Upper Allen Township
Anti-Data Center Policies
Upper Allen Township’s enacted resolutions give officials a protected period to address zoning gaps, which can delay developers challenging existing rules but does not prohibit every data-center project.
Incentives
Financial Incentive3
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Upper Allen TownshipThe Board adopted Resolutions 1126 and 1127 to begin a curative amendment for data centers.Upper Allen Township, Cumberland County — data-center resolution 1126
What this means
The measure starts a protected period for local officials to fix gaps in their zoning rules. This can delay developers who need to challenge the old rules, but it does not by itself prohibit every data-center project.
Sources
current law · Upper Allen TownshipThe Board adopted Resolutions 1126 and 1127 to begin a curative amendment for data centers.Upper Allen Township, Cumberland County — data-center resolution 1127
What this means
The measure starts a protected period for local officials to fix gaps in their zoning rules. This can delay developers who need to challenge the old rules, but it does not by itself prohibit every data-center project.
Sources
pending · Upper Allen TownshipProposes allowing data centers only with conditional-use approval in industrial districts, subject to rules for siting, water use, noise, power, emergency response, and decommissioning.N/A — no enacted data center-specific law identified
What this means
The proposal would newly allow data centers as conditional uses in industrial areas, but only after detailed studies and approvals. Strict setbacks, noise rules, limits on cooling water and a ban on routine on-site power generation would add substantial costs and could make some sites impractical (250-foot setbacks near homes and sensitive sites).
People behind it
- Upper Allen Township
Municipality publishing the proposed zoning amendment and identified in the draft as the enacting body.
Restrictions & requirementsHide restrictions & requirements23
Data centers and stand-alone battery energy storage systems (BESS) would be conditional uses in the Industrial District, requiring conditional-use approval; a BESS used for emergency backup power for a data center is treated differently under the specified exception. Conditional-use classification
Applicants must submit a comprehensive conditional-use package, including a conceptual site plan, technical studies, exhibits, a compliance matrix, and a written compliance statement. The Township may require additional information, and third-party reviews required for requested design alternatives are at the applicant’s expense. Conditional-use submission requirements
Expansion, increased capacity, changes to cooling technology, greater water or energy demand, increased noise or environmental impacts, and additional or changed backup generators beyond the approved scope would require new conditional-use approval, even if building area does not increase. Expansion and change-of-use trigger
Enhanced setbacks and forested buffers apply near certain uses: 250 feet from a residential zoning district or a lot containing a sensitive receptor within 500 feet, with a 200-foot buffer; or 150 feet from specified agricultural, village, commercial, office, or institutional districts within 300 feet, with a 100-foot buffer. Exceptions and a limited modification process are specified. Enhanced setback requirements
If land is rezoned to Industrial after the ordinance’s effective date, data centers next to residential districts or sensitive-receptor lots would need a 1,000-foot setback; next to specified agricultural, commercial, village, institutional, or office districts, a 500-foot setback. Future industrial rezoning setbacks
Setback and buffer areas generally cannot contain buildings, equipment, parking, loading areas, generators, substations, cooling equipment, fuel systems, or security fencing; barbed wire is prohibited. The proposal also requires extensive forested screening, specified planting and berm standards, early installation, and ongoing maintenance and financial security. Setback-area restrictions
Principal buildings and structures are limited to 66 feet including rooftop appurtenances. Above 35 feet, added side-yard and building-separation distances and additional screening apply; taller facades also face architectural-articulation requirements. Maximum height
Rooftop and ground-mounted equipment must be enclosed or screened, with acoustic measures where needed. Ground equipment that cannot feasibly be enclosed must be located within or screened by buildings, or screened with an acoustic wall and landscape buffer. Equipment screening
Lighting plans and photometric plans are required. Maximum illumination is 0.1 footcandle at property lines adjoining residential, agricultural, village districts, or sensitive receptors, and 0.5 footcandle at other nonresidential district lines. Fixtures must be shielded and directed downward; nonessential accent lighting must be off from 11 p.m. to 6 a.m. Lighting limits and controls
Parking must include at least one space per peak-shift employee, one per vehicle stored on site, and five guest spaces. Minimum parking
Data-center industrial processes and cooling generally may not use potable water, groundwater, untreated raw water, private wells, or surface-water withdrawals; routine consumptive or evaporative cooling use is not authorized. Reclaimed water may be used for approved non-potable purposes but not routine cooling. Once-through and high-loss evaporative cooling using potable water as the primary source are prohibited, and applicants must provide a professional-engineer water-impact analysis and certification of cooling-system compliance. Water-use restrictions
Before conditional-use approval, applicants must provide wastewater and thermal-impact analyses. The proposal restricts untreated wastewater discharge and routine cooling-system or industrial-process wastewater discharge unless expressly authorized and approved by applicable agencies. Wastewater and thermal studies
A detailed pre-construction noise and vibration study is required, with specified baseline measurements, predictive modeling, and maximum-capacity operating assumptions. If modeling indicates a potential exceedance, physical or operational mitigation must be incorporated. Post-construction testing is required before a permanent certificate of occupancy; a temporary certificate may last no more than 90 days, and violations trigger remediation deadlines and possible TCO revocation. Noise and vibration review and verification
Fuel, flammable-liquid, and hazardous-material storage tanks, associated containment, and high-volume transfer or filling manifolds must be at least 200 feet from the development tract’s perimeter property line. Fuel and generator areas also trigger stormwater-hotspot planning requirements. Fuel-storage setback
