Union Township

Anti-Data Center Policies

Union township’s listed measure limits noise, requires sound testing, sets setbacks from homes and other protected places, and restricts building height; data centers may still be approved, but compliance can add costs.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Union City
Borough Council adopted Ordinance No. 1188 on August 11, 2026, the same day as its public hearing, amending Zoning Ordinance No. 1118.Union City, Erie County — data-center ordinance (No. 1188)

What this means

The measure imposes noise limits and sound testing, setbacks from homes or other protected places and building-height limits. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements25
  • Environmental Impact Assessment including riparian buffers and wetlands, and floodplain exclusion, § 4.B and J

  • 67 dBA day and 57 dBA night and weekend at the property line, 57 dBA at residential boundaries, § 4.C.1 and C.4

  • Section 4.C.1 requires preliminary, interim, and as-built studies using ANSI S1.4 meters and generally accepted methodology.

  • Vibration study showing nothing perceptible beyond the property line, § 4.C.2.

  • Water Utilization Report and provider capacity certification; wells not barred, § 4.F

  • Cooling system type and efficiency disclosed, § 4.F.1

  • Total daily intake volume disclosed; no cap, reporting, or drought plan, § 4.F.1

  • Section 4.G requires the applicant to demonstrate that domestic, cooling, and industrial wastewater disposal has been provided and approved by the Union City Municipal Authority or DEP.

  • Compliance with borough stormwater ordinances required, § 4.F.1

  • Backup generators must meet EPA Tier 4 with annual testing reports, § 4.D

  • Thermal Impact Mitigation Plan including waste heat reuse, § 4.I.

  • Electronic Waste Plan for servers, hazardous materials, and batteries, § 4.H.

  • Provider certification of capacity; no third-party electrical inspection, § 4.E.3.

  • Energy Management Plan; renewable energy is a good-faith effort only, § 4.E.1 to E.2

  • On-site generation is a separate use with separate permits; no separate setbacks, § 4.E.4

  • Accessory substations screened or enclosed near roads and homes, § 4.R.1

  • Known rate impacts must be provided, § 4.E.3

  • 100-ft buffer along property lines next to residential uses or zoning, § 4.P.2.

  • Equipment within 75 ft enclosed or screened, rooftop screened on four sides; no height standard, § 4.R

  • Emergency Response Plan accepted by the fire department with 24-hour contact signage; no annual updates, § 4.V

  • First responders must receive system-specific training, § 4.V

  • Annual fire safety inspections, § 4.V

  • Section 4.B.2 requires a traffic study of the impact of data center traffic on the surrounding area, neighborhoods, and roads.

  • One as-built sound study after opening; annual reports cover emissions, not noise, water, or power, § 4.C.1 and D.2

  • Section 4.X requires a $5,000 escrow, replenished on request, for Borough engineering and legal fees in the application and permitting process.

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Special exception in the Industrial District