Borough of Stewartstown
For Borough of Stewartstown, see York County’s laws and regulations below. No additional city or town-specific measures are listed in our research.
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Specific to York County only.
pending · County measureRecommends that municipalities adopt data center zoning rules covering siting, noise, lighting, safety, environmental impacts, emergency planning, and decommissioning.York County Planning Commission Data Center Model Ordinance
What this means
If adopted, the ordinance would make data centers harder and more costly to build and operate, with requirements for noise studies, environmental reviews, large buffers, and financial security for removal and cleanup—set at 110% of estimated decommissioning costs. These are significant barriers, though the document is a customizable model with some standards left for each municipality to fill in, not a blanket ban.
People behind it
- York County Planning Commission (YCPC)
Prepared the model ordinance offering suggested language for municipalities to consider.
Restrictions & requirementsHide restrictions & requirements25
The model requires data centers to meet its standards, applying the more restrictive rule if they conflict with other zoning rules. It also contemplates review through a conditional-use or special-exception process, including a sound study submitted with the application and an impact analysis provided before the hearing. conditional-use/special-exception application
Principal buildings, accessory structures, and data-center substations must be set back 150–200 feet from property lines; required parking setbacks are left as blanks for the municipality to fill in. set back at least
The ordinance must set a maximum building height, but the model leaves the height limit blank. maximum building height
The model requires at least one parking space per employee on the largest shift plus three visitor spaces, and at least one loading space. Loading spaces or bays may be on only one façade of the principal building. one parking space per employee
Buildings must be designed and sited to be compatible with the site and surrounding properties, reduce visual impacts from public streets and sensitive receptors, provide safe access and on-site gate queuing, accommodate parking, and minimize impacts to natural resources. Minimize visual impacts
The model sets noise limits of 60 dBA CNEL at the boundary of a property containing a sensitive receptor and 70 dBA CNEL at the boundary of a developed property without one. Sound lasting no more than one cumulative minute per hour may exceed those limits by up to 10 dBA. The limits do not apply to specified emergencies, snow removal, or road repair; C-weighted and octave-band noise must also be kept at acceptable levels. shall not exceed 60 dBA
Applicants must submit pre-construction and post-construction sound studies covering exterior sound-producing utility functions. A certified noise-control engineer must conduct them, and a municipality-selected qualified engineer reviews them. The post-construction study is due before occupancy; if it finds a violation, the owner or occupant must promptly remedy it. pre- and post-construction sound studies
Air, dust, smoke, glare, exhaust, heat, and humidity from a use or activity must not be perceptible at or beyond the property line. not perceptible at or beyond the property line
Electrical equipment must be housed in a metered, grounded, pre-engineered metal-encased structure rated to resist an internal electrical fire for at least 30 minutes, with fire baffles that close independently of a possible power failure. Battery or other energy-storage proposals must demonstrate compliance with NFPA 855 or similar standards and include battery-specific fire suppression. fire rating
Before a certificate of completion or occupancy, the applicant must obtain written service-provider verification of adequate capacity and infrastructure, adequate cooling and operation systems, defined storage capacity if applicable, efforts to maximize renewable or clean energy, and no electrical interference or voltage fluctuations. The municipality must also receive proof that electrical work passed a third-party final inspection. written verification from the applicable service provider
Lighting must be aimed down and shielded, with limits on light trespass of 0.1 footcandle at residential uses and 0.5 initial footcandle at nonresidential uses. LED color temperature may not exceed 3000K, luminaires may not be mounted more than 20 feet above the surface lit, and roof-mounted light poles are prohibited. Parking and traffic-way lighting must go off within 30 minutes after closing; after-hours safety lighting is limited to 25% of regular-hours fixtures, with specified dimming or motion-sensor options for continued overnight activity. 0.1 footcandle
The model requires a maximum fence height and a minimum screen height for substations, but leaves both heights blank for the municipality to determine. Fences shall not exceed
