Upper Moreland Township

Anti-Data Center Policies

Upper Moreland Township permits data centers only through conditional-use approval, with substantial site, setback, study, cooling, and water-use requirements that limit feasible projects.

Incentives

Financial Incentive
2

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Township of Upper Moreland
Would allow data centers by conditional-use approval only in the Limited Industrial District, subject to detailed requirements on siting, energy, water, noise, emissions, safety, and decommissioning.Upper Moreland Township Zoning Ordinance — Data Center Provisions (Chapter 350)

What this means

The proposal would allow data centers in the Limited Industrial District, but only with conditional-use approval and demanding standards. Large minimum lot sizes, 500-foot setbacks, and extensive studies and operating requirements could make projects difficult and costly to build and run (conditional-use requirements).

People behind it

  • Proposed the zoning amendment to allow data centers by conditional use in the Limited Industrial District.

  • Identified as the preparer of the agenda item concerning the proposed amendment.

  • The body considering and enacting the proposed zoning ordinance amendment.

Restrictions & requirementsHide restrictions & requirements29
  • Data centers would be allowed only in the Limited Industrial District and only with conditional use approval. permit data centers by conditional use

  • A data center must take access from an arterial or collector road and provide secondary access suitable for emergency response. arterial or collector road

  • Minimum lot area would be 20 acres for data centers exceeding 100,000 square feet of gross floor area, individually or collectively on one property, and 10 acres for smaller data centers. minimum lot size of 20 acres

  • Data centers, accessory uses, energy generation systems, and truck-idling areas would have to be at least 500 feet from every property line. minimum setback from all property lines of 500 feet

  • Data centers, accessory uses, substations, and energy generation systems would have to be at least 500 feet from residential uses, specified nonindustrial zoning districts, mapped streams, wetlands and floodplains, and sensitive receptors. The distance is measured in a straight line to the applicable property line. minimum of 500 feet

  • Buildings and energy generation systems would be limited to 60 feet in height, including rooftop equipment and appurtenances; impervious coverage could not exceed 70% of the tract. may not exceed 60 feet in height

  • Air, dust, smoke, glare, exhaust, heat, or humidity from the use could not be perceptible at or beyond the property line. shall not be perceptible

  • Building design would have to meet facade articulation and material limits: specified architectural elements must extend across at least 60% of a facade; principal facades must have offsets of at least 10 feet at intervals no greater than 50 feet; and no more than 80% of a facade may use one material or 50% one color. Main entrances must be articulated, and rooftop equipment must be set back from the parapet at least its height above the roof. at least 60 percent of the facade

  • The project would have to meet at least a certified level under the USGBC LEED BD+C: Data Center rating system or an equivalent design standard approved by the Township Engineer. at a minimum, be at a Certified Level

  • A qualified professional would have to prepare an Energy Usage Plan for the conditional use application, covering matters including demand, supply, backup power, renewable-energy efforts, grid interconnection status, and potential electric-rate and reliability effects. The Township may require supplemental or amended plans before approval. provide an Energy Usage Plan

  • A proposed data center with power demand over 50 megawatts that plans to connect to the grid would have to procure at least 10% of its power from qualifying renewable generation within the applicable regional transmission organization; purchasing renewable energy credits alone would not suffice. minimum of 10% of its power

  • On-site energy generation used to power a data center during normal operations would generally be treated as a separate principal use requiring its own approvals. It may be included as part of a data center campus if the same entity owns and operates both and shared ownership is maintained. Peak shaving or supplying power to the grid is prohibited unless specifically approved as a principal use in the conditional use approval. shall not be considered part of the Data Center use

  • Substations and energy generation systems would face additional siting and screening rules, including restrictions on front-yard placement of substations, screening from public view in specified circumstances, and a 500-foot setback for substations or generation systems on property adjoining a nonindustrial district or sensitive-receptor property. Power lines must be buried when feasible, and on-site lines of 34.5 kV or less must be buried. set back a minimum of 500 feet

