Union Township
Anti-Data Center Policies
Union Township allows data centers only with conditional-use approval in heavy industrial areas, at least 1,000 feet from homes, and subject to size, spacing, utility, safety, and study requirements.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Union TownshipRegulates data centers as a conditional use in Union Township’s H-1 Heavy Industrial District, defining them to include associated utilities, backup systems, communications infrastructure, and security systems; the Board of Supervisors approved adoption on June 29, 2026.Pennsylvania Union Township Data Center Ordinance (2026)
What this means
The measure would allow data centers only as conditional uses in the heavy industrial district and bars them within 1,000 feet of residential property, creating major limits on where they can be built (conditional uses in H-1 and 1,000 feet from residential property). It also requires utility-capacity documentation, fire protections, sound studies, and size and spacing limits, adding substantial cost and delay; it is not an outright ban.
People behind it
- C. Hanford
Moved to adopt the 2026 Data Center Ordinance.
- L. Speer
Seconded the motion to adopt the 2026 Data Center Ordinance.
- Union Township Board of Supervisors
Proposed, held the public hearing on, and adopted the Data Center Ordinance.
Show 2 more peopleShow fewer people
- Michalle M. Dupree
Chairman of the Union Township Board of Supervisors and signatory on the ordinance and public notice.
- Lauren Rupcic
Township Secretary identified in the ordinance's attestation.
Restrictions & requirementsHide restrictions & requirements14
Data centers are conditional uses in the H-1 Heavy Industrial District, limiting them to that zoning district and requiring conditional-use approval.
Data centers and their exterior equipment must be at least 1,000 feet from residential property, measured radially.
Applicants must provide an electrical-provider letter certifying that the grid can serve the facility while maintaining sufficient service for existing township residents and businesses.
Applicants must provide a raw-water needs and sources analysis and a water-provider letter certifying sufficient capacity without reducing service to existing residents and businesses.
Data centers must use automatic fire suppression systems complying with NFPA 75 and 76, subject to the Township's reasonable satisfaction.
A gravel berm must extend at least 30 feet under and around each storage structure, and must be large enough to serve as a fire break.
Developers must provide township fire companies annual training on facility-specific firefighting procedures and hazards, update them about changes, and pay for any special firefighting equipment and related training.
Buildings may not have blank exterior walls, and must include adequate fenestration plus horizontal and vertical breaks every 35 linear feet.
Buildings must use durable brick or other context-sensitive masonry materials with color variation, and rooflines must vary throughout.
Each data-center building is limited to 80,000 gross square feet, with at least 300 feet between other similar uses.
Applicants must submit preconstruction and post-construction sound studies covering exterior rooftop and ground-mounted utility equipment; the post-construction study must be submitted before an occupancy permit is issued.
Rooftop and ground-mounted sound-producing equipment must be fully screened, with screening positioned to shield the direction of emitted sound.
Proposals must include roof-mounted solar panels at the maximum allowance under the Zoning Ordinance to offset the facility's power needs.
Proposals must use the latest water-conservation technology, including closed-loop systems, to reduce demand for public water.
Benefits & exceptionsHide benefits & exceptions3
Data centers are expressly authorized as conditional uses in the H-1 Heavy Industrial District, allowing them to be proposed and developed there subject to conditional-use approval. Data Centers are a Conditional Use in H-1 Heavy Industrial District
The data-center definition includes accessory and supporting utilities, infrastructure systems, mechanical equipment, cooling systems, backup power supplies, redundant communications connections, and security systems, allowing these associated facilities to be treated as part of the data-center use. accessory and supporting public utilities
The ordinance permits each data-center building to contain up to 80,000 gross square feet and establishes a framework for multiple similar buildings, provided they are separated by at least 300 feet. limited to no more than 80,000 gross square feet
Sources
current law · Union TownshipRequires data centers to be approved conditionally in heavy industrial zones and meet requirements for distance from homes, utility capacity, fire safety, building design, noise, solar power, and water conservation.Union Township Zoning Ordinance Section 280-117, Data Centers
What this means
It would allow data centers as conditional uses in heavy industrial areas, but the 1,000-foot separation from residential uses and limits on building size and spacing could rule out many sites. Developers would also need to meet utility, water, fire-safety, sound-study, design, and conservation requirements, creating significant costs and hurdles.
People behind it
- Union Township Board of Supervisors
The ordinance identifies the Board as the body that enacted and ordained the measure: “ENACTED AND ORDAINED by the Board of Supervisors”.
