Borough of Springdale

Anti-Data Center Policies

Springdale borough’s data center has conditional-use approval and key zoning variances, but further plan changes, studies, and permits may add costs and delays before approval.

current law · Springdale Borough
Restricts data-center development by requiring borough approval and compliance with data-center-specific siting and operating rules.Springdale Borough conditional-use approval for proposed Springdale Data Center

What this means

The review requires many added plan revisions, engineering studies, and permits before approval, which could add meaningful cost and delay to the project (permits and approvals). But the project already has conditional-use approval and several key zoning variances, so the review creates hurdles rather than blocking the data center (Conditional Use Approval).

People behind it

  • Proposed the data center redevelopment and requested modifications to the subdivision and land development regulations.

Restrictions & requirementsHide restrictions & requirements13
  • The preliminary application cannot proceed to approval unless the review items are addressed to Springdale Borough’s satisfaction or made conditions of approval. The applicant must also demonstrate compliance with the conditions of its previously granted conditional-use approval. Review items must be addressed

  • The approved zoning relief still limits the project to buildings no higher than 60 feet, rooftop structures no higher than 75 feet, and fences no higher than 8 feet. Granted height and fence variances

  • Parking and driveway lighting must average at least two footcandles during operating hours, with lighting standards no more than 80 feet apart; the plan must show lighting extending at least to the property line. The facility must meet the zoning district’s noise limits, supported by an updated sound study. Lighting requirements Noise requirements

  • Garbage, trash, and rubbish must be kept in covered, vermin-proof containers and screened from public view; the dumpster enclosure must be shown on the plan if applicable. Waste-storage requirement

  • Development in the undeveloped 100-year floodplain should be avoided and must comply with applicable state and federal rules. A 50-foot setback from the top of a watercourse bank bars grading, vegetation removal, and other disturbance, subject to the stated limited allowance for minor work and required approvals. Floodplain and watercourse restrictions

  • The development may remove no more than 50% of mature woodland or 75% of total woodland on the site, and large, unique, or 24-inch-DBH-and-larger trees are subject to preservation and documentation requirements. Woodland limits

  • Disturbance on slopes of 15% or greater is subject to additional standards and analysis; slopes steeper than 2 horizontal to 1 vertical require a retaining wall designed and sealed by a registered professional engineer. Slope requirements

  • A contaminated site is considered safe for development only after a remediation plan is completed and approved by Pennsylvania DEP, with required remediation notes or details shown in the plans. Contaminated-site condition

  • Required permits and approvals must be obtained before final approval or recording, unless the recording plan specifies that they will be obtained before construction permits. The review specifically requires applicable floodplain and watercourse permits, NPDES approval before grading, sanitary-sewage approval and permits, and PennDOT approvals and highway occupancy permits for proposed street and driveway connections. Permit timing and requirements

  • The applicant must meet stormwater design and review requirements, including drainage and hydraulic analyses, approved and coordinated plans and models, and an operations-and-maintenance plan identifying long-term responsibility, maintenance schedules, estimated annual costs, and financing. Stormwater O&M requirements

  • The county ordinance generally requires a 10-foot minimum width for a single-purpose trail; the applicant has requested permission to use 8 feet. The requested modification is not stated as granted, and the review also requires PennDOT confirmation and county confirmation that the trail satisfies the applicable standard. Trail-width requirement and requested modification

  • Structures, vehicle-use areas, utilities, and light standards are generally prohibited in buffer yards. The applicant has requested a modification to place specified cemetery-accessible parking, lighting, and certain utilities in buffer-yard areas; the review does not say that the modification has been granted. Buffer-yard restriction and requested modification

  • Before final land-development approval, the applicant must provide a lot-consolidation plan. The review also requires resolution of traffic-study comments and a traffic-control plan meeting a conditional-use condition before final plan approval. Final-approval requirements

Benefits & exceptionsHide benefits & exceptions10
  • Conditional-use approval was granted for the redevelopment, subject to the applicant providing documents showing compliance with the decision’s conditions (Conditional Use Approval).

  • A variance allows buildings up to 60 feet tall, rather than the 45-foot zoning maximum (maximum building height of up to 60’).

  • A variance allows rooftop structures up to 75 feet tall (maximum rooftop structure height of up to 75’).

  • A variance permits smaller parking stalls: 9-by-18-foot standard stalls, 13-by-18-foot accessible stalls, and 16-by-18-foot accessible van stalls (parking stall size).

  • A variance reduces the minimum parking-aisle width from 25 feet to 24 feet (reduction in parking aisle width).

  • A variance reduces the required number of off-street loading spaces to four (reduction to four).

  • A variance allows fences up to 8 feet tall, instead of the 7-foot limit (maximum fence height of 8 feet).

  • The applicant requests permission to use an 8-foot trail width instead of the 10-foot minimum; the review says PennDOT must confirm the proposed trail is acceptable and the Department must confirm it meets the ordinance (minimum trail width of 10 feet). This is a requested modification, not an approval stated in the review.

  • The applicant requests permission to landscape the principal parking area only with low-growing vegetation to allow a solar canopy; the review does not state that this modification has been approved (low-growing vegetation).

  • The applicant requests permission to place cemetery-benefiting accessible parking, related lighting, and certain lights and utilities within required buffer yards; the review does not state that this modification has been approved (within the required buffer yard).

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data