  • Diesel backup generators would have to meet EPA emissions standards and undergo annual testing, with reports provided to the Township. undergo annual testing

  • A data center could not receive conditional use approval if it proposes to use groundwater wells, springs, or direct withdrawals from surface watercourses as water sources. The application must also analyze potential effects on public water rates and service reliability. No conditional use approval shall be granted

  • Wastewater disposal would have to rely on the Township’s public system where permitted, comply with the applicable sewer authority’s industrial pretreatment requirements, and be supported by a certified showing that the authority can convey and treat the expected wastewater. Untreated wastewater could not be discharged to stormwater systems, surface waters, aquifers, storage tanks, or wells. rely solely upon the Township’s public system

  • The conditional use application would have to include a thermal-impact mitigation plan prepared and certified by a qualified professional, addressing waste-heat sources, off-site impacts, mitigation, possible heat reuse, and monitoring. Thermal Impact Mitigation Plan

  • Data centers and related equipment would be subject to specified noise limits by adjoining land use and time of day, with separate low-frequency noise criteria. A qualified professional would have to conduct a pre-construction study with the application and post-construction verification within 180 days after operations begin; testing and additional Township-requested testing may also be required. Required with conditional use application

  • The application would have to include a qualified professional’s plan or report on compliance with air-pollution laws. Six months after operations begin, the operator must submit an air-pollution and plume study; thereafter, annual testing and reports are required, and identified noncompliance must be corrected and documented. Six months after a Data Center

  • A qualified professional would have to prepare an Emergency Response Plan for approval by Township fire and emergency-management services. It must address emergency procedures, responder training, and annual fire-safety inspections; the applicant bears the stated training and inspection costs. The proposal also requires 24-hour emergency contact signage and any needed emergency-communications enhancements. An Emergency Response Plan shall be required

  • An Electronic Waste Plan would have to be submitted with the conditional use application, describing safe removal, recycling, or disposal of servers, batteries, hazardous materials, and related waste when equipment is updated or the facility is decommissioned. The Township may require supplemental or amended plans. An Electronic Waste Plan shall be submitted

  • Parking would be required at one space per employee on the largest shift, plus five visitor spaces; the Township may request up to 25% additional parking. One parking space shall be required for each employee

  • Facilities and pollution- or odor-producing equipment would have to be oriented away from adjoining sensitive receptors unless physically impossible. Buffering and screening would be required, including a 150-foot vegetative buffer along public-street frontage and property lines abutting or within 500 feet of residential property or a sensitive receptor, and a 50-foot buffer along other property lines. 150-foot vegetative buffer yard

  • Service areas, loading docks, refuse areas, and service entrances would have to be screened from public-road views, sensitive receptors, and residential zoning districts. The draft also calls for a 300-foot vegetative buffer along specified street frontage and sensitive-residential boundaries when the combined footprint of principal structures exceeds 250,000 square feet. exceeds 250,000 square feet

  • The conditional use application would have to include a decommissioning plan. Before a construction permit is issued, the owner, operator, or developer must provide financial security based on decommissioning costs, with the required amount equal to net decommissioning costs plus 10% and never less than 50% of estimated costs. Security must be maintained, updated every five years, and supported by a Township decommissioning agreement; Township review and agreement costs are charged to the applicant. Prior to issuance of the permit

  • Lighting would have to meet shielding and direction requirements, limits on illumination at neighboring properties, a maximum mounting height of 20 feet, and a 3,000 K color-temperature cap for LED sources. Parking and traffic-way lighting generally must be extinguished within 30 minutes after closing, subject to stated reduced-activity alternatives. within ½ hour of the close

  • Before the conditional use hearing, an applicant for a data center over 100,000 square feet or one using an on-site electrical substation would have to hold a public meeting at least 14 days before the first hearing. The applicant must also maintain a public project website beginning at least two weeks before that meeting and through final land-development approval. at least fourteen (14) days prior

