Borough of Trappe
Anti-Data Center Policies
Trappe Borough allows data centers only through conditional-use approval in its Limited Industrial zone, with a 500-foot setback and noise limits and testing. Required studies and safeguards may raise costs and narrow suitable sites, but do not ban projects.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Trappe BoroughRestricts data centers to conditional-use review in Limited Industrial zones and requires safeguards for setbacks, noise, water and power use, emergency planning, and decommissioning.Trappe Borough Zoning Ordinance, Chapter 340, § 340-254 (Data Center)
What this means
Data centers would only be considered through conditional use in the Limited Industrial zone, and must meet a 500-foot minimum setback. The required noise, water, power, emergency-planning, and decommissioning studies and safeguards could add substantial costs and make suitable sites hard to find, though they do not amount to a ban.
People behind it
- Mark Plachta
Borough Solicitor who presented Ordinance #481 for Council’s official consideration.
- Scott Martin
Moved the motion to adopt Ordinance #481.
- Heather Gustafson
Seconded the motion to adopt Ordinance #481.
Show 1 more peopleShow fewer people
- Bob Korp
Identified as participating in the process of creating the zoning amendment.
Restrictions & requirementsHide restrictions & requirements13
Data centers are not permitted in the IGO district and may be considered only through a conditional-use application in the Limited Industrial district. The minutes state these location and approval limits.
A data center must be set back at least 500 feet from property lines, or farther if the district’s maximum setback requires it. The setback also applies to major-impact sources such as generators, substations, mechanical equipment, buildings, accessory uses, and truck idling. The ordinance sets the 500-foot minimum.
The site plan must reserve adequate area for at least one future microgrid element, such as a backup power source, battery storage, geothermal, solar, or wind; the stormwater system must count these reserve areas as impervious cover. The ordinance requires microgrid reserve areas.
Applications must include noise and vibration studies prepared by qualified noise professionals, with measurements at property lines and evaluations that assume simultaneous operation of noise-producing equipment at maximum rated capacity. Limits vary by neighboring land use: 40 dBA for residential/agricultural, 50 dBA for commercial, and 55 dBA for industrial; low-frequency noise is limited to 50 dBC. The ordinance specifies the study and noise limits.
Noise studies are required at preliminary, building-permit, and post-construction stages; post-construction verification is due within 180 days after operations begin. Exceedances must be remedied, and probable violations may lead to interim mitigation, operational changes, equipment limits, or temporary curtailment. The ordinance requires post-construction verification and remedies.
For public water, the application must include the supplier’s written certification that service will be adequate and will not adversely affect Borough customers. For nonpublic water, it must include a professional water study addressing demand, sources, recycling or discharge, nearby wells and surface waters, and potential impacts; a drought-response plan is required regardless of water source. The ordinance requires water-service documentation and a drought plan.
The application must include a professional study of wastewater-disposal feasibility and, for service by a public system, written confirmation of capacity. Discharging untreated wastewater into stormwater systems or surface waters is prohibited. The ordinance requires a wastewater feasibility study.
The applicant must obtain a written statement from the electric utility about available power, effects on service and customer costs, and power sources. If serving the center would adversely affect service quality, reliability, or customer costs, the applicant must pay for necessary system improvements. The ordinance assigns required power-system improvements to the applicant.
Backup generators must meet Tier IV requirements. Commissioning and testing are limited to 7 a.m.–7 p.m. Monday through Friday, excluding national holidays; other generator activity is limited to backup or emergency use. The ordinance sets generator standards and hours.
An application must include an engineer-prepared thermal-impact mitigation plan addressing waste heat, off-site effects, mitigation measures, and feasible opportunities for waste-heat reuse. The Borough may require supplemental or amended plans before approving the use. The ordinance requires a thermal-impact plan.
Applicants must submit an emergency-planning report addressing fire, EMS, and emergency-management impacts and emergency procedures. Local first responders must receive facility-specific training at the owner’s expense before operations begin, and annual fire-safety inspections are required. The ordinance requires first-responder training at the owner’s expense.
A zoning permit is required before a building permit, and new construction requiring land development review must obtain land-development-plan approval before the use is established. The ordinance requires a zoning permit and prior land-development approval.
A qualified professional must prepare a decommissioning plan. Decommissioning must begin within one year after operations cease or abandonment is noticed and generally be completed within 18 months after it begins; the Borough may allow a one-year extension for active marketing for a compatible replacement use. The owner, operator, or developer must post financial security, calculated from decommissioning costs and reviewed by the Borough, and maintain it through periodic updates. The ordinance sets the decommissioning timetable and security requirement.
Benefits & exceptionsHide benefits & exceptions3
Data centers may be considered through a conditional-use application in the Limited Industrial zone; this is an approval pathway, not automatic permission. Conditional Use Application in Limited Industrial Zone
A data-center site layout must include adequate reserve areas for at least one future microgrid element, with examples including backup power, battery storage, geothermal, solar, and wind. The stormwater system must count those reserve areas as impervious cover. adequate reserve areas to support at least one future microgrid element
A lawfully established data-center use that later becomes nonconforming may continue, subject to the ordinance’s nonconforming-use rules. The ordinance also presumes abandonment if the use ceases for six continuous months, and limits changes to a less-restrictive use. may continue on such land
Sources
current law · Trappe BoroughBorough Council adopted the provisions in Ordinance 481 by a 7-0 vote on September 1, 2026 after a public hearing, according to the posted minutes, which also state that data centers are not permitted in the Institutional Government Overlay.Trappe Borough, Montgomery County — data-center ordinance (No. 481)
What this means
The measure imposes setbacks from homes or other protected places, limited eligible locations and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements21
Conditional use; no approval expiration
Section 340-254.B(3) Table 2 sets a single 40 dBA one-hour Leq limit day or night at residential and agricultural property lines, measured with a Type 1 or Type 2 meter under Table 5, but it allows 50 dBA at commercial and 55 dBA at industrial property lines at all hours.
Section 340-254.B(3) Table 6 treats an increase of 3 dBA or more above the baseline ambient level documented before construction as a violation, measured under the Table 5 procedures.
50 dBC day and night
Section 340-254.B(2) and Table 4 require a pre-construction study modeled under ISO 9613-2 or an equivalent model and a post-construction verification within 180 days, and Table 5 requires Type 1 or Type 2 meters with measurements at peak cooling load and generator operation under load.
Numeric vibration limits with study
Water service study for nonpublic sources; no pump tests
Cooling method not addressed
Drought response plan and projected demand; no ongoing reporting
Wastewater feasibility study; no cooling discharge plan
Stormwater design must count reserve areas as impervious
Tier IV generators; no annual emissions testing
Thermal Impact Mitigation Plan with waste heat reuse review.
Hazardous materials disposal at decommissioning
Utility statement with application; no third-party inspection.
Substations subject to the 500 ft setback
Section 340-254.D(1) requires a written statement from the electric utility on adequate power, cost and reliability impacts, and the source of power and any proposed substations, with the applicant paying for system improvements needed to avoid adverse impacts.
Emergency planning report; no radio coverage or annual update
Annual fire safety inspections
Net cost plus 10% security and closure notice; removal within 18 months
Applicant pays the Borough's review costs for decommissioning estimates
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Limited Industrial District
Sources