Towamencin Township

Anti-Data Center Policies

Towamencin allows data centers only with conditional-use approval in limited industrial areas, subject to siting, road-access, utility, power, water, cooling, and noise restrictions. The enacted rules limit where and how facilities can operate but do not ban them outright.

Incentives

Financial Incentive
2

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · Towamencin Township
Amends Towamencin Township’s data-center rules, but the provided document does not show what specific changes it makes.Ordinance 26-08 — Amended Data Center
current law · Towamencin Township
Restricts data centers to conditional-use approval in the limited industrial district and sets rules for their location, utilities, noise, cooling systems, backup power, screening, public meetings, emergency plans, and decommissioning.Ordinance 26-04 — Data Centers

What this means

The measure would allow data centers only through conditional use in the limited industrial district, with siting and road-access limits, including a rule that the site not directly abut or be adjacent to residential uses. It also requires public-utility capacity confirmation, bans onsite private power and groundwater use, and imposes cooling and noise controls, creating significant costs and operating limits despite not banning data centers outright.

People behind it

  • The ordinance identifies the Board as the body enacting the measure. “BE IT ENACTED AND ORDAINED”

Restrictions & requirementsHide restrictions & requirements15
  • Data centers are added as uses by condition in the LI Limited Industrial District, requiring conditional use approval. uses by condition list

  • A data-center tract may not directly abut or be adjacent to a residential district or residential use, inside or outside the township. shall not directly abut

  • The tract must have direct access to an arterial street, and access improvements must extend to the nearest intersection with an arterial street. direct access to an arterial street

  • Data Center Equipment may not be placed between the building and the street and must be separated from adjacent residential uses by a principal building. Accessory uses and equipment must be on the same tract or on adjacent parcels developed as a unified data-center development; accessory uses must meet principal-building setbacks and the specified height limits. shall not be located between the building and the street

  • The use must rely on public electric, water, and sewer utilities. Applicants must submit provider will-serve letters and a professional capacity assessment, including projected needs for future municipal growth, to the Township Engineer’s satisfaction. If capacity is insufficient, the applicant must pay for the necessary public-utility system improvements. at its own expense

  • Conditional use approval is prohibited for data centers proposing groundwater wells, springs, direct surface-water withdrawals, or onsite private power generation in whole or in part. No conditional use approval shall be granted

  • Generators may be used only for backup or emergencies; testing is allowed only on weekdays from 9:00 a.m. to 5:00 p.m. backup/emergency use only

  • Utility lines from substations to a data center must be placed underground to the extent practical. placed underground

  • Parking must be provided at one space per 10,000 square feet of principal-structure gross floor area, including data halls, equipment rooms, and support spaces, or one space per employee on the largest shift, whichever is greater. Parking for portions devoted to other uses follows those uses’ requirements. whichever is greater

  • Mechanical equipment must be fully enclosed unless manufacturer specifications make enclosure mechanically infeasible. In that case, equipment visible from ground level from existing or planned public roads or adjoining parcels must receive visual screening satisfactory to the township. fully enclosed

  • Mechanical equipment must have acoustical barriers, and a professional acoustical expert’s sound study must demonstrate compliance at all property lines: no more than 65 dB(A) daytime (7:00 a.m.–8:00 p.m. Monday–Friday) or 55 dB(A) nighttime (8:00 p.m.–7:00 a.m. Monday–Friday and all day Saturday and Sunday). Studies are required during conditional use, building-permit, and as-built stages; the as-built study is due six months after the certificate of occupancy and may be required later on request. Violations must be promptly remediated. The limits are exempt during a power outage, but the study must report anticipated levels with all equipment running. maximum nighttime decibel level of 55 dB(A)

  • Water-based cooling must use a closed-loop system. Facility water may not be discharged, released, or exported except through an approved public sanitary sewer connection; open-loop, once-through, and water-intensive evaporative cooling systems are prohibited. expressly prohibited

  • Before filing a conditional use application, the applicant must hold a public informational meeting, publicized and conducted to reasonably inform the general public, with knowledgeable data-center representatives attending. prior to any Conditional Use application

  • At building-permit issuance, the owner or owner/operator must provide an emergency-management plan satisfactory to the Township Emergency Management Coordinator, demonstrating adequate fire, police, and emergency-service coverage, including for intentional external, natural, and man-made threats. provide an emergency management plan