  • Where federal or state law allows the Township to enter a community-benefits agreement, the applicant would have to enter an agreement to the Township’s satisfaction. shall enter into such an agreement

  • Plan or operating violations would trigger enforcement after written notice and a 30-day opportunity to cure; the Township may also inspect relevant premises and records, and failure to provide requested records within 10 days would itself be a violation. The draft provides for enforcement remedies, including permit suspension or revocation. thirty (30) day opportunity to cure

Benefits & exceptionsHide benefits & exceptions3
  • Data centers may be approved as conditional uses in the Limited Industrial District, subject to the measure’s criteria and approval process (permit data centers by conditional use).

  • The measure recognizes data-center accessory facilities—including administrative, fiber-optic, electrical, water, and wastewater facilities—and allows them on the same tract or on adjacent parcels developed as a unified campus (same tract or assemblage of adjacent parcels).

  • An energy-generation system may be located on the same property as a data center as part of a data-center campus if the same entity owns and operates both and shared ownership is maintained (permitted upon the same property).

Sources

current law · Upper Moreland Township
The standards were added by Ordinance No. 1780, which the Board of Commissioners enacted on October 5, 2026 after declaring on May 4, 2026 that its zoning ordinance was partly invalid for lacking any provision for data centers.Upper Moreland Township, Montgomery County — data-center ordinance (No. 1780)

What this means

The measure imposes setbacks from homes or other protected places, minimum site-size requirements and cooling and water-use rules. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements36
  • Conditional use in the Limited Industrial District only; exclusion elsewhere not separately stated, § 350-110 and § 350-115.F

  • District building coverage limit and 70% impervious coverage cap only, § 350-115.F(2)(e)-(f)

  • 60 ft including rooftop equipment, above the 40-ft Limited Industrial district limit, and screened rooftop equipment may exceed the district height, § 350-115.F(2)(b) and (15)(d)(ii) and § 350-112

  • 500 ft from any mapped stream, wetland, or floodplain; no wider buffer on steep slopes, § 350-115.F(2)(d)

  • Retesting may follow equipment changes, but no new approval is required for expansion, § 350-115.F(9)(f)

  • Increase of more than 3 dBA above baseline ambient is a violation, by stated method; no floor and not an L90 baseline, § 350-115.F(9)(h), Tables 5 and 6

  • 70 dBC day and 60 dBC night Leq at the nearest property line, above 60 and 55 dBC, § 350-115.F(9)(h), Table 3

  • Predictive study with the application by ISO 9613-2 or equivalent at maximum rated capacity, and measured as-built study within 180 days of operation at peak cooling load with generators under load using ANSI standards, § 350-115.F(9)(b) and Tables 4-5

  • 0.2 to 0.5 in/s PPV under USBM RI 8507 and 65 VdB under ISO 2631-1, with pre-construction and as-built vibration studies, § 350-115.F(9)(b)

  • Public water provider must confirm exclusive public service and capacity, and no approval for wells, springs, or surface withdrawals, § 350-115.F(7)(b)-(c)

  • Closed-loop cooling required and open-loop, once-through, and evaporative cooling prohibited, § 350-115.F(7)(a)

  • Proposed demand confirmed by the water provider; no metered use reporting or drought plan, § 350-115.F(7)(b)

  • Public sewer only, with an analysis of wastewater including HVAC and closed-loop water and sewer authority certification of capacity and pretreatment compliance with the conditional use application, § 350-115.F(7)(e)

  • Diesel generators must meet EPA Tier 4, with an air study 6 months after opening and annual emissions testing and reports, § 350-115.F(6)(a)-(b) and (10)

  • Thermal Impact Mitigation Plan evaluating off-site thermal impacts under seasonal conditions and waste heat reuse, § 350-115.F(8)

  • Electronic Waste Plan for servers, hazardous materials, and batteries; refrigerants and a disposal contract not required, § 350-115.F(12)

