Borough of Tarentum
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Borough of Tarentum.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · Borough of TarentumRestricts data centers to approved commercial and industrial zones, where they must meet utility, noise, screening, safety, and reporting requirements.Draft zoning ordinance amendment: Data centers and cryptocurrency facilities
What this means
The measure would allow data centers only in specified commercial or industrial districts and only with conditional-use approval, excluding residential and several other districts (permitted districts). Utility studies and written utility-capacity certification, plus operating standards and a new approval for expansions above 10%, would add substantial cost and delay; because development remains possible in some districts, this is a significant barrier rather than a complete ban (utility certification).
People behind it
- Borough Council of the Borough of Tarentum
Enacted the ordinance and is responsible for conditional-use approvals and enforcement.
- Tarentum Borough Planning Commission
Reviewed the ordinance and provided a recommendation to Borough Council.
Restrictions & requirementsHide restrictions & requirements15
Data centers and related regulated computing facilities are prohibited in R-1 and R-2 residential, P-1 public, riverfront overlay, traditional neighborhood development, and any district where commercial or industrial uses are not specifically authorized. (prohibited zoning districts)
In designated commercial and industrial districts, a facility may proceed only with conditional-use approval after Planning Commission recommendation and Borough Council approval; approval is unavailable in unlisted districts. (permitted districts)
Conditional-use applicants must provide extensive studies and plans, including utility, water-capacity, traffic, noise, emergency-operations, security, construction-management and decommissioning plans; disclose generators and battery storage; provide a 10-year expansion plan; and show prior coordination with the Borough’s electric and water departments. (submission requirements)
The applicant must demonstrate that the project meets specified public-safety, utility, nuisance, compatibility, emergency-response and planning standards, and has received or is obtaining applicable special electric and water service agreements. (general conditional use standards)
No conditional-use approval may be granted until the Borough Manager and electric and water departments certify in writing that the facility can be served without adversely affecting existing customers. The Borough may hire independent licensed engineers to review utility studies at the applicant’s expense. (utility certification and review)
Principal structures must be at least 100 feet from a residential zoning boundary and 50 feet from a public right-of-way, with the more restrictive measurement applying. Outdoor equipment must be screened; residential-facing property lines require a 10-foot landscaped buffer, or, where space is insufficient, an opaque wall or fence at least 8 feet high. (setbacks and screening)
Facility noise may not exceed 55 dBA at the nearest residential property line from 7 a.m. to 10 p.m. or 45 dBA from 10 p.m. to 7 a.m. Emergency generator operation is exempt during emergencies; routine testing is exempt from the nighttime limit only if it does not occur during nighttime hours. (noise standards)
Exterior lighting must use full cut-off fixtures, and light at a property line adjoining a residential district may not exceed 0.1 footcandles; a photometric plan is required. (lighting standards)
Generators and fuel storage must meet applicable air-emissions, fire and fuel-storage rules; battery energy storage systems must comply with NFPA 855 and applicable codes. Fire-response plans addressing battery thermal runaway and generator operation must be coordinated with the Fire Department and submitted before operation. (emergency generation and battery storage)
Applicants must submit a construction-management plan covering traffic, worker parking, dust, noise, lighting, construction phasing and hours. The Borough Manager must receive written notice at least 30 days before construction begins, and Council may impose additional construction-phase conditions. (construction phase standards)
Approved facilities must file an annual report by March 1 covering the prior year’s monthly electricity and water use and peak demand, generator hours and fuel, five-year expansion plans, and material operational or equipment changes. Failure to report violates the ordinance. (annual reporting)
Before a building or land-development permit is issued, the applicant must submit a decommissioning plan covering equipment removal, site restoration, battery disposal, fuel-system removal and electronic-waste disposal. Council may also require a performance bond, letter of credit or escrow sufficient to fund decommissioning for the facility’s life. (decommissioning requirements)
An expansion exceeding 10% above approved footprint, connected electrical load or water demand requires a new or amended conditional-use application and Council approval. An expansion exceeding the Large Load Customer threshold must also meet the electric-service ordinance’s Article XIV requirements. (future expansion)
Violations or failure to meet approval conditions may lead to conditional-use revocation, enforcement proceedings, fines or civil penalties, court-ordered injunctive relief, or suspension or termination of electric or water service. (violations and enforcement)
The ordinance does not exempt facilities from other applicable requirements, including the Borough’s electric and water service ordinances, subdivision and land-development rules, floodplain and stormwater regulations, construction codes, and environmental, fire, building and electrical rules. (compliance with other regulations)
Benefits & exceptionsHide benefits & exceptions2
Regulated facilities may seek conditional-use approval in the Commercial Center, General Commercial, Light Industrial, Heavy Industrial, and any future commercial or industrial technology or innovation district. They are barred from residential, public, and overlay districts, and approval is not automatic. Eligible districts.
An approved facility may increase its footprint, connected electrical load, or water demand by up to 10% above approved levels without a new or amended conditional-use application. Larger increases require a new or amended application and Borough Council approval; increases exceeding the ordinance’s Large Load Customer threshold must also meet the electric-service ordinance’s requirements. Expansion limit.
Sources
pending · Tarentum BoroughThe draft (Ordinance 26-__) was posted on the borough website in June 2026 and discussed by Borough Council on June 9, 2026, and council agendas through the September 29, 2026 special meeting show no advertisement, hearing, or vote on it.Tarentum Borough, Allegheny County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose money set aside for eventual removal, technical studies and utility checks and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements18
55 dBA day and 45 dBA night at residential line, Section 7.3
Noise study with application only, Section 7.3
Water demand and capacity study, Section 6
Cooling system description required, Section 6
Monthly water use in annual report; no drought plan, Section 9
Generators must meet DEP air rules, Section 7.5
Servers, batteries, and e-waste in decommissioning; no refrigerants, Section 10
Borough electric utility certification; no third-party inspection, Sections 5 and 6.
Utility impact study of average and peak demand, Section 6
10-ft evergreen buffer next to residential districts, Section 7.2
Outdoor equipment screened from view, Section 7.2
Emergency operations plan with fire department, Section 4
Section 4(C) requires a Traffic Impact Analysis under PennDOT guidelines with every conditional use application, and Section 8(A) handles construction haul routes separately, but the study itself has no stated scope or study area.
Haul routes in construction management plan, Section 8
Plan required; financial security optional, Section 10
Annual report on power and water use, Section 9
Section 13 allows Borough Council to revoke conditional use approval following notice and an opportunity to be heard, and provides fines and civil penalties under 53 P.S. Section 10617.2.
Section 6 allows the Borough to retain independent licensed engineers at the applicant's expense to review the utility studies, but this review is part of the conditional use application rather than land development review.
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Conditional use in the CC, C-1, I-1, and I-2 districts (draft)
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data