Restrictions & requirementsHide restrictions & requirements15
Data centers are allowed only as conditional uses in the H1 Heavy Industrial District, requiring conditional-use approval. Conditional Uses in H1
A data center building or exterior equipment must be at least 1,000 feet from residential property. 1,000 feet
An application must include an electrical-provider letter certifying the grid can serve the facility while maintaining service levels for existing township residents and businesses. letter from the electrical provider
An application must include the developer’s analysis of anticipated raw-water needs and sources, plus a water-provider letter certifying sufficient capacity while maintaining existing service levels. analysis of the anticipated raw water needs
Data centers must use an automatic fire-suppression system compliant with NFPA 75 and 76, to the Township’s reasonable satisfaction. NFPA 75 and 76 Standards
A gravel berm must extend at least 30 feet under and around any storage structure and be large enough to serve as a fire break. at least 30 feet under and around
The developer must provide township fire companies annual training on site-specific firefighting procedures, methods, and hazards, and promptly advise them of necessary changes. annual training on firefighting procedures
If special equipment is needed to fight a data-center fire, the developer must pay for it, and fire departments must be trained to use it. at the expense of the developer
Buildings may not have blank exterior walls; they must provide adequate fenestration and horizontal and vertical breaks every 35 linear feet. breaks every 35 lineal feet
Building materials must be durable brick or other context-sensitive masonry with color variation, and rooflines must vary. durable, consisting of brick
Each building is limited to 80,000 gross square feet, and similar uses must be at least 300 feet apart. 80,000 gross square feet
Applications must include pre- and post-construction sound studies examining sound-producing exterior utility functions and identifying compliance with the applicable zoning sound standard; the post-construction study is due before an occupancy permit may issue. submitted prior to an occupancy permit
Sound-producing rooftop and ground-mounted equipment must be fully screened from view, with screening positioned to shield emitted sound. fully screened from view
Proposals must include roof-mounted solar panels at the maximum allowance specified in the zoning ordinance to offset the facility’s power needs. at the maximum allowance
Data centers must include the latest water-conservation technology, including closed-loop systems to reduce public-water demand. including utilizing closed loop systems
Benefits & exceptionsHide benefits & exceptions2
Data centers are allowed as conditional uses in the H1 Heavy Industrial District, subject to conditional-use approval and the ordinance’s requirements (“Data Centers” as Conditional Uses).
The definition of a data center includes accessory and supporting utilities, infrastructure, mechanical equipment, backup power, and redundant data connections, bringing these facilities within the ordinance’s data-center framework (“accessory and supporting public utilities”).
Sources
current law · Union TownshipRequires data centers in Union Township to obtain conditional-use approval in heavy industrial zones and meet rules on location, utility capacity, fire safety, building design, noise, solar power, and water conservation.Union Township Data Center Ordinance
What this means
Data centers would still be allowed in the heavy industrial zone, but only with conditional-use approval, and they must stay 1,000 feet from homes (1,000-foot separation). The 80,000-square-foot building limit, spacing rules, and requirements for utility capacity, sound studies, fire safety, solar panels, and water conservation create significant added hurdles and costs (building-size limit).
People behind it
- Board of Supervisors of Union Township, Washington County, Pennsylvania
Enacted and ordained the ordinance.
Restrictions & requirementsHide restrictions & requirements17
Data centers require conditional-use approval in the H1 Heavy Industrial District. Conditional use in H1
A data center building or exterior equipment must be at least 1,000 feet from any residential use. 1,000 feet
Each proposal must include an electrical-provider letter certifying the grid can serve the facility while maintaining sufficient service for existing township residents and businesses. Electrical-provider capacity letter
Each proposal must include the developer’s analysis of anticipated raw-water needs and proposed sources. Raw-water needs and sources
Each proposal must include a water-provider letter certifying capacity to serve the facility while maintaining sufficient service for existing township residents and businesses. Water-provider capacity letter
Facilities must use an automatic fire-suppression system complying with NFPA 75 and 76, to the Township’s reasonable satisfaction. NFPA 75 and 76
A gravel berm must extend at least 30 feet under and around any storage structure and be large enough to serve as a firebreak. At least 30 feet
The developer must provide township fire companies annual training on facility-specific firefighting procedures, methods, and hazards, and advise them of necessary changes as soon as reasonably possible. Annual training
The developer must pay for any special equipment needed to fight a data-center fire and ensure fire departments are trained to use it. Equipment at the developer’s expense
Buildings may not have blank exterior walls; they must include adequate fenestration and horizontal and vertical breaks every 35 linear feet. Breaks every 35 lineal feet
Buildings must use durable brick or other context-sensitive masonry materials with color variation, and rooflines must vary. Building materials and rooflines
No individual data-center building may exceed 80,000 gross square feet. 80,000 gross square feet
Data centers must be at least 300 feet from other similar uses. At least 300 feet
Each proposal must include pre- and post-construction sound studies covering exterior sound-producing utility functions and identifying compliance with the applicable ordinance standard; the post-construction study is due before an occupancy permit may issue. Post-construction study before occupancy
Sound-producing rooftop and ground-mounted equipment must be fully screened from view, with screening positioned to shield the direction of emitted sound. Screen equipment to shield sound
Proposals must include roof-mounted solar panels at the maximum allowance under the zoning ordinance to offset the facility’s power needs. Maximum allowable solar panels
Proposals must include the latest water-conservation technology, including closed-loop systems, to reduce demand for public water. Closed-loop systems
Benefits & exceptionsHide benefits & exceptions1
Data centers are allowed to seek conditional-use approval in the H1 Heavy Industrial District, creating a zoning path for them to be built there. “Data Centers” as Conditional Uses
Sources
current law · Union TownshipThe Board of Supervisors held a hearing and unanimously adopted the Union Township Data Center Ordinance of 2025 (Ordinance No. 6, listed on eCode360 as Ordinance No.Union Township, Washington County — data-center ordinance / amendment 2025-06 (2025-10-22)
What this means
A score of -3 is assigned as the requested fallback because the available sources do not provide enough detail to assess the impact. It should not be read as a source-confirmed finding of significant barriers.
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data