City of St. Marys
Slightly Anti-Data Center Policies
St. Marys requires data-center studies, utility checks, noise testing and setbacks, while separate power-plant rules may add hurdles for onsite generation without restricting data centers themselves.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
current law · City of St. MarysAllows electric power generation facilities in certain zones subject to environmental, noise, landscaping, emergency-access, and traffic requirements, but does not specifically regulate data centers.St. Marys Ordinance No. 348 (2026), electrical power-generation zoning amendment
What this means
This measure does not regulate data centers directly; it covers electric power generation facilities. It could add permitting and operating hurdles for a data center’s onsite power plant, including a 40 dBA property-line noise limit, but the sources do not show that it restricts building or operating data centers themselves.
People behind it
- Saint Marys City Council
The ordinance identifies the City Council as the body that ordained and enacted the measure; a news report says the council approved it.
Sources
current law · St. Marys CityMarys allows data centers only as a conditional use, approved by City Council, in the Industrial and Limited Industrial districts, with a 200-foot setback from residential zoning, a 60-foot height limit, three sound studies, and a requirement that the electric utility certify that local ratepayers will not bear upgrade costs.St. Marys City, Elk County — data-center ordinance (No. 347)
What this means
The measure imposes technical studies and utility checks, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements18
Industrial and Limited Industrial districts only, § 462.A
Zone noise limits apply (70 dBA in I and LI, § 318), § 462.F
Section 462.F requires a preliminary study in the conditional use process, an interim study at building permit, and an as-built study six months after occupancy, using ANSI S1.4 meters and generally accepted methodology.
Generator noise reported only; no testing limits, § 462.F
Vibration study showing none perceptible past the property line, § 462.F.
Water authority certification or feasibility study; no pump tests or cooling-well bar, § 462.G
Projected water demand disclosed; no cap or drought plan, § 462.G
Section 462.G requires the applicant to demonstrate that domestic, cooling, and industrial wastewater disposal has been provided and approved by the Sewage Enforcement Officer or DEP, with no stated timing.
Utility capacity certification before approval; no electrical inspection, § 462.H.
On-site generation is a separate use needing its own zoning approval, § 462.H.
Substations are accessory uses; nearby equipment enclosed or screened, § 462.E
Utility must certify no upgrade costs fall on ratepayers; cost-sharing agreement required, § 462.H.
25-ft native planted buffer, § 462.D
Equipment within 300 ft enclosed or screened; no height or acoustic standard, § 462.E
Plan accepted by fire department; no annual update, radio, or 24-hour contacts, § 462.I
Annual fire safety inspections; no electrical inspection, § 462.I
One as-built sound study after opening, § 462.F
As-built noise violation declared a violation of the ordinance; no specific penalties, § 462.F
Benefits & exceptionsHide benefits & exceptions1
Approval pathway: Conditional use in the Industrial and Limited Industrial districts
Sources
repealed · City of St. MarysRequires digital-currency-mining facilities—not data centers generally—to operate indoors, maintain 100-foot setbacks, meet a noise limit, and provide evidence they won’t harm local power or internet services.Ordinance No. ___ (2022), amending the City Zoning Ordinance to regulate Digital Currency Mining Facilities and Solar Energy Systems
What this means
The measure would add meaningful costs and hurdles for crypto-mining data centers: they must operate inside a building, meet a 100-foot setback, keep noise below the stated limit, and provide an engineer’s certification about effects on local electricity and internet services (requirements for digital currency mining). These rules apply only where mining is allowed by special exception, and the sources describe no incentives or protections for data centers.
People behind it
- Tom Wagner
City solicitor who drafted the zoning ordinance covering digital currency mining and solar energy systems.
- St. Marys City Council
Approved the proposed zoning ordinance for publication.
Restrictions & requirementsHide restrictions & requirements5
Digital currency mining requires special-exception approval where the zoning chapter allows it, adding a permitting requirement. “allowed by special exception”
All activities constituting digital currency mining must take place inside an enclosed building. “within an enclosed building”
The mining building must be at least 100 feet from any street or property boundary. “set back at least 100 feet”
Noise at the property boundary cannot exceed 65 dBA, or the lower applicable federal limit, measured over the relevant OSHA industrial-activity time period. “shall at no time exceed”
Applicants must provide professional-engineer-certified evidence that the proposed mining use will not adversely affect neighborhood or City electrical or digital internet services. “certified by a professional engineer”
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data