South Middleton Township

Anti-Data Center Policies

South Middleton Township requires conditional-use approval in designated industrial districts, bars sites in a limited wellhead-protection overlay, and imposes water, noise, setback, and study requirements.

Incentives

Financial Incentive

Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.

current law · South Middleton Township
Restricts data centers to conditional approval in two industrial zones and requires safeguards for nearby residents, noise, water use, power, emergency response, and eventual cleanup.N/A — No enacted South Middleton data center-specific law or ban identified

What this means

The measure would allow data centers only by conditional use in I-2 and I-3 industrial districts, while barring them in the Wellhead Protection overlay (limited to I-2 and I-3). It also requires major buffers near sensitive uses and detailed studies and plans for water, noise, traffic, emergency response, and decommissioning, creating substantial cost and approval hurdles (water supply feasibility study). Because development remains possible in designated districts, this is a significant barrier rather than a ban.

People behind it

  • Approved the zoning amendments, including the data center regulations (approved zoning amendments).

Restrictions & requirementsHide restrictions & requirements17
  • Data centers and BESS are allowed only by conditional use in the I-2 and I-3 industrial districts and are prohibited in the Wellhead Protection District Overlay Zone; applicable underlying district regulations also remain in force. Conditional-use-only districts

  • Conditional use and land-development review are required. If a project does not require a land-development plan, such as a retrofit of an existing building, all applicable requirements must still be met during conditional-use review. all applicable requirements must be met

  • Minimum setbacks are 200 feet where the use abuts or is adjacent to a sensitive receptor; for other nonresidential neighbors, the minimum front setback is 75 feet and side and rear setbacks are 50 feet. Sensitive receptors include residential uses and places such as schools, daycares, health facilities, places of worship, parks, and playgrounds. 200-foot setback

  • A buffer is required along abutting property lines and adjoining sensitive receptors or public roads. Along a line shared with a sensitive receptor, it must be at least 200 feet deep and include a berm at least 10 feet high, with specified slope, planting, and screening requirements; a soundwall at least 20 feet high may substitute where natural features prevent a berm. 200-foot buffer yard

  • Lighting plans must show that illumination will not exceed zero foot-candles at any abutting lot or right-of-way line. Exterior fixtures are limited to 35 feet above adjacent grade and 20 feet above the surface being lit, must be shielded and directed inward and downward, and roof-mounted pole lighting is prohibited. zero foot-candles

  • Hazardous-material storage tanks must be at least 200 feet from any property. Storage must meet applicable Pennsylvania DEP standards and use spill-containment and environmental-protection measures; before land-development approval, the Township and first-due fire departments must be informed of potential hazardous materials and concerns addressed in the plan. 200-foot tank setback

  • A data-center conditional-use applicant must provide an electric-service-provider interconnection agreement showing necessary capacity is available and stating known project impacts on electricity rates or availability for other users. Diesel generators may be used only for emergency backup and must meet EPA Tier 4 emissions standards. interconnection agreement

  • Loading docks and truck-maneuvering areas must be at least 200 feet from property lines adjoining sensitive receptors. At least one loading space is required, and loading spaces may be located on only one façade of the principal data-center building. loading-area setbacks

  • Before land-development approval, the owner must submit an emergency-response plan for Township acceptance covering fire suppression, containment, ventilation, evacuation, emergency access, first-responder training, and annual fire-safety inspections by a qualified professional. Sites must comply with NFPA 855 or similar standards and include battery-specific fire suppression where applicable. emergency-response plan

  • Applicants must submit a traffic-impact study during conditional-use review addressing daily operations and emergency access and demonstrating that the facility will not adversely affect local road capacity. traffic-impact study

  • Public water and sewer must serve sanitary facilities. If public water is available, the applicant must provide a municipal-authority will-serve letter before conditional-use approval, and the data-center owner must pay for necessary increases in public-water distribution or capacity. Public water serving sanitary facilities cannot be used to augment the primary water source for processing capacity if another source is selected for equipment and heat-mitigation needs. The cooling system must be closed-loop, and required regulatory permits must be obtained before final approval. public-water requirements

