Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for South Park Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · South Park TownshipThe September 11, 2026 draft was posted with the Planning Commission's October 28, 2026 agenda for a recommendation, and the Board of Supervisors had rescheduled its public hearing to November 9, 2026.South Park Township, Allegheny County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose money set aside for eventual removal, technical studies and utility checks and noise limits and sound testing. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.
Restrictions & requirementsHide restrictions & requirements29
Application narrative on effects on wells, streams, and wetlands; no riparian buffer, 137-131(A)(63)C(2)
Section 137-131(A)(63)C(3) requires a ten-year plan showing planned growth or expansion, but the plan does not state the electrical demand of each phase and no new approval is required for expansion.
LEQ of 65 dB outside Business Hours, 55 dB abutting a sensitive receptor; no daytime limit, Exhibit A Section 2(b)
Unweighted pure tone limits by octave band from 16 Hz; no dBC limit, Exhibit A Section 2(e) and Table 1. Version 2.0 gives full credit to octave-band limits at 31.5, 63, and 125 Hz, which the stated range of bands covers, so the limits earn 2 points.
Sound modeling study with the application, as-built study six months after occupancy, and annual studies; none at building permit, 137-131(A)(63)G(4)-(5)
Off-hours testing may exceed limits for up to 1 cumulative hour per 7 days; not limited to daytime, Exhibit A Section 3(e)
Vibration study showing none perceptible past the property line, with annual as-built studies, 137-131(A)(63)G(2) and (5).
Water feasibility study, with a hydrogeologic report and aquifer test for groundwater sources; wells not barred where public water is available, 137-131(A)(63)I(1)-(2)
Projected water demands disclosed in the feasibility study; no cap, reporting, or drought plan, 137-131(A)(63)I(1)(b)
Section 137-131(A)(63)I(1)(c) and (d) require the applicant to show that disposal of domestic and cooling or industrial wastewater has been provided and approved by the Sewage Enforcement Officer or PA DEP and bar on-site discharge, but they do not state that the approval must be in hand before the zoning permit.
Electronic Waste Plan for servers, batteries, hazardous materials, and electronic waste, updated annually; refrigerants not named, 137-131(A)(63)C(4)
Interconnection documentation before construction; no electrical inspection before occupancy, 137-131(A)(63)J(2)
Energy Usage Plan with the application; no on-site renewable requirement, 137-131(A)(63)J(1)
Known impacts on electric rates must be documented, 137-131(A)(63)J(2)
25-ft planted landscape buffer next to adjoining properties and sensitive receptors, 137-131(A)(63)E(1)
Shielded lighting with a 0.5 footcandle limit beyond the property line, 137-131(A)(63)H
Equipment fully enclosed or screened by buildings, buffer, or fence; no height or acoustic standard, 137-131(A)(63)F
Emergency Response Plan accepted by the fire department and a posted 24-hour contact sign; no annual updates or radio coverage, 137-131(A)(63)K(1) and (4)
Plan must ensure first responders receive system-specific training; no funding, 137-131(A)(63)K(1)(d)
Hazardous materials disposal addressed in the Electronic Waste Plan; no storage setbacks or containment, 137-131(A)(63)C(4)
Annual fire safety inspections; no electrical inspection before occupancy, 137-131(A)(63)K(1)(e)
Traffic impacts discussed in the narrative only; no traffic study, 137-131(A)(63)C(2)
Construction noise exempt only during Business Hours with noise controls; no haul routes or road bond, Exhibit A Section 3(f)
110% financial security, removal within 180 days after a 60-day start following a final abandonment determination; longer than 6 months, 137-131(A)(63)L
Decommissioning cost estimate and security updated every year, 137-131(A)(63)L(1)(c) and (e)
Annual as-built sound and vibration studies and regular energy and emissions reports, 137-131(A)(63)G(5) and J(1)(e)
Noise or vibration violation treated as a violation of the ordinance, 137-131(A)(63)G(2) and (4)(a)
Applicant pays for added studies; no township expert review, 137-131(A)(63)D
Sign must identify the person or entity controlling the data center; developer and end user not named, 137-131(A)(63)K(4)
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed conditional use in the I-1 and I-2 districts