City of Titusville

Neutral Data Center Policies

Titusville permits computer and data-processing centers in its Industrial Overlay District, but projects there must still meet requirements such as off-street parking.

current law · City of Titusville
Allows computer centers and data-processing service centers in Titusville’s Industrial Overlay District, subject to the district’s zoning requirements.Ordinances | City of Titusville, Pennsylvania

What this means

The code specifically lists computer centers and data-processing service centers as permitted uses in the Industrial Overlay District, which gives data-center projects a clear path in that area. The benefit is limited because it applies only in that district, and projects still face requirements such as off-street parking.

People behind it

  • Enacted and adopted Ordinance No. 3182.

  • Identified as the Zoning Officer; the ordinance assigns the Zoning Officer responsibility for administering and enforcing its provisions.

Restrictions & requirementsHide restrictions & requirements8
  • The ordinance expressly lists computer centers and data-processing service centers as permitted uses in the Industrial Overlay District (IOD); a proposed site must also comply with the use rules for its zoning district. “Computer Centers; Data Processing Service Center”

  • In the IOD, new construction must meet the stated 20-foot yard requirements from established boundaries and structures existing as of the applicable effective date. “20 feet from established boundary”

  • IOD structures may not exceed 45 feet unless the Zoning Hearing Board approves a special exception based on safety and aesthetic concerns and compliance with applicable laws. “No structure shall exceed forty-five (45) feet”

  • A new IOD use or enlargement of an existing use must provide off-street parking under the Industrial District standards. Alternatives may be considered, but designated off-site parking may not be more than 1,000 feet from the IOD boundary. “Off-street parking space shall be provided”

  • A zoning certificate is required before using vacant land or a newly constructed, moved, enlarged, or differently used structure. The application must include a plot plan and a City-established fee; an authorized use or work not initiated within six months makes the certificate or permit void. “A zoning certificate shall be obtained”

  • For a land development involving a building or buildings totaling 5,000 square feet or more, the zoning permit alone does not satisfy the land-development process: a final site plan must be approved and recorded. Developments under 5,000 square feet in aggregate may use a zoning permit as compliance with that process. “less than five thousand (5,000) square feet”

  • Land-development applications require a site plan and review process; applicable DEP and highway-occupancy permits must be secured, and the final site plan must be recorded. The process also carries City-established application, review, and inspection fees. “Final Site Plan has been approved”

  • Land-development site plans must include landscaping, and at least 5% of the lot area must be landscaped. “At least five percent (5%) of the lot area”

Benefits & exceptionsHide benefits & exceptions5
  • The Industrial Overlay District (IOD) expressly lists “Computer Centers; Data Processing Service Center” as a permitted use, rather than a conditional use. Computer Centers; Data Processing Service Center.

  • The IOD relaxes dimensional requirements: the table sets no minimum lot area or lot width, zero front, side, and rear yards for current structures, and 20-foot setbacks for new construction from the stated established boundaries and existing structures. The district’s general height limit is 45 feet, with a possible special exception from the Zoning Hearing Board. IOD lot and yard requirements.

  • If the IOD provisions conflict ambiguously with other zoning rules, the ordinance directs that the ambiguity be interpreted to produce the least restrictive application of the overall ordinance to the IOD. least restrictive application.

  • For a new or enlarged IOD use, the ordinance allows alternatives to the usual industrial off-street parking allocations to be considered; designated off-site parking must be within 1,000 feet of the IOD boundaries. Alternatives to traditional off-street parking.

  • Essential services are listed as a permitted IOD use, which can accommodate qualifying utility infrastructure; the ordinance defines essential services to include utility transmission and distribution systems, but excludes office buildings and outside equipment-storage or maintenance depots. Essential Services.

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data