  • A water-supply feasibility study is required before conditional-use approval if the project uses water resources, including public or private supplies; it must identify the cooling source and analyze water needs. If a private well is proposed, a licensed professional must prepare a water-resources impact study, the Township must approve test-well locations and the work plan, and specified well installation, pumping tests, monitoring, and analyses are required. A supply that is inadequate, fails applicable drinking-water standards, or adversely affects nearby wells, ponds, or streams cannot be approved. water-supply feasibility study

  • A thermal-impact mitigation plan, certified by a professional engineer, must be submitted before conditional-use approval. It must assess heat sources and off-site impacts, explain mitigation and feasible waste-heat reuse (or why reuse is infeasible), and may need a monitoring plan. thermal-impact mitigation plan

  • A qualified professional must provide a sound study before conditional-use approval demonstrating compliance at the property line with limits of 55 dB(A) and 60 dB(C) during daytime hours (7 a.m.–8 p.m. weekdays) and 45 dB(A) and 50 dB(C) at night (8 p.m.–7 a.m. weekdays and all day weekends). A baseline and modeling study is required before construction; an as-built study is required six months after occupancy, and further studies or mitigation may be required. Weekday generator testing is excepted from the ordinary limits only up to 70 dB(A) and 80 dB(C), for no more than three hours per day and once per week. noise limits and studies

  • Before conditional-use approval, a qualified professional must provide a vibration/electromagnetic study demonstrating that no electromagnetic waves from the proposed use will extend beyond a property line. vibration/electromagnetic study

  • Before conditional-use approval, the applicant must analyze wastewater disposal needs and expected quantities. Private disposal requires approval by the Sewage Enforcement Officer and/or DEP and must avoid adverse impacts on surrounding waters; public conveyance or treatment requires municipal-authority documentation of capacity. Chemical treatment requires on-site pretreatment and continuous monitoring before discharge to the public system, and untreated wastewater may not be discharged to stormwater systems or surface waters. wastewater requirements

  • At closure, the owner or operator must notify the Township and decommission within 12 months. A decommissioning plan and Township agreement are required, and financial security must cover the estimated decommissioning cost, be updated every five years, and remain in effect; failure to maintain security is a zoning violation and may lead to operations being halted. 12-month decommissioning deadline

Benefits & exceptionsHide benefits & exceptions5
  • Data centers and BESS may seek conditional-use approval in the I-2 and I-3 districts, but are prohibited in the Wellhead Protection Overlay Zone. This gives them a specified approval route in those industrial districts, subject to the ordinance’s conditions. Conditional use only in I-2 and I-3

  • For a retrofit of an existing building that does not require a land development plan, the applicable requirements may be addressed during the conditional-use phase rather than through a land-development submission. all applicable requirements must be met during the conditional use phase

  • The ordinance recognizes a range of data-center accessory facilities—including emergency generators, electrical substations, utility lines, cooling and water facilities, and security structures—as part of the use when located on the same tract or adjacent parcels developed as a unified project. The definition excludes energy generation intended to supply normal operations. Data Center Accessory Use

  • A data center may use diesel generators for emergency backup power, subject to Tier 4 emissions standards; generators may also operate when utility power fails, subject to the ordinance’s noise provisions. They cannot be used to increase processing capacity or for normal operations. emergency backup power

  • The ordinance provides for utility connections: applicants must submit an electric-service-provider interconnection agreement showing that the needed capacity is available; public water must serve the project if available, and public water and sewer must serve sanitary facilities. The data-center owner bears the cost of water-system capacity or distribution improvements needed for the project. interconnection agreement

Sources

current law · South Middleton Township
The rules are in Ordinance 2026-03, which the Board of Supervisors adopted on July 30, 2026, and township staff told the Board on September 24, 2026 that a draft follow-up amendment would be ready for review by late October 2026, with adoption targeted for late January 2027.South Middleton Township, Cumberland County — data-center ordinance (No. 2026-03)

What this means

The measure imposes cooling and water-use rules, noise limits and sound testing and setbacks from homes or other protected places. Data centers can still be approved, but these obligations meaningfully increase construction, compliance or review costs.