  • At building-permit issuance, the owner or owner/operator must enter a written decommissioning agreement. After discontinuation or cessation, the township must be notified within three months, and servers, electronic data-storage devices, and batteries must be removed within 18 months, subject to extension for good cause. Written removal certification is due within 10 days after removal, and the township must be allowed to inspect. If removal is not completed, the township may (but need not) remove the items at the owner’s or operator’s expense and lien the tract for the cost. within 18 months

Benefits & exceptionsHide benefits & exceptions1
  • The measure provides a zoning approval route for data centers in the districts where they are allowed as a conditional use. Approval is not automatic; proposals must meet the ordinance’s applicable conditions. (conditional use)

Sources

current law · Towamencin Township
The Board of Supervisors adopted the rules as Ordinance 26-04 on April 29, 2026 and replaced the data center standards with Ordinance 26-08, enacted October 14, 2026.Towamencin Township, Montgomery County — data-center ordinance / amendment 26-08

What this means

The measure imposes setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements23
  • Conditional use; no approval expiration in the data center text

  • 1,000 ft from residential uses and districts, with accessory uses including data center equipment held to the same setback and the tract barred from abutting residential uses, § 153-502(E)(14)(a), (c), and (d)[2]

  • LI height limits of § 153-414 apply, § 153-502(E)(14)(d); rooftop equipment screened by an acoustical barrier but not counted

  • 45 dBA weekday daytime and 40 dBA at night and weekends at the property boundary, with ANSI S1.4-2014 meters, § 153-612(B)(1) and (4)

  • 60 dBC by day and 50 dBC at night at all property lines with full-spectrum low-frequency modeling, § 153-612(B)(4)

  • Preliminary, interim, and as-built studies with ANSI S1.4-2014 meters, § 153-612(B)(4); the as-built study is not tied to full operating load

  • Generator testing weekdays 9:00 a.m. to 5:00 p.m.; no hours cap, § 153-502(E)(14)(d)[3][vi]

  • Public utilities only and no approval for groundwater wells, springs, or surface withdrawals, § 153-502(E)(14)(d)[3] and [3][iv]

  • Closed-loop required; open-loop, once-through, and evaporative cooling prohibited, § 153-502(E)(14)(j)

  • Diesel generators must meet EPA Tier 4, § 153-502(E)(14)(d)[3][vi]; no annual emissions testing or reports

  • Thermal Impact Mitigation Plan with off-site impact evaluation and waste heat reuse review, § 153-502(E)(14)(n); no modeled property line temperatures

  • Electronic Waste Plan for servers, batteries, and hazardous materials, § 153-502(E)(14)(m); no disposal contract

  • Electric will-serve letter, filed utility application, and signed transmission security agreement with the conditional use application, § 153-502(E)(14)(d)[3][i]-[ii]

  • Certified Energy Usage Plan with annual demand and efficiency measures, § 153-502(E)(14)(d)[3][ii]; no peak demand by phase or solar requirement

  • On-site private power generation barred except backup generators and rooftop solar or wind, § 153-502(E)(14)(d)[3][v]

  • Lines from substations underground where practical and mechanical equipment enclosed or screened, § 153-502(E)(14)(d)[4] and (h)

  • Utility capacity assessment with applicant-funded system improvements and a transmission security agreement, § 153-502(E)(14)(d)[3][ii]-[iii]; no cost or tariff disclosure

  • All mechanical equipment fully enclosed or fully screened, with an acoustical barrier on all exterior equipment, § 153-502(E)(14)(h)-(i)

  • Emergency Response Plan acceptable to the Fire Marshal and fire department, with 24-hour contacts kept on file, § 153-502(E)(14)(e); no annual update

  • Containment procedures in the response plan and hazardous materials in the waste plan, § 153-502(E)(14)(e)[3] and (m); no storage setbacks

  • Annual fire safety inspections by a qualified professional, § 153-502(E)(14)(e)[5]; no report or correction deadline

  • Decommissioning agreement, equipment, batteries, fuel, and refrigerant removed within 18 months, Township lien on default, § 153-502(E)(14)(o); no financial security

  • As-built sound study after occupancy and every two years thereafter, § 153-612(B)(4)(c)

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the LI Limited Industrial District