Upper Nazareth Township
Anti-Data Center Policies
Upper Nazareth’s enacted ordinances allow data centers through approval but impose siting, noise, utility, environmental, decommissioning, and thermal-plan requirements that can increase costs.
Incentives
Financial Incentive2
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Upper Nazareth TownshipRequires new data centers and certain large expansions to submit an engineer-prepared heat-impact plan and meet standards to limit harm to nearby properties, water, and public infrastructure.Upper Nazareth Township Ordinance No. 207
What this means
The measure would add meaningful costs and approval steps: covered projects must submit an engineer-prepared thermal plan, and the township may require extra mitigation and review at the applicant’s expense (thermal plan requirement). It applies broadly to new data centers and larger expansions, with possible ongoing monitoring, but it does not ban them (applicability rules).
People behind it
- Board of Supervisors of Upper Nazareth Township
Proposed the zoning amendments and is identified as the body that would consider enactment and enact the ordinance.
Restrictions & requirementsHide restrictions & requirements7
New data centers, including conversions, must meet the thermal-impact rules. They also apply to existing data-center expansions that increase gross floor area by more than 25%, and to specified high-density computing facilities exceeding 10,000 square feet or 2 MW of projected electrical demand. The Township may extend the rules to smaller facilities it determines are likely to cause comparable thermal impacts. Applicability thresholds and scope
A data-center development plan’s conditional-use application must include a Thermal Impact Mitigation Plan, prepared and sealed by a Pennsylvania-licensed professional engineer practicing in a specified engineering field. Plan and engineer requirement
The required plan must provide extensive analyses and information, including facility operations and demand, cooling systems and heat generation, effects on neighboring properties and natural resources, water use and discharge, heated runoff, heat-island measures, noise coordination, and emergency operations. Required plan contents
Applicants must demonstrate that the data center will not cause adverse thermal impacts to neighboring properties, public infrastructure, or environmentally sensitive resources, and that thermal discharges will not adversely affect listed resources such as groundwater, streams, wetlands, and stormwater facilities. Thermal performance standards
The Board of Supervisors may make approval conditional on mitigation, including increased setbacks, screening, buffers, limits on cooling technologies, reduced impervious coverage, thermal-discharge controls, monitoring, or additional environmental studies. It may also require further mitigation on the Township Engineer’s recommendation when impacts may be adverse. Potential mitigation measures
The Township may retain consultants to review the mitigation plan, and the applicant must reimburse the consultant-review costs. Applicant reimbursement of review costs
After construction, the Township may require verification, operational monitoring, annual reporting, thermal-performance testing, and corrective actions if actual impacts exceed approved projections. Failure to maintain compliance with approved mitigation measures is an ordinance violation. Ongoing compliance requirements
Benefits & exceptionsHide benefits & exceptions2
The thermal-mitigation requirements apply to expansions only when gross floor area increases by more than 25%, and to specified high-density computing facilities only when they exceed 10,000 square feet or 2 MW of projected electrical demand. The Township may still require smaller facilities to comply if it determines they are likely to generate comparable thermal impacts.
The Township may waive specific Thermal Impact Mitigation Plan submission requirements if the applicant shows they do not apply or equivalent information has been provided in other required studies.
Sources
current law · Upper Nazareth TownshipWould allow data centers only with conditional-use approval in the TD-11 district and impose requirements for site size, noise, safety, utilities, environmental review, and eventual decommissioning.Upper Nazareth Township Ordinance No. 205
What this means
The measure permits data centers only through conditional-use approval in the TD-11 district, with minimum lot sizes of 10 to 50 acres and large required buffers (conditional use only in TD-11; minimum buffer strips). It also adds substantial requirements for utilities, noise, environmental review, and decommissioning, making projects harder and costlier even though development remains possible.
People behind it
- Angela Strohl
Updated the data centers ordinance and submitted a review letter with proposed changes.
- Upper Nazareth Township Planning Commission
Recommended changes to the ordinance and voted to send them to the Board of Supervisors for review.
