South Coventry Township
Anti-Data Center Policies
Pennsylvania requires data centers over 25 megawatts to obtain local approvals and meet power, grid-cost, environmental, and community commitments; covered facilities also face annual energy and water reporting. These rules make large projects harder, not impossible, while eligible centers may receive equipment tax breaks.
Rating and summary from Pennsylvania statewide as there are no scored current or future laws outside temporary restrictions for South Coventry Township.
Incentives
Financial Incentive
Financial incentives not assessed from full ordinance text in this tracker import; an empty list is not a confirmed finding that no incentive exists.
pending · South Coventry TownshipRestricts data centers to conditional-use approval in South Coventry’s rural-conservation district and sets requirements for their location, size, water and energy use, noise, safety, and eventual closure.N/A — no South Coventry data-center-specific regulation identified
What this means
The draft would allow data centers only by conditional use in the rural-conservation district, with requirements such as a 50-acre minimum and 1,000-foot buffers. It also requires air-cooled or closed-loop cooling and extensive studies and plans, creating significant hurdles and costs for approval and operation. (http://southcoventry.org/wp-content/uploads/2026/10/2026-10-19-South-Coventry-Data-Center-Ordinance-DRAFT-CCPC-Revised.pdf#:~:text=designed%20to%20use%20air-cooled%20or%20closed-loop%20water%20circulation%20systems)
Restrictions & requirementsHide restrictions & requirements27
Would allow data centers only in the RC Rural Conservation District and only by conditional use, requiring conditional-use approval in addition to other applicable approvals. permitted by conditional use in the RC – Rural Conservation District
Would require a tract of at least 50 gross acres, limit each data-center building to 250,000 square feet and 35 feet in height, and limit density to one data center per 25 gross acres. minimum lot size
Would impose setbacks: data-center buildings and accessory structures at least 500 feet from property lines, substations at least 1,000 feet from property lines and in rear yards, and loading docks and truck maneuvering areas in side or rear yards. No Data Center buildings or Data Center accessory structure shall be less than 500 feet
Would bar data-center buildings and accessory uses within 1,000 feet of residential zoning, a property with an existing residence, a school, cemetery, or licensed daycare; distance is measured from the nearest data-center component to the relevant boundary or lot line. No Data Center building or Data Center Accessory Use shall be located within 1,000 feet
Would prohibit locating a data center within 1,000 feet of another data center on a different property in the township. within 1,000 feet of another Data Center
Would require compliance with the RC district’s area and bulk rules, with whichever rule is more restrictive controlling. the provision imposing the greater restriction or higher standard shall govern
Would require evidence from each serving public utility that service is feasible, plus a professionally prepared electric grid-impact evaluation addressing demand, capacity, upgrades, reliability effects, and mitigation. submit a grid-impact evaluation
Would require a preliminary land-development plan and a master plan for the entire tract with the conditional-use application; later phases must substantially conform unless amended conditional-use approval is obtained. A preliminary land development plan and a master plan
Would require screening of mechanical equipment, specified facade and rural-design features, visual simulations and view analysis, screened fencing without barbed or razor wire, and a main entrance feature. Screening, Facades and Design Requirements
Would require a pre-construction noise and vibration study with the application and a post-construction study within 180 days after occupancy certification and commencement of operations; studies must assume concurrent maximum-rated operation of noise-producing equipment. post-construction noise and vibration study
Would impose noise limits by receiving land use and time of day, including residential limits of 55 dBA daytime and 45 dBA nighttime, plus low-frequency noise limits and vibration criteria. Exceedances or a material increase of at least 3 dBA above baseline could constitute violations. Residential 55 dBA Leq (1-hour)
Would allow the township to require further noise and vibration testing after substantiated complaints or specified equipment changes, and interim operational limits or temporary curtailment if monitoring or complaints indicate a probable violation. Noncompliance requires a corrective-action plan within 30 days and remediation generally within 90 days of notice. temporary curtailment of specific noise producing activities
Would require detailed water-use estimates and a sealed water-supply feasibility study; approval would require demonstrating no adverse effects on other users or water resources. No Data Center shall be approved unless the study demonstrates
Would prohibit private groundwater wells or direct surface-water withdrawals as the primary cooling or equipment-operation water source, and require air-cooled or closed-loop cooling. An alternative system would require a professional showing that it uses less water and energy than closed-loop cooling and township approval. designed to use air-cooled or closed-loop water circulation systems
