South Annville Township

Anti-Data Center Policies

South Annville Township requires data center projects to submit a decommissioning plan and community benefits agreement, adding work and potential costs. It did not adopt the proposed 1,000-foot residential setback, and the full burden is unclear.

current law · South Annville Township
South Annville Township, Lebanon County, unanimously approved Ordinance #10-14-26 on October 14, 2026, regulating data centers through zoning.South Annville Township Ordinance No. 10-14-26 (2026)

What this means

The zoning ordinance adds requirements, including a decommissioning plan and community benefits agreement, which mean extra work and potential costs for data center projects (those requirements). The source says the township did not adopt the proposed 1,000-foot residential setback, so the available evidence suggests meaningful but not severe barriers; it does not give enough ordinance details to estimate the full burden.

Timing

Ends
unknown

Reported as a zoning ordinance regulating data centers, not a moratorium. Enacted text was not retrieved; any sunset or temporary provisions remain unknown. Source: adoption reporting.

Restrictions & requirementsHide restrictions & requirements2
  • Data center proposals must include a decommissioning plan. The source does not specify its required contents or timing. The ordinance added a decommissioning plan

  • Data center proposals must include a community benefits agreement. The source does not specify its terms. The ordinance added a community benefits agreement