Upper Macungie Township

Anti-Data Center Policies

Upper Macungie allows data centers only by conditional use in GI and RT districts, requiring approval, a 200-foot setback, and sound, utility, and emergency-planning documentation. These limits and reviews add costs and potential delays.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Upper Macungie Township
Restricts data centers to conditional approval in designated industrial districts and requires 200-foot setbacks from homes and sensitive sites, plus noise, water, power-supply, and emergency-response reviews.Upper Macungie Township Zoning Ordinance, Ordinance 2504 (data center-specific zoning amendment)

What this means

Data centers would be allowed only by conditional use in the GI and RT districts, so developers would face an approval process and a limited choice of locations (district use table). Applicants would also need to meet a 200-foot setback and provide sound, water, power, and emergency-planning documentation, adding substantial cost and delay (data center requirements).

People behind it

  • Conducted the public hearing and enacted the ordinance (enacted and ordained).

Restrictions & requirementsHide restrictions & requirements9
  • Data centers are listed as prohibited in the NC, HC, LI, and LI(L) districts; they may be considered only as conditional uses in GI and RT. Conditional uses require a decision by the Board of Supervisors, with Planning Commission review. The use table lists the district status.

  • Data centers and their equipment must be at least 200 feet from a residential zoning district boundary or the lot line of a property with a sensitive receptor, including residences, schools, daycare centers, places of worship, and parks. The 200-foot setback requirement.

  • Data centers must meet the Township’s buffer-yard requirements. If the facility or equipment is visible from beyond the lot lines, an earthen berm is also required. The additional berm requirement.

  • Applicants must provide professional sound studies at three stages: a preliminary study for conditional use, an interim study during building permitting, and an as-built study six months after the certificate of occupancy and before final escrow release for a land-development phase. The Township may request later studies; violations must be promptly remediated, and continuous noise compliance is required. The required study phases.

  • For public water, applicants must provide Lehigh County Authority documentation that it will supply the needed water. For nonpublic water, applicants must provide a feasibility study demonstrating adequate supply and no adverse effects on nearby groundwater or surface water; the specified study information includes projected demand, water sources and uses, nearby wells and waters, and effects on water quality and quantity. The water feasibility-study requirement.

  • Applicants must provide Delaware River Basin Commission review and approval for projects proposing withdrawals of at least 100,000 gallons per day averaged over 30 days from sources in the Delaware River Basin, or consumptive use of at least 20,000 gallons per day averaged over 30 days from any water source. The DRBC thresholds.

  • Applicants must demonstrate adequate wastewater disposal, including domestic wastewater and cooling or industrial wastewater, with approval from the Sewage Enforcement Officer and/or Pennsylvania Department of Environmental Protection. The wastewater approval requirement.

  • For a proposed grid connection, applicants must document that the electric provider has capacity and will serve the data center, and submit an assessment of project-attributable impacts on electric rates or availability for other uses. If the assessment identifies detrimental impacts or insufficient capacity, the applicant must pay for necessary system improvements. On-site utility methods may be considered only if both the Township Engineer and utility provider determine those improvements infeasible. The applicant-funded improvements requirement.

  • Applicants must submit an Emergency Response Plan prepared by a qualified professional and reviewed and accepted by the Township’s Bureau of Fire as part of conditional-use review. The plan must address fire suppression, containment, ventilation, evacuation, emergency access, and first-responder training, and provide for annual fire-safety inspections. The Emergency Response Plan requirements.

Benefits & exceptionsHide benefits & exceptions3
  • Data centers may seek conditional-use approval in the GI and RT districts. They are not permitted in the NC, HC, LI, or LI(L) districts; approval is decided by the Board of Supervisors with Planning Commission review. The use table lists the districts where data centers are conditional uses.

  • If needed electric-grid improvements are found infeasible by both the Township Engineer and the electric utility, the Township may consider on-site utility methods, subject to Township ordinances. On-site utility methods may be considered.

  • The data-center definition includes same-tract supporting equipment and structures, including utilities, substations, cooling facilities, and outdoor equipment providing redundant power. Data Center Equipment is included in the defined use.

Sources

current law · Upper Macungie Township
The current rules are in Ordinance No. 2025-04, which the Board of Supervisors adopted on December 4, 2025.Upper Macungie Township, Lehigh County — data-center ordinance (No. 2025-04)

What this means

The measure imposes technical studies and utility checks, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements15
  • Must meet Chapter 10 limit of 65 dBA at the property line, § 27-402.T.1(3)

  • Section 27-402.T.1(3) requires preliminary, interim, and as-built studies, the last six months after occupancy, using generally accepted criteria.

  • Water feasibility study for nonpublic water, § 27-402.T.1(4)(b)

  • Water use for cooling described; cooling method not regulated

  • Projected water demand disclosed, § 27-402.T.1(4)(b)

  • Section 27-402.T.1(4)(d) requires the applicant to show that domestic, cooling, and industrial wastewater disposal has been provided and approved by the Sewage Enforcement Officer or DEP, with no stated timing.

  • Utility certification of capacity; no third-party inspection, § 27-402.T.1(5)(a).

  • Section 27-402.T.1(5)(a) and (b) require a provider letter confirming capacity and service and an assessment of rate impacts, and require the applicant to pay for system improvements if capacity is insufficient.

  • Base buffer yard plus earthen berm, § 27-402.T.1(2)

  • Visible equipment screened by earthen berm, § 27-402.T.1(2)

  • Emergency Response Plan accepted by the Bureau of Fire, § 27-402.T.1(6)

  • Plan must ensure first responder training, § 27-402.T.1(6)(a)(4)

  • Annual fire safety inspections, § 27-402.T.1(6)(a)(5)

  • One as-built sound study after opening, more on request, § 27-402.T.1(3)

  • Owner must promptly remediate noise violations, § 27-402.T.1(3)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the General Industrial and Rural Technology districts

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data