Would require a sealed thermal-impact mitigation plan, permits before any cooling-water discharge, and a drought-response plan. submit a Thermal Impact Mitigation Plan
Would require wastewater analysis and documentation of public-system capacity or, for a private system, a sealed feasibility study; untreated wastewater could not be discharged to stormwater systems, groundwater, or surface water. Untreated wastewater generated by the Data Center shall not be discharged
Would require an energy-usage plan covering demand, energy sources, backup power, efficiency and clean-energy efforts, and—if grid-connected—documentation of the interconnection application, transmission security agreement, and proposed energization date. It would also require a demand-management and curtailment plan. provide with the conditional use application an energy usage plan
Would require diesel backup generators to meet EPA Tier 4 standards and undergo annual testing with reports to the township. Fossil-fuel emergency generation would be limited to emergency outages and maintenance/readiness testing capped at 100 hours per year; testing would be restricted to weekdays from 10 a.m. to 4 p.m.; peak shaving and grid supply would be prohibited. capped at 100 hours per year
Would require advance public website notice and township notice at least 24 hours before generator testing. announced on the website at least 24 hours in advance
Would treat on-site generation used during normal operations as a separate principal use, not an accessory use, requiring zoning authorization and applicable land-development, state, and federal approvals. treated as a separate principal use
Would require an emergency response plan reviewed and accepted by the fire department, EMS, and township emergency management coordinator; annual fire-safety inspections; and payment of necessary specialized first-responder training costs. responsible for all costs for specialized training
Would impose additional requirements for battery or other energy storage, including NFPA 855 or similar standards, purpose-designed fire suppression, emergency-team review and approval, specified monitoring and containment features, and township review of later upgrades or changes. demonstrate compliance with National Fire Protection Association
Would require an engineered system to contain contaminated firefighting water and hazardous substances, with documented capacity for the maximum anticipated volume and emergency-handling procedures. engineered collection and containment system
Would require a township-approved construction-vehicle plan as part of final land-development approval, with the township able to demand added detail and updates as construction progresses. approved by the Township as part of final land development plan approval
Would require a decommissioning plan with the conditional-use application; decommissioning must begin within one year after operations cease or abandonment is noticed and finish within 18 months after that. One extension of up to one year may be granted if actively marketed for compatible reuse; the township may require financial security for decommissioning and restoration. shall be completed within 18 months thereafter
Would require a community and environmental impact statement with the conditional-use application, covering operational activities and potential effects on services, municipal finances, and specified environmental resources. provide a community and environmental impact statement
Would require one parking space per two employees on the two largest shifts combined, plus one space for each vehicle stored on site. one parking space per two employees
Benefits & exceptionsHide benefits & exceptions4
Data centers are authorized in the RC – Rural Conservation District through conditional use approval, subject to the ordinance’s standards. permitted by conditional use
The ordinance recognizes utilities, substations, pump stations, backup power supplies, and other listed facilities as data-center accessory uses when they are on the same tract or unified adjacent parcels. Normal-operation on-site energy generation is excluded and must be authorized separately. Data Center Accessory Uses
Applicants may submit a master plan covering ultimate buildout and anticipated phases, providing for phased development under the conditional-use approval. Each phase must substantially conform to that plan unless amended conditional-use approval is obtained. proposed ultimate buildout and all anticipated phases
Emergency fossil-fuel generators may operate when the primary energy source is unavailable because of an emergency outage, and for routine maintenance or readiness testing subject to the ordinance’s time and annual-hour limits. Peak shaving and supplying power to the grid are prohibited. When the primary source of energy is not available due to an emergency outage
Sources
pending · South Coventry TownshipThe draft has no ordinance number yet and is dated October 19, 2026, following Chester County Planning Commission review on August 24, 2026, and the Board of Supervisors will review it on November 2, 2026 and consider authorizing a public hearing, which would be held in December.South Coventry Township, Chester County — proposed data-center ordinance (None Adopted)
What this means
The proposal would impose setbacks from homes or other protected places, minimum site-size requirements and noise limits and sound testing. Data centers still have an approval route, but the siting or operating limits significantly narrow feasible projects.