  • Energy Usage Plan documents the utility application and transmission security agreement status; executed agreement not required before the zoning permit, § 350-115.F(4)(a)(vi)

  • Energy Usage Plan with annual demand, and 10% renewable procurement above 50 MW; rooftop solar is an effort to document, not a set share, and peak demand by phase not required, § 350-115.F(4)

  • Energy generation for normal operation is a separate principal use with its own approval and 500-ft setbacks, with data center buildings placed between it and homes, § 350-115.F(5)(a), (f)-(g)

  • Substations to the side or rear and screened from public view, and on-site lines of 34.5 kV and below buried, § 350-115.F(5)(c)-(e)

  • NFPA 855 with battery-specific fire suppression; no setbacks, fire test data, or hazard mitigation analysis, § 350-115.F(11)(e)

  • Ratepayer impact analysis on electric rates with the application; required upgrades, cost, and tariff terms not disclosed, § 350-115.F(4)(a)(viii)

  • Vegetative buffer of 100, 150, or 300 ft by footprint along streets and lines within 500 ft of homes or sensitive receptors, on berms up to 10 ft; replacement of dead plants not stated, § 350-115.F(15)(e)

  • Full cutoff fixtures for horizontal surfaces and a 0.1-footcandle limit on homes; light crossing the property line not barred, § 350-115.F(17)

  • Facade offsets every 150 ft, 80% limits on one material and one color, 60% articulation, and an articulated entrance, § 350-115.F(3)(a)-(f)

  • Rooftop equipment screened on all four sides and all mechanical equipment behind an acoustical barrier, but ground equipment in industrial areas screened only from public roads, § 350-115.F(9)(a) and (15)(d)

  • Elevations and renderings of facades visible from off-site, and a line-of-sight study for service areas; no visual impact study from roads and historic sites, § 350-115.F(3)(h) and (15)(b)

  • Emergency Response Plan acceptable to the fire department and EMS, with 24-hour contact signage and radio coverage; no annual plan update or walk-through, § 350-115.F(11)(a)-(c)

  • Hazardous material disposal in the waste and decommissioning plans only; no storage setbacks or containment, § 350-115.F(12) and (16)

  • Annual fire safety inspections by a qualified professional; no report to the fire official or correction period, § 350-115.F(11)(a)(v)

  • Security of net decommissioning cost plus 10% before the construction permit and an agreement that may be recorded; removal begins within 1 year and ends within 18 months, § 350-115.F(16)(c)-(e)

  • Definition includes cryptocurrency mining and blockchain processing but not artificial intelligence; incidental equipment exempt without a size or power limit, § 350-13

  • One as-built noise and vibration study; annual reports cover emissions only, and generator records are provided on request, § 350-115.F(6)(b)-(c), (9)(b), and (10)(c)

  • Plan violations enforceable after written notice and a 30-day cure, and failure to remediate results in permit revocation or suspension; no hearing before revocation and MPC Sections 616.1 and 617.2 not cited, § 350-115.F(19)-(20)

  • Township may hire a consultant to witness and review noise testing paid from the applicant's escrow, and the applicant pays decommissioning review costs; review of other studies not assigned, § 350-115.F(9)(h)(2) and (16)(e)(vii)

  • Public meeting 14 days before the first conditional use hearing and a project website through final land development approval, for data centers over 100,000 sq ft or with a substation; meeting not tied to planning commission review, § 350-115.F(18)(a)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the Limited Industrial District

Sources

current law · Upper Moreland Township
The Board of Commissioners approved Resolution R-2026-7 by a 7-0 vote, declaring a portion of the zoning ordinance invalid due to the lack of data center uses.Upper Moreland Township, Montgomery County — data-center resolution R-2026-7

What this means

The measure starts a protected period for local officials to fix gaps in their zoning rules. This can delay developers who need to challenge the old rules, but it does not by itself prohibit every data-center project.

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data