements, and no thermal air changes affecting the nearest receptors. Setback reduction criteria.

  • The ordinance recognizes a range of data-center accessory uses, including backup generation, administrative and security facilities, substations, utility and fiber lines, and cooling-related facilities. Backup generation cannot be used to regularly supply power during normal operations. Data center accessory uses.

  • Energy-generation systems intended to regularly power a data center may be proposed as separate principal uses, subject to applicable state, federal, and township approvals and regulations. Separate treatment of energy-generation systems.

  • An on-site electric utility substation serving a data center may be located on the same property, to the side or rear of the data-center building; no buffer or screening is required between the substation and that building. Other siting and screening limits apply. On-site substation provisions.

  • Fossil-fuel emergency generators may operate during emergency outages and for maintenance or readiness testing, subject to Tier 4 emissions standards, annual testing and reporting, a 100-hour yearly cap on routine testing, and limits on testing hours; peak shaving and supplying power to the grid are prohibited. Backup-power operating rules.

Sources

current law · Upper Providence Township
The rules are in Ordinance No. 619, adopted June 15, 2026, and Ordinance No. 623, enacted September 21, 2026, which added a decommissioning plan and removal deadlines without financial security.Upper Providence Township, Montgomery County — data-center ordinance (Nos. 619 And 623)

What this means

The measure imposes setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements19
  • Overall site master plan for the site, § 300-560.C.1.d

  • Section 300-560.C.1.d requires a new conditional use for any material change to the master plan or site layout, but it lists no triggers such as added building area, generators, cooling, battery, substation capacity, or electrical demand, and does not exempt like-for-like replacement.

  • Section 300-560.C.8.b sets 45 dBA from 7:00 a.m. to 7:00 p.m. and 40 dBA at night at the property lines, but no metric, meter class, or measurement procedure is stated beyond full-spectrum modeling.

  • 60 dBC day and 50 dBC night, § 300-560.C.8

  • Pre-construction and post-occupancy studies, § 300-560.C.8

  • Closed-loop required or alternative shown; evaporative not restricted, § 300-560.C.6.b

  • Drought response plan; no cap or reporting, § 300-560.C.6.f

  • Tier 4 with annual testing reports, § 300-560.C.5

  • Thermal Impact Mitigation Plan with waste heat reuse review, § 300-560.C.7.

  • Electronic Waste Plan for server infrastructure, § 300-560.C.10

  • Utility interconnection documentation in Energy Usage Plan, § 300-560.C.3.b(6)

  • Energy Usage Plan required; rooftop solar encouraged only, § 300-560.C.3.b

  • Substations side or rear and screened; lines 34.5 kV and below buried, § 300-560.C.4

  • Substations screened from public view, § 300-560.C.4

  • Plan reviewed by fire department, radio coverage, 24-hour signage; no annual updates, § 300-560.C.9

  • Annual fire safety inspections, § 300-560.C.9.a(5)

  • Decommissioning plan, closure notice, start within one year and finish within 18 months, removal of all above-ground structures and equipment, § 300-560.C(12) (Ord. 623); no financial security

  • Annual generator testing reports only, § 300-560.C.5.b

  • Public meeting before planning commission and project website, § 300-560.C.11

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the M-2 Manufacturing Industrial District

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data