Restrictions & requirementsHide restrictions & requirements23
Data centers and data center campuses are permitted only by conditional use in the TD-11 district; data center equipment also requires conditional-use approval. Converting an existing building to a data center is treated as land development. Conditional use only in the TD-11 Zoning District
For new principal buildings in TD-10 and TD-11, applications must identify the intended occupant and principal use and describe operations, utility demand, and hours. Approval is tied to those details; a materially different use requires Township review, and conversion to a data center requires new zoning approval. Intended Occupant Disclosure
Minimum lot area is tiered by building size: 10 acres for buildings under 50,000 square feet; 20 acres for 50,000–100,000 square feet; 30 acres for 100,001–250,000 square feet; and 50 acres for buildings over 250,001 square feet. Minimum Lot Area
Parking, loading, and interior driveways must be set back 50 feet from public street rights-of-way and 25 feet from other lot lines; data-center parking must be 50 feet from a residential district or residential-use property line. At least one loading space and 1.5 parking spaces per employee on the largest shift are required. Truck parking and idling must be 300 feet from residential districts or occupied homes, reducible to 250 feet if sound studies demonstrate compliance with the 55 dBA limit without sound mitigation. Parking, loading and interior driveway setbacks
Buffer strips and landscaping are required near sensitive receptors, residential uses or districts, and collector or arterial roads. Depending on building footprint, required buffers include 300-, 400-, or 500-foot strips along specified street frontages and nearby sensitive or residential properties; other lot lines require 100-foot front and 50-foot side or rear strips. The ordinance also specifies berms, dense plantings, screening targets, and landscape-management plans with financial security for ongoing maintenance. enhanced buffer strip
Data center buildings are limited to 50 feet, with qualifying rooftop equipment allowed up to 10 feet above the roof; total height cannot exceed 60 feet, and rooftop projections cannot contain habitable or occupiable floor area. shall not exceed 50 feet in height
Utility lines from substations to data centers must be underground where practical, subject to exceptions for utility-company requirements or infeasibility. On-site power lines of 34.5 kV and below must be buried. must be buried
Applicants must demonstrate adequate second emergency access and provide written Fire Chief approval addressing access, truck turning, fire suppression, and hydrant availability. On-site energy generation requires Fire Chief approval, a safety plan, annual plan recertification, and an annual site inspection; stationary fuel-cell systems are conditional uses and must meet specified setbacks and design-certification requirements. annual site inspection
Data centers must meet a 55 dBA sound limit. Applications require preliminary, interim, as-built, and post-construction sound studies; the post-construction study is due within six months after occupancy and commercial operation, and the Township may require later studies. Violations require immediate remediation, and backup generators must also remain within 55 dBA, including during testing. pre-, during, and post-construction sounds studies
Specified data-center equipment must be housed in grounded, metered, fire-rated metal enclosures designed to resist an internal electrical fire for at least 30 minutes, with fire-closing baffles. Applicants must demonstrate compliance with relevant NFPA standards, submit applications and plans for Fire Chief review and comment, and provide specialized firefighting equipment required by local emergency services. resist an internal electrical fire for at least 30 minutes
Applicants must obtain written utility-provider verification of capacity, equipment adequacy, cooling and operational-system adequacy, and absence of electrical interference or voltage fluctuations; electrical work must pass a third-party final inspection. Facilities must comply with applicable NERC reliability standards. written verification from the applicable service provider
The ordinance imposes architectural and screening requirements, including no blank building sides, façade breaks, specified fenestration, screened loading bays, and screening or enclosure of certain equipment. Rooftop equipment must be screened, set back from exterior walls when visible above the parapet, and placed as far as feasible from residential uses and sensitive receptors. shall not have blank exterior walls
Lighting must be shielded and directed to avoid spillover; illumination at residential properties cannot exceed 0.1 footcandle and at nonresidential properties cannot exceed 0.5 footcandle. LED sources are limited to 3000K, luminaires cannot be mounted more than 20 feet above the illuminated surface, and roof pole lighting is prohibited. shall at no time exceed 0.1 footcandle
The ordinance sets an EMF ceiling of 2 milligauss above ambient at the nearest property line or a publicly accessible point and requires baseline and post-construction measurements, an EMF management plan, and mitigation if limits are exceeded. Data centers must also prevent electromagnetic interference and immediately correct verified interference. shall not exceed 2 milligauss
Construction and operation must keep vibration at or below 0.2 inches per second peak particle velocity. Where facilities or equipment are within 1,000 feet of residential uses, residential zones, or sensitive receptors, pre- and post-construction vibration studies are required; the initial post-construction study is due within six months after occupancy and commercial operation, and the Township may require ongoing monitoring. 0.2 inches per second
Data centers must use public water and public sanitary sewer exclusively; private wells, groundwater withdrawals, private water facilities, on-lot septic systems, and private wastewater facilities for the data-center use are prohibited. Applicants must provide written confirmation that the public providers have adequate capacity. served exclusively by a public water supply system
