Todd Township
Anti-Data Center Policies
Todd Township’s enacted ordinance requires setbacks from homes and other protected places, cooling and water-use rules, and noise limits and sound testing; approval remains possible, but these limits narrow where and how data centers can operate.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · Todd TownshipThe Board of Supervisors adopted these standards as Ordinance No. 1 of 2026 on August 6, 2026, effective immediately.Todd Township, Fulton County — data-center ordinance (No. 1 of 2026)
What this means
The measure imposes setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements31
Township has no zoning; no district limits
Board of Supervisors approves applications with a land development plan; no conditional use hearing or special exception, Section 7
Buffer widths scale with footprint; no footprint or megawatt cap, Section 5(p)
Section 5(c)(2) applies the 1,000-foot setback from existing residential structures and Sensitive Receptors to principal buildings, accessory structures, and substations, and the Data Center Accessory Use definition includes generators, cooling towers, and environmental control equipment.
65 ft maximum building height, Section 5(b)
Riparian forest buffer of 100 ft on each side, wider on steep slopes and 25 ft more at wetlands, Section 5(y)
Single 57 dBA CNEL limit at sensitive receptor, developed and residential property boundaries, Section 5(f)(1)
Noise limit applies to regular testing of equipment; no testing hours or cap, Section 5(f)(1)(d)
Water feasibility study for nonpublic water, including effects on wells within 1,000 ft; no pump test or well bar, Section 5(s)
Closed loop cooling required and open-loop, once-through and discharge-based systems prohibited; evaporative cooling not restricted, Section 5(v)(2)(b)
Projected water demands disclosed in the feasibility study; no cap, reporting, or drought plan, Section 5(s)
Sewer authority must certify capacity, and discharges are described in the water study, Section 5(s)
Stormwater management plan under the Township SALDO, Section 5(u)(3)
Tier 4 or greater generators required; no annual emissions testing, Section 5(m)
Disposal of materials must comply with state and federal rules; no recycling plan, Section 5(q)(3)
Utility verification of capacity and third-party final electrical inspection, Section 5(i)
Renewable energy, rooftop solar and LEED only encouraged; no energy usage plan, Sections 5(v) and 5(w)
On-site generation permitted subject to environmental, safety, and interconnection standards, Section 5(m)
Substations screened and placed to the side or rear; on-site lines of 34.5 kV and below buried, Section 5(l)
Planted buffer yard of at least 100 ft along lines within 500 ft of homes, rising to 150 or 300 ft for larger footprints, Section 5(p)(3).
Fully shielded with no light across property lines, 0.2 footcandle average, and photometric plan review, Section 5(j)
Low-reflective earth tone colors required; fluorescent and metallic colors prohibited, Section 5(r).
Ground equipment behind opaque wall and rooftop equipment screened on four sides; no 12-ft or acoustic standard, Section 5(p)(2)
Visual impacts to be minimized in siting; no study or elevations required, Section 5(a)
Emergency Response Plan to county EMA and fire departments, in-building radio coverage, 24-hour contact signs; no annual updates, Sections 5(n) and 5(t)
Applicant must confirm local departments have needed supplies; no training or funding, Section 5(t)
Third-party final electrical inspection; no annual fire inspections, Section 5(i)(5)
Vehicle trips described in impact analysis; no traffic study, Section 5(q)(1)
Security of at least 100% of net removal cost; no closure notice or removal deadline, Section 6
Section 7 revokes approval if the facility is moved or altered out of conformity and provides judgments of up to $600 per day through the district justice, but it requires no notice or hearing before revocation.
Applicant pays Township engineer and Solicitor review fees and costs, Section 7(D)