Before conditional-use approval, applicants must submit an emergency response plan reviewed with Township and emergency-service officials. Requirements include responder training, annual fire inspections and public-safety meetings, emergency notifications, access provisions, and annual reporting. Annual reports must include proof of liability insurance of at least $25 million naming the Township as an additional insured. Emergency response and annual reporting
Applicants relying on public electric service must document adequate available or reasonably available capacity. On-site power generation is prohibited, except authorized emergency backup generators and standby systems. Electricity and on-site generation
Emergency generators and BESS are limited to emergency, backup, testing, maintenance, and safety-related operations. Fossil-fuel generator testing generally may not exceed 100 hours per year and must occur Monday through Friday, 10 a.m. to 3 p.m., excluding holidays; peak shaving and supplying power to the grid are prohibited. Generator and BESS inventories must be disclosed, and expanding generator inventory requires a new conditional-use proceeding. Backup-power operating limits
The proposal imposes additional BESS conditions, including NFPA 855 fire-safety compliance, detection and suppression systems, emergency-response planning, and a 100-foot separation from public rights-of-way and adjacent non-participating property for stand-alone facilities. Data-center-associated BESS is also subject to the applicable data-center standards. Stand-alone BESS standards
Plans are required for electronic and hazardous-waste handling, and operators must attest to compliance with air-emissions laws and provide copies of applicable Pennsylvania DEP air-quality permits. Waste and air-quality requirements
Before construction, operators must submit construction truck routes and a transportation plan, enter into a road-maintenance agreement, provide financial security for potential Township-road damage, and document road conditions. Construction traffic and roadway protection
Power transmission and other lines, wires, or conduits serving the data center must be underground, except for power switchyards or areas within a substation. Underground-line requirement
Applicants must submit a decommissioning plan and provide financial security equal to 125% of estimated decommissioning and restoration costs before grading and building permits. Security must be updated at least every three years and before ownership transfers. A facility inactive for 12 consecutive months may be deemed abandoned; decommissioning must begin within 60 days and generally finish within 180 days. Decommissioning security and deadlines
Applicants must provide a recent Pennsylvania Natural Heritage Program screening and any required agency clearance letters. Sites within 150 feet of specified water bodies are subject to riparian forest-buffer requirements, including a minimum 100-foot buffer on each side, possible added width for slope or wetlands, and restrictions on earth disturbance and material storage. Species and riparian-buffer requirements
Benefits & exceptionsHide benefits & exceptions8
The draft would allow data centers and their accessory uses as conditional uses in the Industrial District, rather than barring them there. Data Center including Data Center Accessory Use
An applicant that meets the draft’s specific standards and general conditional-use criteria would be entitled to approval, unless an opponent establishes by credible evidence a high probability of a greater or different adverse impact than normally generated by this type of use. shall be entitled to approval of the conditional use
A BESS serving as emergency backup power for a data center would not need separate conditional-use approval as a principal use; this exception does not cover a stand-alone BESS, which requires separate approval. unless providing emergency backup power for a Data Center
The Board could reduce required setbacks or buffer widths to the minimum necessary if their combined application leaves too little land for a reasonably sized project, provided alternative design offers substantially equivalent visual, acoustic, lighting, and safety mitigation and the Board makes the required findings. reduce the required setback and/or buffer width
The draft allows the Board to consider alternative buffer and screening designs that provide equal or superior performance, subject to written justification and review by a Township-selected landscape architect at the applicant’s expense. It also allows architectural alternatives under similar conditions, with review by a Township-selected architect. Alternative Design Compliance
A temporary certificate of occupancy could authorize energizing the facility, testing or operating server infrastructure, and cycling cooling systems for commissioning and required noise and vibration testing. The TCO is limited to 90 days, and the as-built study is due within 60 days of issuance. authorize the issuance of a TCO
The draft expressly allows emergency generators and BESS for emergency, backup, testing, maintenance, and safety-related use. Routine fossil-fuel generator operation for maintenance and testing is limited to 100 hours per calendar year, testing is generally restricted to weekday daytime hours, and peak shaving or grid supply is prohibited. limited to emergency, backup, testing, maintenance, and safety-related operations
If an approved reclaimed-water supply and connection are available, the applicant may use reclaimed water for approved non-potable purposes such as initial filling, testing, maintenance, and irrigation. It may not be used for routine consumptive or evaporative cooling, and the applicant pays the infrastructure and connection costs. may connect to such line and use reclaimed water
Sources
pending · Upper Allen TownshipBoth drafts are revisions dated October 13, 2026 that are posted on the township ordinance amendments page, the zoning draft was listed for discussion at the Planning Commission meeting of October 26, 2026, and no public hearing date has been posted.Upper Allen Township, Cumberland County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose cooling and water-use rules, money set aside for eventual removal and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements34
Conditional use decided by the Board of Commissioners; no one-year expiration of approval, § 245-14.20.5.B
Base IND District lot coverage limit applies; no footprint or megawatt cap, § 245-14.20.5.D(1)(a)
Riparian forest buffer of 100 ft on each side, widened on slopes of 10% or more and by 25 ft at wetlands, § 245-14.20.5.D(26)
Section 245-14.20.5.C(13) and D(17)(a)xiii require a new conditional use approval for any expansion, change in operational capacity or cooling technology, increase in water or energy demand, or added backup generators, but no like-for-like replacement exemption is stated.