Applicants must coordinate with the Township Emergency Management Coordinator and Fire Chief on in-building emergency-radio coverage and install enhancement systems if needed. Applications must also disclose necessary on-site and off-site fiber infrastructure, routes, construction methods, public-infrastructure impacts, restoration methods, and responsible parties. install enhancement systems as needed
A conditional-use application must include an environmental impact assessment covering specified air emissions, nuisance effects, stormwater, cultural resources, comprehensive-plan impacts, alternatives, mitigation, and critical impact areas. A PNDI report dated within two years of the relevant application, required agency clearance letters, and compliance with clearance measures are also required. Environmental Impact Assessment
Buildings must be designed as solar-ready. Uncovered rooftop areas must use roofing material with a solar reflective index of at least 78 for the life of the building. For buildings over 250,000 square feet, rooftop solar panels must be installed and operated before occupancy to supply as much of the facility's needed power as feasible. All building roofs shall be solar-ready
A data center must use the best available cooling technology as determined at site-plan approval; the specified criteria include minimizing potable-water use and environmental impact and meeting the 55 dBA sound limit. best available cooling technology
A land-development application must include a decommissioning plan. Owners or operators must post financial security equal to 110% of estimated decommissioning costs, without credit for salvage value, keep it in effect for the facility's life, and update it every five years or sooner if required. Decommissioning is triggered, at minimum, by 20 months of non-operation without redevelopment plans submitted for approval; the plan itself must also be updated every five years or upon major ownership or operational changes. financial security shall equal 110%
Every data-center proposal must include a construction transportation plan covering construction schedules, truck routes and volumes, traffic and safety measures, road protection, staging, emergency access, agency coordination, and a responsible coordinator. shall include a construction transportation plan
Campus development requires a master plan covering the full site, followed by an individual site plan for each data center or phase before a building permit and submission of applicable third-party permits. Major changes to the approved master plan require Planning Commission review and Board of Supervisors approval. subject to a data center campus master plan
Benefits & exceptionsHide benefits & exceptions8
Data centers, data center campuses, and their accessory uses are eligible for conditional-use approval in the TD-11 district; the approval path is limited to that district and requires compliance with applicable ordinance requirements. permitted by Conditional Use only in the TD-11 Zoning District
The ordinance provides for data center campuses with multiple or cumulatively developed centers, including centers on separately owned parcels under the same ownership or within 500 feet of an existing data center. Campus development may proceed in phases, subject to a campus master plan and individual site plans before building permits. A data center campus may be developed in one or more phases
A site plan can qualify as a minor modification to an approved campus master plan, avoiding the major-modification process for specified changes. Examples include relocating accessory uses or utility lines and increasing building floor area by up to 5%; major changes still require Planning Commission review and Board approval. A minor modification to an approved data center campus master plan
The ordinance expressly allows data center accessory infrastructure, including power generation stations and redundant or backup power supplies. Stationary fuel-cell power systems may be approved as conditional uses accessory to data centers, subject to the required Fire Chief safety-plan review and other listed conditions. Accessory Uses/Structures include
Data center buildings may have functionally required rooftop mechanical equipment, cooling towers, generators, screening, antennas, or other appurtenances up to 10 feet above the roof, subject to a 60-foot overall height cap and other limits. may extend up to 10 feet above the roof surface
The utility-line rules allow lines from off-site to substations to be above ground, and permit above-ground lines where underground placement is impractical or required by the utility company. On-site power lines of 34.5 kV and below must be buried. Utility lines to the substations from off-site may be placed above ground
For required data-center buffers, existing vegetation may substitute for new berms and plantings if the Board of Supervisors approves it. may be substituted for new berms and plantings
The ordinance sets graduated minimum lot areas, including 10 acres for data-center buildings under 50,000 square feet, thereby specifying a route for facilities at that size; larger buildings require larger minimum lots. Buildings less than 50,000 square feet- 10 Acres
Sources
current law · Upper Nazareth TownshipThe rules are in Ordinance No. 205, adopted June 17, 2026, as amended by Ordinance No. 207, adopted September 16, 2026.Upper Nazareth Township, Northampton County — data-center ordinance / amendment 207
What this means
The measure imposes setbacks from homes or other protected places, minimum site-size requirements and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements32
Conditional use before the Supervisors, no approval expiration, § 27-402.71.A
Buffer strips along lines within 500 ft of schools, day cares, hospitals, parks, § 27-402.71.I
Environmental Impact Assessment required, § 27-402.71.U
Campus master plan with phases; major modifications need Board approval, § 27-402.71.CC
Single 55 dBA limit, § 27-402.71.O
Section 27-402.71.O requires preliminary, interim, as-built, and post-construction sound studies, with the post-construction study within six months after commercial operation, but names no measurement method and does not require full operating load.
