Anti-Data Center Policies

South Whitehall Township requires data centers to meet noise limits, undergo sound testing, maintain setbacks from homes and other protected places, and meet minimum site-size rules, increasing costs without barring approval.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · South Whitehall Township
The current rules are in Ordinance No. 1103, which the Board of Commissioners adopted on October 15, 2025.South Whitehall Township, Lehigh County — data-center ordinance (No. 1103)

What this means

The measure imposes noise limits and sound testing, setbacks from homes or other protected places and minimum site-size requirements. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements18
  • Permitted by right with an owner's opt-in consent under the PIRT Overlay; conditional use route has no expiration, § 350-33(g), § 350-24(c)(17), § 350-48(d)(2)

  • 350-ft principal structure setback from all non-industrial uses

  • 350-ft setback from all non-industrial uses, below 1,000 ft

  • 40-ft height in Industrial, 50-ft in PIRT; no rooftop equipment height cap found

  • Environmental evaluation of air, soil, water, groundwater, and habitat required

  • Single 24-hour average limit of 57 dB (residential) and 67 dB (industrial) in PIRT, § 350-33(g)(3)(A)

  • Pre-development noise level cap applies in Industrial district only; PIRT uses fixed limits

  • Low-frequency noise impact statement required in pre-construction noise study

  • Pre-construction noise study and post-construction monitoring plan; no building permit stage study

  • Generator testing weekdays 9 a.m. to 5 p.m., 25% of generators at once; no hours cap

  • Community and Environmental Impact Statement must address water supply

  • Community and Environmental Impact Statement must address sewage

  • 200-ft bermed buffer zone in Industrial district; PIRT buffer zone width not stated

  • Fixtures over 1,000 lumens fully shielded, 0.05 footcandle trespass limit, § 350-33(g)(2)(F)(v)

  • Ground equipment enclosed or screened on at least three sides by sound dampening walls

  • Impact statement covers emergency services; no emergency plan required

  • Post-construction noise monitoring plan required before approval

  • Only landowner consent required; developer, operator, and end user not required

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Industrial district only, by conditional use or by right through the PIRT Overlay opt-in

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data