45 dBA night but 55 dBA day at residential and sensitive receptor properties, § 181-2.9.C Table 1
3 dBA cumulative cap only where baseline exceeds the Table 1 limits, § 181-2.9.G; otherwise a 3 dBA rise triggers design mitigation, § 245-14.20.5.D(13)(d)
70 dBC day and 60 dBC night, with a 15 dB C-minus-A cap, § 181-2.9.C Table 1 and D
Predictive study with the application and as-built study after a temporary occupancy permit; building permit plans show mitigation only, § 245-14.20.5.D(13)(c)-(e)
Testing weekdays 10:00 a.m. to 3:00 p.m., capped at 100 hours a year and at 1 hour a day and 3 hours a week above the limits, § 245-14.20.5.D(17)(a) and § 181-2.9.K
65 VdB and 0.02 in/s PPV limits with vibration studies; not a no-perceptible standard, § 181-2.9.L and § 245-14.20.5.D(13)(c)iv
Potable water, groundwater, and private wells may not be used for cooling, § 245-14.20.5.D(9)(b).
Air-cooled, closed-loop, or similar low-water cooling required; once-through and high-loss evaporative cooling prohibited, § 245-14.20.5.D(9)(e).
Ongoing water monitoring and reporting plan; no drought response plan, § 245-14.20.5.D(9)(a)ii
Wastewater plan before conditional use approval; routine cooling discharge and blowdown prohibited, § 245-14.20.5.D(10)
Section 245-14.20.5.D(12) treats fuel storage and generator areas as stormwater hotspots and requires a Hotspot Management Plan with secondary containment, treatment of petroleum-contaminated runoff, and spill procedures, but transformer areas are not covered.
Diesel generators must meet EPA Tier 4; no annual emissions testing or reports, § 245-14.20.5.D(17)(a)i and D(20)
Thermal Impact Mitigation Plan including evaluation of waste heat reuse, § 245-14.20.5.D(11).
E-waste plan, with removal and recycling of electronic equipment, batteries, and refrigerants at closure, § 245-14.20.5.D(18), D(23) and D(24).
Utility documentation of capacity required; no third-party electrical inspection, § 245-14.20.5.D(16)(a).
Lines buried and ground equipment, including substations, enclosed or screened; substation placement not set, § 245-14.20.5.D(6)(b) and D(22)
Required electric infrastructure improvements must be identified; cost not assigned, § 245-14.20.5.D(16)(a)
200 ft Enhanced Forested Buffer next to residential districts and sensitive receptors, § 245-14.20.5.D(1)(b)i.3.
All equipment enclosed or screened, with acoustic walls 3 ft above ground equipment; no 12 ft minimum, § 245-14.20.5.D(6)
Section 245-14.20.5.D(15) requires an Emergency Response Plan reviewed by the Fire Marshal and emergency providers before conditional use approval, an annual public safety meeting, and 24-hour contact signs, but no municipal official accepts the plan, annual updates are not required, and no annual site walk-through is offered to responders.
200 ft setback for fuel and hazardous material tanks and secondary containment, § 245-14.20.5.D(12) and D(14).
Annual fire safety inspections; no third-party electrical inspection before occupancy, § 245-14.20.5.D(15)(e)
Refers to the base traffic impact study requirements of Chapters 220 and 245, § 245-14.20.5.D(21)(a)
Two emergency vehicle accesses; no arterial or collector road requirement, § 245-14.20.5.D(15)(m)
Truck routes, road maintenance agreement, and road damage security; no work hours, § 245-14.20.5.D(21)
125% security and notice of closure, but removal may take up to 240 days after a final abandonment finding, § 245-14.20.5.D(23)
Section 245-2.1 defines a data center to include artificial intelligence infrastructure, cryptocurrency mining, and blockchain processing, and treats customarily accessory computer equipment as a principal data center when it exceeds 5,000 square feet in aggregate.
Annual reports on generator hours and complaints and an ongoing water monitoring and reporting plan, § 245-14.20.5.D(9)(a)ii, D(15)(r) and D(17)(a)iv
Section 245-14.20.5.D(13)(e)vi and vii and Section 181-2.9 make noise exceedances violations with penalties and revocation of the temporary certificate of occupancy, but no notice and hearing precede revocation and Sections 616.1 and 617.2 of the Municipalities Planning Code are not cited.
Section 245-14.20.5.D(9)(f) and D(13)(e)v allow third-party review of the cooling certification and noise data at the applicant's expense, but the applicant is not required to pay for consultant review of its studies in land development review.
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the IND Industrial District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data