Restrictions & requirementsHide restrictions & requirements30
  • Conditional use, § 1658.2; no approval expiration

  • Underlying district regulations, including height, stated as applying, § 1658.3

  • Barred from the Wellhead Protection Overlay, with a water resources impact study for wells; no riparian buffer, § 1658.2.b and 3.n

  • 55 dBA day and 45 dBA night at the property line, § 1658.3.o

  • Where baseline ambient exceeds the limits, sound may not exceed the baseline; no 10 dBA cap, § 1658.3.o(i)(b)

  • 60 dBC day and 50 dBC night at the property line, § 1658.3.o

  • Pre-construction study with the conditional use application and as-built study six months after occupancy; none at building permit, § 1658.3.o

  • Section 1658.3.o(iv)(a) allows generator testing only on weekdays in daytime hours, for at most three hours per day and once per week, with no allowance for longer tests required by code.

  • Vibration and electromagnetic study before approval; no vibration standard, § 1658.3.p

  • Public water required where available, and any groundwater use for cooling requires a hydrogeologic study with pump tests, § 1658.3.m and n

  • Section 1658.3.m(v) requires the heat mitigation cooling system to be closed loop and Section 1658.3.n requires the cooling source and water needs to be disclosed, but evaporative systems are not barred or limited to a stated water-use rate and shown to meet the noise limits.

  • Water needs usage analysis disclosed; no cap, reporting, or drought plan, § 1658.3.n

  • Wastewater analysis and authority certification before conditional use approval, with pretreatment and monitoring of chemically treated cooling water, § 1658.3.q

  • Diesel generators must meet EPA Tier 4; no emissions testing, § 1658.3.g

  • Thermal impact mitigation plan with evaluation of waste heat reuse, § 1658.3.l.

  • Decommissioning plan for removal and recycling of servers, batteries, e-waste, and hazardous materials, § 1658.3.r.

  • Interconnection agreement confirming capacity; no electrical inspection, § 1658.3.g.

  • Electric rate impacts disclosed and public water upgrade costs borne by the owner; grid upgrade costs not assigned, § 1658.3.g and m

  • 200-ft buffer yard with a 10-ft planted berm next to sensitive receptors, § 1658.3.c.

  • Principal facades must use at least two specific design elements, § 1658.3.b.

  • Screening along all property lines with berms or 20-ft soundwalls; no equipment screening standard, § 1658.3.c

  • Emergency response plan accepted by the Township with annual inspections; no fire company review, radio coverage, or contact signs, § 1658.3.i

  • Plan must ensure first responders are trained; cost not assigned, § 1658.3.i

  • Annual fire safety inspections, § 1658.3.i

  • Section 1658.3.j(i) requires a traffic impact study during the conditional use process addressing daily operational traffic and emergency response access.

  • Construction noise limited to daytime hours; no haul routes or road bond, § 1658.3.o(iv)(g)

  • Closure notice, removal within 12 months, and security of at least 100% of cost; not 110% or 6 months, § 1658.3.r

  • One as-built sound study, with later studies on Township request, § 1658.3.o

  • Township may stop operation if decommissioning security lapses, § 1658.3.r.

  • Section 1658.3.o(i) requires the sound study to be reviewed by a noise professional selected by the Township, without assigning the review cost, and Section 1658.3.o(v) allows a Township-selected post-occupancy study at the owner's expense.

Benefits & exceptionsHide benefits & exceptions1
  • Approval pathway: Conditional use in the I-2 and I-3 districts

Sources

Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data