Anti-Data Center Policies

Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.

Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for Borough of Spring City.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · Borough of Spring City
Expresses Spring City’s opposition to a neighboring data center proposal and asks the borough solicitor to explore zoning changes for future data center proposals within Spring City.Spring City data center zoning discussion / proposed rules

What this means

The resolution expresses Spring City’s opposition to a project in neighboring East Vincent and asks its solicitor to explore possible zoning changes; it does not itself restrict data-center construction or operation. The article notes the plans are before East Vincent, not Spring City.

Timing

Ends
after three years

The article describes a proposed bill to halt hyperscale data-center development for three years; it does not specify when the period would begin.

People behind it

  • Adopted a February resolution conveying the borough’s position to East Vincent Township and asking its solicitor to examine zoning changes; the article describes the resolution.

Sources

pending · Spring City borough
The borough posted proposed Ordinance No. 592 on its website on October 20, 2026 and listed it on the October 21, 2026 Planning Commission agenda, the outcome of that review has not been posted, and the next Borough Council meeting is November 2, 2026.Spring City, Chester County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements28
  • Section 525-48 area and bulk requirements stated as applying; no data center minimum, proposed § 525-54.D(3)(a)(i)

  • Section 525-49 height limits stated as applying, proposed § 525-54.D(3)(a)(ii)

  • Proposed Section 525-54.D(3)(a)(xi) requires 1,000 ft from any data center on another property, but the ordinance does not regulate a campus on commonly controlled lots as one use; the definition only counts equipment on adjacent parcels in a unified development.

  • 55 dBA from 7:00 a.m. to 7:00 p.m. and 50 dBA at night at the property line, proposed § 525-54.D(3)(h)

  • Proposed Section 525-54.D(3)(i) requires preliminary, interim, as-built, and annual noise studies using ANSI S1.4 meters, but the as-built and annual studies are not required at full operating load.

  • Non-emergency generator operation capped at 50 hours per year; no daytime limit, proposed § 525-54.D(3)(r)(iii)

  • Public water required with supply documentation and a hydrological study of private wells within 1,000 ft; no pump tests, proposed § 525-54.D(3)(m), (o), and (p)

  • Proposed Section 525-54.D(3)(a)(viii) requires a closed-loop liquid cooling system and bars air cooling as the primary system, but the definitions allow cooling towers and no water-use rate or noise showing is set for any evaporative system.

  • Raw water needs and quantity disclosed; no cap, reporting, or drought plan, proposed § 525-54.D(3)(o)

  • Cooling fluids and condensate must be removed off site and never discharged to sewer or stormwater; no approved discharge plan, proposed § 525-54.D(3)(a)(viii)

  • Cooling, fuel, and fire-fighting runoff kept out of stormwater facilities; no added stormwater standards, proposed § 525-54.D(3)(a)(viii)-(x)

  • Generators must meet state and federal air rules, with dispersion modeling above 1 MW; no EPA Tier 4, proposed § 525-54.D(3)(r)

  • Decommissioning removes electronic equipment, batteries, and generators, recycled or reused where practical; refrigerants not addressed, proposed § 525-54.D(3)(w)

  • Interconnection agreement confirming capacity with the application; no third-party electrical inspection, proposed § 525-54.D(3)(q).

  • On-site generation limited to temporary emergency use, proposed § 525-54.D(3)(l)

  • Battery systems must meet applicable fire, building, and electrical codes; NFPA 855 not named, proposed § 525-54.D(3)(a)(x)

  • Buffer yard with a berm and dense screen within the setback; width not stated, proposed § 525-54.D(3)(v)(iii)

  • Mechanical and electrical equipment screened with noise mitigation; no height standard, proposed § 525-54.D(3)(v)(ii)

  • Emergency Response Plan reviewed and approved by the Fire Chief or Fire Marshal; no annual updates, radio coverage, or posted contacts, proposed § 525-54.D(3)(b)

  • Proposed Section 525-54.D(3)(f) and (g) require the data center to provide annual firefighter training at its expense and to give specialized equipment to the fire company, but training is not required before occupancy and the equipment is not kept on site.

  • Secondary containment of 110% and an SPCC plan for fuel; no storage setbacks, proposed § 525-54.D(3)(a)(ix)

  • Fire safety maintenance and auditing plan considered; no inspection requirement, proposed § 525-54.D(3)(b)

  • Secondary emergency ingress and egress required; arterial or collector access not required, proposed § 525-54.D(3)(d)

  • 125% security of net decommissioning cost and removal within 6 months of end of useful life; security reduced by salvage value, proposed § 525-54.D(3)(w)

  • Estimate submitted at zoning permit and every fifth year; no first-year update, proposed § 525-54.D(3)(w)

  • Annual noise studies after occupancy, proposed § 525-54.D(3)(i)(iv)

  • Owner must remediate noise violations found by the borough; no specific penalties, proposed § 525-54.D(3)(i)

  • Applicant pays for its own noise studies; no municipal expert review, proposed § 525-54.D(3)(i)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: special exception in the I Industrial District