Upper Merion Township
Anti-Data Center Policies
Upper Merion Township allows data centers in some districts with conditional-use approval, but setbacks, noise and water rules, and size caps in two districts limit projects; they are not banned outright.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Upper Merion TownshipRequires data centers in designated industrial zones to get township approval and follow rules on size, distance from homes, noise, water use, screening, utilities, and emergency planning.Upper Merion Township Ordinance amending Chapter 165 (Zoning) — data center regulations
What this means
Data centers could be built in some districts, but they would need conditional-use approval and face a 1,000-foot setback from homes, strict noise and water rules, and size caps in two districts. These limits create significant hurdles, though they do not ban data centers outright and one district has no size cap.
Restrictions & requirementsHide restrictions & requirements17
Data centers in the SM-1, Limited Industrial, and Heavy Industrial districts require conditional-use approval and a public hearing. The approval expires if the applicant does not seek a building or other necessary development permit within one year, though the Board may extend the deadline by up to one year for cause. Conditional-use hearing and standards One-year time limit
In SM-1 and Limited Industrial, data centers must have less than 49,999 square feet of gross floor area. In SM-1, the data center must also be accessory to a permitted use. SM-1 size and accessory-use limits Limited Industrial size limit
In Limited Industrial and Heavy Industrial, data centers may not exceed 65 feet in height. Height limit
In Heavy Industrial, the total building footprint may not exceed 40% of the lot area. Building-footprint limit
In Heavy Industrial, building facades must include at least five specified design elements or other architectural features the Board finds satisfactory. Five facade design elements
In all three districts, data-center buildings, structures, and associated mechanical equipment must be at least 1,000 feet from a lot containing a residential use or property zoned residential. The distance is measured in a straight line to the nearest residential property line or district boundary. 1,000-foot separation
In all three districts, areas abutting a residential-use parcel or residential district must have a planted buffer at least 50 feet wide. 50-foot planted buffer
In all three districts, mechanical equipment must be separated from an adjacent residential district by the principal building. Equipment visible at ground level from public roads or adjoining parcels must be fully screened. Principal-building separation Visual screening
In all three districts, mechanical equipment must have acoustical barriers. Sound at the parcel line may not exceed 50 dB(A) next to residential zoning or 62 dB(A) next to a district permitting retail or office commercial uses. Acoustical barrier and sound limits
Applicants in all three districts must provide a pre-construction noise study with the conditional-use application and a post-construction study at least one month but no more than 12 months after the first certificate of occupancy. Exceeding the applicable sound limit requires mitigation; where baseline noise already exceeds the limit, operations may not materially increase it unless approval specifically allows the increase. Noise-study requirements Post-construction study deadline
Before plan recording, an approved data center must provide confirmation from the electric utility that the site has sufficient capacity. Proposed alternative or off-grid generation requires regulatory review and approval and must comply with applicable requirements before installation or operation. Electric-capacity confirmation
In all three districts, water-based cooling must use a closed-loop system. Open-loop, once-through, and water-intensive evaporative cooling are prohibited, and water may be discharged or exported from the site only through an approved public sanitary sewer connection. Cooling-system restrictions
In all three districts, the application must include written confirmation from an authorized public water utility that the facility will use the public water system exclusively and that it has sufficient capacity. Approval may not be granted for a proposal using groundwater wells, springs, or direct withdrawals from surface watercourses. Public-water and capacity requirement
Before submitting a conditional-use application, the developer must hold a public informational meeting. Pre-application public meeting
In Heavy Industrial, the operator must provide an emergency management plan demonstrating that fire, police, and emergency services can adequately serve the facility, including for intentional external, natural, and man-made threats. Emergency management plan
Data centers must provide parking at one space per 10,000 square feet of principal-structure gross floor area, plus four spaces per 1,000 square feet of gross leasable office area for administrative, training, or similar functions. They must also identify reserved parking under warehouse parking standards; the Township may require construction of that area if documented operational or use changes materially increase demand. Parking requirements
Backup emergency generators may be used only for backup or emergency purposes, except for testing or commissioning. Generator testing is allowed only from 9:00 a.m. to 5:00 p.m. Generator testing hours
Benefits & exceptionsHide benefits & exceptions4
Data centers may seek conditional-use approval in the SM-1, Limited Industrial (LI), and Heavy Industrial (HI) districts; this is not approval by right. In SM-1, a center must be accessory to a permitted use and under 49,999 square feet. In LI, it must be under 49,999 square feet. HI has no stated maximum floor area, but limits the building footprint to 40% of the lot and height to 65 feet, and requires at least five specified facade design elements. Approval also requires, among other things, a 1,000-foot separation from residential uses or zoning, noise studies and compliance with noise limits, documentation of public-water and utility capacity, and closed-loop cooling.
Alternative or off-grid energy generation may be proposed for a data-center site, subject to approval by relevant authorities and compliance with applicable requirements.
The baseline parking requirement is one space per 10,000 square feet of principal-structure floor area. Office, training, and similar space requires four spaces per 1,000 square feet; the applicant must identify a reserved area, which the Township may require to be built if parking demand materially increases and that increase is documented.
Backup emergency generators are expressly addressed as an exception in the noise-performance standards. They may be used only for backup or emergencies, and testing or commissioning is allowed only from 9 a.m. to 5 p.m.
Sources
current law · Upper Merion TownshipThe Board of Supervisors adopted the rules as Ordinance 2026-905 on March 12, 2026.Upper Merion Township, Montgomery County — data-center ordinance (No. 2026-905)
What this means
The measure imposes setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements15
Conditional use after a Board of Supervisors hearing, expiring if no permit is sought within 1 year, Sections 165-219.12 and 165-219.1.B and D
Section 165-219.12.A(5) bars any data center building, structure, or associated mechanical equipment, including generators, cooling systems, substations, and rooftop or ground mounted equipment, within 1,000 feet of any lot with a residential use or any residentially zoned property, measured from the closest point of the building or equipment.
50 dBA at the parcel line next to residential districts and 62 dBA next to commercial districts, single limits, Section 165-219.12.A(7)
Pre-construction and post-construction noise studies; none at building permit, Section 165-219.12.A(8)
Public water only; groundwater wells, springs, and surface withdrawals barred, Section 165-219.12.A(11)
Closed-loop cooling required and evaporative cooling prohibited, Section 165-219.12.A(10)
Capacity confirmation only; no cap, reporting, or projected use disclosure
Water may leave the site only through an approved public sewer connection, Section 165-219.12.A(10)
Utility capacity confirmation before plan recording; no electrical inspection, Section 165-219.12.A(9).
50-ft planted buffer next to residential uses and districts, Section 165-219.12.A(4)
Section 165-219.12.C(1) requires Heavy Industrial facades to include at least five of six design elements (height change, step-backs, fenestration, change in material or color, accent materials, or other features satisfactory to the Board), but sets no measurable intervals or limits for articulation, materials, or color.
Full visual screening and acoustical barriers for all mechanical equipment; no 12-ft height, Section 165-219.12.A(6) and A(7).
Emergency management plan required in HI, Section 165-219.12.C(14)
One post-construction noise study after opening, Section 165-219.12.A(8)(b)
Noise increases deemed violations with Zoning Officer enforcement; no specific penalties, Section 165-219.12.A(8)
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the LI, HI, and SM-1 districts
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data