On-site substations must be on the side or rear of the principal building, screened from public view, and outside required front yards. On-site power lines of 34.5 kV or below must be buried. must be buried
Substations, generators, HVAC units, and other noise- or odor-producing equipment must, unless physically impossible, face away from abutting sensitive receptors and have screening. oriented away from abutting Sensitive Receptors
All site boundaries must have buffer yards and screening except at access points. Service areas must be screened from specified roads, sensitive receptors, and residential districts. Ground equipment must generally be fully screened and cannot be placed in a required setback; rooftop equipment must be screened under specified design rules. The model leaves the maximum rooftop-equipment share of the roof blank. buffer yards and screening along all property boundary lines
Enhanced buffers are required next to sensitive receptors or collector/arterial roads, with berm-height requirements left blank. For building footprints under 100,000 square feet, the specified buffer is 100 feet along public street frontage and qualifying nearby sensitive uses, and 50 feet along other nonresidential boundaries. For footprints of 100,000–250,000 square feet, those distances are 150 and 50 feet; above 250,000 square feet, they are 300 and 50 feet. minimum 300-foot buffer yard
The specified buffer must include trees and shrubs of stated numbers and minimum sizes, and plantings must provide a complete visual screen at least 12 feet high within three years. No impervious surface is allowed in the buffer except access drives, sidewalks, and associated improvements. within three (3) years
Before the conditional-use or special-exception hearing, applicants must provide an environmental and community impact analysis. It must address proposed operations and trips, site resources, regulated material disposal, effects on emergency services, utilities, schools, municipal finances and stormwater, likely environmental impacts and mitigation, specified air pollutants and prevention practices, and consistency with municipal and county comprehensive plans. environmental and community impact analysis
Applicants must coordinate with the municipal emergency-management coordinator on in-building emergency-radio coverage and install enhancement systems if needed. They must submit an emergency response plan for review by local fire and emergency services, covering response procedures, equipment and access adequacy, responder training, and annual professional fire-safety inspections. Emergency Response Plan
Each operation must post visible 24-hour emergency contact signage at its access entrance, including the company, owner or representative, and local power-company contact details. 24-hour emergency contact signage
Before occupancy, the owner must submit a decommissioning plan and provide financial security equal to 110% of estimated decommissioning costs minus salvageable value. The municipality may review the estimate every five years and adjust the security; the owner pays the review fees. 110% of the estimated decommissioning cost
Tree and woodland disturbance must be minimized. Trees, hedgerows, and tree masses at least six inches in diameter at breast height may be removed only when clearly necessary, and no more than 50% may be removed. no more than 50%
Applicants must provide a Pennsylvania Natural Heritage Program study dated within two years of the relevant application and comply with agency clearance measures for protected species and habitat. dated within two (2) years
Sites containing, alongside, or within 150 feet of specified waters must protect, convert, or establish a riparian forest buffer. The minimum is 100 feet on each side, with added width based on slope and an additional 25 feet beside specified wetlands or ponds. Earth disturbance, development, and material storage are prohibited in the buffer, which must be protected in perpetuity. minimum of 100 feet on each side
The definition of an accessory use excludes energy-generation systems used or intended to supply the data center during normal operations. shall not include energy generation systems
Benefits & exceptionsHide benefits & exceptions5
The definition of a Data Center accessory use includes supporting facilities such as backup generators, electrical substations, cooling equipment, water and wastewater facilities, and security structures. These can be located on the same tract or on adjacent parcels developed as a unified project; normal-operation energy generation is excluded.
Screened rooftop equipment may exceed the applicable zoning district’s maximum building height.
Noise limits allow sound to exceed the applicable standard by up to 10 dBA for a cumulative period of no more than one minute per hour.
Noise limits do not apply to emergency alerts or emergency work involving electricity, water, or other public utilities when public health or safety is involved, or to snow removal and road repair.
The noise limitations do not apply to a Sensitive Receptor established next to the Data Center after the facility receives its certificate of completion or occupancy.
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data