Section 27-402.71.Q sets a limit of 0.2 inches per second peak particle velocity at the nearest property line and requires pre-construction and post-construction vibration studies and monitoring, but states no measurement standard or procedure.
Public water only, wells barred, provider capacity letter, § 27-402.71.R
Best available cooling technology and cooling analysis, no closed-loop mandate, § 27-402.71.Z; Ord. 207
Projected daily use and drought contingency in thermal plan, no cap or reporting, Ord. 207
Section 27-402.71.R(4) to (6) requires public sanitary sewer and written capacity confirmation from the sewer authority, and Ordinance 207 requires a blowdown and discharge analysis in the Thermal Impact Mitigation Plan, but neither states that sewer authority or DEP approval must be in hand before the zoning permit.
Act 167 stormwater plan stated as applying, § 27-402.71.U(1)(c)
Emission sources identified and air permit copies required, § 27-402.71.U(1)(a)
Thermal Impact Mitigation Plan required; heat reuse only an optional measure, Ord. 207
Hazardous materials removed at decommissioning, § 27-402.71.AA(4)(e)
Utility capacity letter at application and third-party final electrical inspection, § 27-402.71.K
Rooftop solar required on buildings over 250,000 sq ft; no energy usage plan, § 27-402.71.Y
Fuel cell systems a separate conditional use with setbacks and safety plan, § 27-402.71.G.
Fire Chief safety plan citing NFPA and fire code; no NFPA 855, § 27-402.71.G, P
300 to 500 ft planted buffer strips next to homes, § 27-402.71.I.
Section 27-402.71.L bars blank walls, requires horizontal and vertical breaks every 35 lineal feet, a change in material, pattern, texture, or color every 150 horizontal feet, fenestration of at least 30 percent of each facade, and durable brick or masonry materials with variation of color.
Rooftop screened on four sides; ground equipment partly screened, § 27-402.71.L(5), M
Fire Chief safety plan with annual recertification and radio coverage, § 27-402.71.G, S
Annual Fire Chief inspection is limited to on-site energy generation (§ 27-402.71.G), and the third-party electrical inspection is listed among conditional use application items rather than before occupancy (§ 27-402.71.K)
Construction transportation plan only; no traffic study
Second emergency access required, § 27-402.71.E
Construction routes, hours, and road protection measures; no road bond, § 27-402.71.BB
110% security, but 20-month abandonment trigger, § 27-402.71.AA
Plan and security updated every 5 years, § 27-402.71.AA
Post-construction sound study within 6 months, § 27-402.71.O(5)
General remediation and security draw provisions, § 27-402.71.AA(5), O
Ordinance 207, Section vii, allows the Township to retain consultants to review the Thermal Impact Mitigation Plan with all review costs reimbursed by the applicant, but this covers only the thermal plan at the conditional use stage and no applicant-paid consultant review of the other studies in land development review is stated.
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the TD-11 Manufacturing District
Sources
current law · Upper Nazareth TownshipThe Board of Supervisors adopted Ordinance No. 205, which added the data center rules to the zoning code.Upper Nazareth Township, Northampton County — data-center ordinance / amendment 205 (2026-06-17)
What this means
A score of -3 is assigned as the requested fallback because the available sources do not provide enough detail to assess the impact. It should not be read as a source-confirmed finding of significant barriers.
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data