Restrictions & requirementsHide restrictions & requirements32
Allowed in the RC Rural Conservation District; no farmland or agricultural security area bar
Section 1645.A(6) bars any Data Center building or accessory use within 1,000 feet of a residential district or a lot with an existing residential use, measured from the nearest exterior wall, equipment pad, or other component of the use.
35-ft height limit; rooftop equipment set back from the parapet but not capped, § 1645.A(3) and D(1)
Community and environmental impact statement covering air, soil, water, groundwater, and wildlife habitat, § 1645.K
Section 1645.A(1) treats a lot or assemblage of adjacent parcels owned in common or developed as a unified development as one Data Center Tract for the area and bulk rules, and Section 1645.A(7) requires 1,000 feet between data centers on different properties.
Master plan of all phases required; phases that depart from it need amended conditional use approval, § 1645.C
55 dBA day and 45 dBA night at residential property lines; daytime limit above 50 dBA, § 1645.E Table 2
Section 1645.E Table 6 makes an increase of 3 dBA or more above the baseline ambient level a violation, and Table 5 documents the baseline before construction with a Type 1 or Type 2 meter, but the baseline is not an L90 measure and no floor is stated below which the cap does not apply.
70 dBC day and 60 dBC night, above the 60 and 55 dBC standard, § 1645.E Table 3
Pre-construction study with the application and as-built study within 180 days; none at building permit, § 1645.E(1) and (3)
Numeric vibration limits of 65 VdB and PPV in the studies; not a no-perceptible-vibration standard, § 1645.E(3)(f)
Air-cooled or closed-loop cooling required; alternatives only if they use less water and energy, § 1645.F(4).
Projected water use and a drought response plan; no use cap or ongoing reporting, § 1645.F(1) and (6)
Wastewater analysis including cooling and HVAC discharge; untreated discharge prohibited, § 1645.G
EPA Tier 4 diesel generators with annual testing reports to the Township, § 1645.H(2)(a)-(b)
Thermal Impact Mitigation Plan including heat recovery or reuse, § 1645.F(5).
Decommissioning plan covers removal and recycling of equipment, batteries, refrigerants, and electronic waste, § 1645.J(2).
Utility evidence that service is feasible and a grid-impact evaluation; no electrical inspection, § 1645.B.
Energy usage plan required; renewable use documented but not required, § 1645.H(1)
On-site generation for normal operations is a separate principal use with its own approvals, § 1645.H(3).
Substations in the rear yard and 1,000 ft from property lines, and accessory equipment screened; no buried-line rule, § 1645.A(4) and D(1)
Grid-impact evaluation must identify required system upgrades; cost not assigned, § 1645.B
80 percent single-material limit, facade articulation, and rural roof and color standards, § 1645.D(2)
Ground and rooftop equipment screened on all sides; no 12-ft or acoustic screening standard, § 1645.D(1)
Emergency response plan accepted by the fire department; no annual updates, radio coverage, or posted contacts, § 1645.I(1)
Engineered containment for contaminated firefighting water and hazardous substances; no storage setbacks, § 1645.I(4)
Annual fire safety inspections; no third-party electrical inspection, § 1645.I(1)(e)
Construction plan sets access times and locations for construction vehicles; no road damage bond, § 1645.J(1)
Decommissioning plan, closure notice, and completion within 18 months; security only at Township option, § 1645.J(2)
One as-built noise and vibration study after opening, § 1645.E(3)
Corrective action plan, 90-day remediation, and interim curtailment; no penalties or revocation, § 1645.E(4) and (8)
Generator testing website only; no community meeting or project website
Benefits & exceptionsHide benefits & exceptions1
Proposed approval pathway: Proposed: conditional use in the RC Rural Conservation District
Sources
Thank you to the Pennsylvania Data Center Ordinance Tracker for providing proposed local ordinance data for PA. Citation: padatacenterordinances.org, accessed November 3, 2026.Cookie preferences · Report missing data