South Shenango Township

Anti-Data Center Policies

Crawford County’s upcoming rules would impose major hurdles on new or expanded data centers where municipalities lack their own land-development ordinance.

Rating and summary from Crawford County as there are no scored current or future laws outside temporary restrictions for South Shenango Township.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

pending · South Shenango Township
The draft, which leaves the ordinance number blank, was provided on October 20, 2026, and the township secretary said it will most likely be on the agenda for the November 10, 2026 supervisors meeting.South Shenango Township, Crawford County — proposed data-center ordinance (None Adopted)

What this means

The proposal would impose setbacks from homes or other protected places, cooling and water-use rules and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.

Restrictions & requirementsHide restrictions & requirements25
  • Section 442.B sets Data Centers back 1,000 feet from residential districts and uses, and Section 202 defines the Data Center facility to include its air handlers, power generators, water cooling facilities, and substations.

  • 67 dBA weekday daytime and 57 dBA night and weekend at the property line, and 57 dBA at residential boundaries, § 442.H.1 and H.4

  • Section 442.H.1 requires preliminary, interim, and as-built sound studies using ANSI S1.4 meters, but the as-built study is not required to be taken at full operating load.

  • Testing limited to 9 a.m. to 3 p.m. weekdays and capped at 100 hours per year, § 442.K.5(iv)

  • Vibration study showing no vibration perceptible beyond the property line, § 442.H.3.

  • Water feasibility study for non-public sources; no well ban or pump tests, § 442.L.2

  • Closed-loop cooling required; evaporative cooling not expressly restricted, § 442.L.4

  • Anticipated raw water needs must be analyzed; no cap or reporting, § 442.L.2(i)

  • Section 442.L.3 requires the applicant to show that disposal of domestic, cooling, and industrial wastewater has been provided for and approved by the local sanitary authority and DEP, but the approvals are not required before the zoning permit.

  • Diesel generators must meet EPA Tier 4; no annual testing or reports, § 442.K.5

  • Heat rejection and cooling discharge must not cause thermal impacts on neighbors; no reuse review, § 442.J.4

  • Decommissioning plan covers disposal of hazardous and recycling materials; no specific server, battery, or refrigerant plan, § 442.N.1(a)

  • Electric provider must certify capacity and service; no third-party electrical inspection, § 442.K.1.

  • Energy generation supplying the data center is a separate use requiring a separate permit, § 442.K.3.

  • Battery storage must meet NFPA standards, § 442.I.3

  • Provider must certify the applicant will pay for its service so as not to affect rates; upgrade costs not expressly assigned, § 442.K.2

  • Fully shielded and directed away from adjacent properties; no property-line limit, § 442.E

  • Facades facing roads or homes must change material or height every 150 ft, § 442.G.

  • Mechanical equipment screened from public roads with sound-attenuating enclosures; no height standard, § 442.J

  • Emergency Response Plan accepted by the fire department; no annual updates, radio coverage, or posted contacts, § 442.I

  • Applicant must show traffic will not create hazards; no traffic study, § 442.F

  • Traffic bonding under other township ordinances; no work hours or haul routes, § 442.F

  • 110 percent security and 30 days notice, but removal may take up to 18 months after a one-year start, § 442.N

  • One as-built sound study after occupancy, § 442.H.1(iii)

  • As-built noise violation treated as a violation of the ordinance, § 442.H.1(iii)

Benefits & exceptionsHide benefits & exceptions1
  • Proposed approval pathway: Proposed: conditional use in the Heavy Industry districts

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data